Salt Lake City v. O'Connor

249 P. 810, 68 Utah 233, 49 A.L.R. 941, 1926 Utah LEXIS 94
CourtUtah Supreme Court
DecidedJune 1, 1926
DocketNo. 4326.
StatusPublished
Cited by29 cases

This text of 249 P. 810 (Salt Lake City v. O'Connor) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Salt Lake City v. O'Connor, 249 P. 810, 68 Utah 233, 49 A.L.R. 941, 1926 Utah LEXIS 94 (Utah 1926).

Opinion

CHERRY, J.

This action arises out of a contract for certain public work in Salt Lake City, and involves the determination of certain claims of materialmen against the surety upon the bond of the contractor, and the distribution of the remainder due and unpaid upon the contract price. On October 23, 1922, John O’Connor (hereinafter called the contractor) entered into a contract with Salt Lake City for the construction of sewer extension 410, and pursuant to Comp. Laws *235 Utah 1917, § 3753, executed and delivered a bond in the sum of $31,000, conditioned for the faithful performance of his contract and the prompt payment for all labor and materials used in the work. National Surety Company (hereinafter called the surety) was the sole surety on the bond. Utah Fire Clay Company and Utah Lumber Company (hereinafter called materialmen) furnished materials which were used in the work, and Utah Savings & Trust Company (hereinafter called the bank) lent money to the contractor, secured by an assignment of all sums to become due on the contract.

The work was completed on June 9, 1924, at which time there remained due and unpaid upon the contract from the city the total sum of $8,714.90, of which amount $7,400 was, under the contract, payable in certain bonds. The contractor had disappeared. There was due and unpaid to the material-men the sums of $19,681.83 and $2,207.21, respectively, and to the bank, on account of money loaned, the sum of $3,000. Conflicting claims to the unpaid portion of the contract price were made, whereupon the city brought this action, implead-ing- the claimants above named, and prayed that they be required to set forth their respective claims, and the same be determined; that the city be permitted to pay into court the said sum due on the contract and be discharged, etc. The liability of the surety to the unpaid materialmen arose out of the controversy and became a part of the action.

By appropriate pleadings the claims of the respective parties were asserted and issues joined thereon. Two main controversies arose. As between the surety and the material-men it was alleged and proved that the contractor had paid to the materialmen the sums of $5,650.96 and $252.83, respectively, at divers dates in February and May, 1923, with funds derived from the proceeds of bonds paid and delivered to him on account of the contract in question, which payments were applied by said materialmen upon pre-exist-ing debts, arising out of a prior and independent transaction, *236 not secured by the bond involved in this action. The surety herein contended that the application of payments thus made could not be sustained, but that such payments must be applied in reduction of the claims of the materialmen for which it, the surety herein, was liable.

The other question involved the disposition of the remainder of the contract price, as between the bank, under its assignment, and the surety, who claimed an equitable right thereto superior to the assignee. Both questions were decided by the trial court adversely to the surety, and judgments were entered in favor of the materialmen against the surety for the full amount of their claims, and in favor of the bank that it had a lien and claim upon the unpaid contract price, superior to any claim of the surety. The surety has appealed.

With respect to the question of the application of the payments made to the materialmen, it was undisputed that the respective debts upon which the payments were applied were for balances due for materials furnished to the contractor for use in a similar, but prior, contract with Salt Lake City for sewer extension 357, which work had been completed shortly before the work on the contract in question had begun. The bond in connection with the contract for sewer extension 357 was executed by a surety company other than the surety herein. It was represented that the recourse of the materialmen upon this bond had expired by lapse of time when the controversy arose with the surety herein. The payments in question were made shortly after the work on the first contract had been completed and the work on the second had begun. The fact that final payment of the amount due on the first contract was made to the contractor by the city on September' 23, 1922, was proved at the trial, but it was not claimed that the materialmen knew of this fact at the time.

As indicating the commingling or overlapping of the two transactions, however, it was shown that the contractor paid *237 out on the last contract about $19,000 before receiving any payment on account thereof from the city. These advance payments were made by checks upon the contractor’s general bank account, in which were deposited money from various sources, including payments received on account of the first contract. The trial court found as facts that the material-men, at the time the payments were made, had no knowledge of the source of the money paid to them, and that the contractor directed that the payments be applied upon the pre-existing indebtedness, to which it applied. These findings are assailed by appellant as being insufficiently supported by the evidence. There were circumstances testified to tending to indicate that the materialmen ought to have known or did know the source of the money paid them, but their positive evidence to the contrary, and other circumstances in the matter, furnish a sufficient basis for the finding of the trial court. There was satisfactory evidence that the contractor directed the application of payments as made. The findings must therefore stand.

