United States Ex Rel. Belmont v. Mittry Bros. Const. Co.

4 F. Supp. 216, 1933 U.S. Dist. LEXIS 1464
CourtDistrict Court, D. Idaho
DecidedJune 20, 1933
Docket1690, 1722
StatusPublished
Cited by10 cases

This text of 4 F. Supp. 216 (United States Ex Rel. Belmont v. Mittry Bros. Const. Co.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Belmont v. Mittry Bros. Const. Co., 4 F. Supp. 216, 1933 U.S. Dist. LEXIS 1464 (D. Idaho 1933).

Opinion

CAVANAH, District Judge.

These eases were consolidated for trial as they were brought by the United States for the benefit of persons who furnished labor and materials against Mittry Bros. Construction Company and the Fidelity & Deposit Company of Maryland in case No. 1690, and against Wiliam Harkins, Mittry Bros. Construction Company, and the Fidelity & Deposit Company in ease No. 1722. They were tried and argued together, and may well be disposed of by the same opinion.

In case No. 1690 about October 1, 1929, Mittry Bros. Construction Company entered into a contract with the United States for the construction of the Millner Canal diverting water from Snake river. The work is known as “The Gravity Extension of the Minidoka Reclamation Project.” The Fidelity & Deposit Company executed, under the act of Congress (40 USCA § 270), the standard government form of performance bond. The Twin Falls North Side Investment Company has intervened and seeks to recover for hay sold and on a number of assigned claims for labor and material used in the prosecution of the work. About July 1, 1930, William Harkins entered into a subcontract with Mittry Bros. Construction Company for the construction of a section of the canal across a depression requiring dirt to be hauled in, and which was situate a considerable distance from any town where adequate boarding facilities could be had for the men. Camp No. 2 was established where the men and horses employed were eared for and fed, and groceries for the camp were furnished from Longinberger & Belmont at Hazelton-

*218 In ease No. 1722, the situation is practically identical with ease No. 1690, except as to the different part of the canal that was under construction. The contract there between Mittry Bros. Construction Company and the United States was entered into on May 27, 1929, and the bond given by the Fidelity & Deposit Company to secure performance of the contract was on June 1,1929. A number intervened seeking to recover for labor and materials furnished and used in the prosecution of the work which was carried on at camp No. 1. The work performed in that case was completed first, and then the same employees and horses used there were moved down on camp No. 2 and continued the work covered by the contract referred to in ease No. 1690.

The defendants contend:

(a) In ease No. 1722 the suit was not timely brought.

(b) If plaintiff and interveners are entitled to recover, they are only entitled to interest on their claims from date of suit.

(c) Materials and supplies furnished by claimants and used in the boarding house maintained by the subcontractor Harkins are not recoverable under the bond. '

(d) Payments made by subcontractor Harkins must be applied to those claims covered by the bond.

(e) Only those who furnished labor and material that went into the construction covered by the bond come within the benefit of the act.

These contentions will be disposed of in their order.

A. Case No. 1722 was commenced on February 26, 1932, and the complaints in intervention were filed on March 5, 1932. There was one contract and bond covering all of the work, whieh was completed and finally settled on”March 16, 1931. The contract and specification 489 are divided into Schedules 2, 3, 4, 8, and 9, whieh the United States paid Mittry Bros. for the work performed thereunder, on Schedule 2 on October 9, 1930, on Schedules 3 and 9 on November 4, 1930, on Schedule 4 on March 16,1931, and on Schedule 8 on April 3, 1930. The last payment made by the United States for work done on that contract was for final settlement of Schedule 4, and was the last schedule to be completed and settled for under the contract. Thus the evidence discloses that the completion and final settlement of the contract was on March 16, 1931, as determined by the proper authority of the government, and the action was commenced on February 26, 1932, within a period of one year as required by the statute. The statute does not contemplate the running of it from the time the schedules are completed but from the date of the completion and final settlement of the entire contract, and those who have furnished materials and labor used in the construction of the work may bring their suit within the one-year period.

The statute we are considering (40 USCA § 270) provides: “That where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until after the complete performance of said eon-tract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later.” The words “final settlement and complete performance” used in the statute relate to the time when the amount due under the contract is determined by the appropriate administrative authority and when the work covered by the contract has been finally completed. Illinois Surety Co. v. U. S., to Use of Peeler, 240 U. S. 214, 36 S. Ct. 321, 60 L. Ed. 609; Mandel v. U. S. (C. C. A.) 4 F.(2d) 629.

The defendants assert that, as bids were considered by the United States on all or any number of the schedules and bidders could make stipulations as they desired regarding combinations of schedules, and when each schedule was completed the work thereunder was paid for, shows that they were separate and distinct contracts as to each schedule, and that, as Harkins having performed all of his work upon Schedules 2, 3, 8, and 9, and having performed no work upon Schedule 4, suit was filed too late. This argument would, without doubt, prevail had the United States entered into separate contracts for each schedule, but that was not done, as there was but one contract entered into between the United States and Mittry Bros. Construction Company covering all of these schedules, whieh included Schedule 4 that was completed and final settlement made by the appropriate administrative authority of the government on March 16, 1931, and brings the commencement of the action within the statutory period of one year. We must not forget that the bond sued upon here was given to secure the entire contract between the United States and Mittry Bros. Construction Company covering all of the schedules and not a portion of them. The mere fact that the United States called for bids for each schedule and settled for the work done *219 under each as the work progressed would not justify the conclusion that there was a separate contract as to each schedule.

B. The theory upon which a surety on a bond is held liable for interest is determined by the laws of the state allowing interest at the rate of 7 per cent, per annum from the date the account becomes due. Section 26-1904, I. C. A. The Supreme Court has settled this question in the case of Illinois Surety Co. v. John Davis Co., 244 U. S. 376, 37 S. Ct. 614, 617, 61 L. Ed. 1206, where it is said: “The contract and bond were made in Illinois and were to be performed there. Questions of liability for interest must therefore be determined by the law of that state. Scotland County v. Hill, 132 U. S. 107, 117, 10 S. Ct. 26, 33 L. Ed. 261, 265.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden West Construction Company v. United States
304 F.2d 753 (Tenth Circuit, 1962)
Guyman v. Anderson
271 P.2d 1020 (Idaho Supreme Court, 1954)
United States Guarantee Co. v. Colonial Oil Co.
145 F.2d 496 (Fifth Circuit, 1944)
Colonial Oil Co. v. United States Guarantee Co.
56 F. Supp. 545 (S.D. Georgia, 1944)
Massachusetts Bonding & Ins. Co. v. United States
88 F.2d 388 (Fifth Circuit, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
4 F. Supp. 216, 1933 U.S. Dist. LEXIS 1464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-belmont-v-mittry-bros-const-co-idd-1933.