The question is thus reduced to whether, in such circumstances, the application of payments so made by the parties1 is valid as against the surety on the bond, or whether the surety, when sued upon the bond, may require that such payments be applied on the particular indebtedness for which it is liable. There is a conflict of law upon the subject.

The appellant surety insists upon its legal right to have the payments applied in reduction of the indebtedness for which it is liable, upon the grounds that it has a special equity in the proceeds of the contract secured by its bond, and that, if not so applied, the net effect is to hold it liable for indebtedness not included in its contract. The authorities cited and relied on by appellant are: (1892) Crane Co. v. Keck, 35 Neb. 683, 53 N. W. 606; (1896) Young v. Swan, 100 Iowa, 326, 69 N. W. 566; (1897) Merchants’ Ins. Co. v. Herber, 68 Minn. 420, 71 N. W. 624; (1898) United States v. Am. Bonding & T. Co., 89 F. 925, 32 C. C. A. 420; (1904) *238 Crane Co. v. Pac. H. & P. Co., 36 Wash. 95, 78 P. 460; (1904) First Nat. Bank v. Nat. Surety Co., 130 F. 401, 64 C. C. A. 601, 66 L. R. A. 777; (1914) Columbia Digger Co. v. Rector (D. C.) 215 F. 618; (1915) Columbia Digger Co. v. Sparks, 227 F. 780,142 C. C. A. 304; (1916) Sioux City F. & M. Co. v. Merten, 174 Iowa, 332, 156 N. W. 367, L. R. A. 1916D, 1247; (1921) Alexander Lbr. Co. v. Aetna Acc. & L. Co., 296 Ill. 500, 129 N. E. 871.

Most of these cases are distinguishable from the case under review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jorgensen v. Aetna Casualty & Surety Co.
769 P.2d 809 (Utah Supreme Court, 1988)
UHL Construction v. Fidelity & Deposit Co. of Maryland
538 A.2d 562 (Superior Court of Pennsylvania, 1988)
Uhl Const. v. FID. & DEP. CO. OF MD.
538 A.2d 562 (Supreme Court of Pennsylvania, 1988)
Geneva Pipe Co. v. S & H Insurance Co.
714 P.2d 648 (Utah Supreme Court, 1986)
Templeton v. Sam Klain & Son, Inc.
425 N.E.2d 89 (Indiana Supreme Court, 1981)
Templeton v. Sam Klain & Son, Inc.
400 N.E.2d 1198 (Indiana Court of Appeals, 1980)
State Bank of Downs v. Moss
454 P.2d 554 (Supreme Court of Kansas, 1969)
Davis County Board of Education v. Underwood
349 P.2d 722 (Utah Supreme Court, 1960)
National Surety Corporation v. Fisher
317 S.W.2d 334 (Supreme Court of Missouri, 1958)
Fausett Builders, Inc. v. Globe Indemnity Co.
247 S.W.2d 469 (Supreme Court of Arkansas, 1952)
Koblegard Co. v. Maxwell
34 S.E.2d 116 (West Virginia Supreme Court, 1945)
Western & Southern Indemnity Co. v. Cramer
10 N.E.2d 440 (Indiana Court of Appeals, 1937)
State Bank of Wheatland v. Turpen
34 P.2d 1 (Wyoming Supreme Court, 1934)
Metropolitan Casualty Ins. v. United Brick & Tile Co.
1934 OK 14 (Supreme Court of Oklahoma, 1934)
United States v. Johnson, Smathers & Rollins
67 F.2d 121 (Fourth Circuit, 1933)
Detroit Fidelity & Surety Co. v. Keys
14 Ohio Law. Abs. 76 (Ohio Court of Appeals, 1932)
United States Fidelity & Guaranty Co. v. Butcher
137 So. 446 (Supreme Court of Alabama, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
249 P. 810, 68 Utah 233, 49 A.L.R. 941, 1926 Utah LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/salt-lake-city-v-oconnor-utah-1926.