United States Guarantee Co. v. Colonial Oil Co.

145 F.2d 496, 1944 U.S. App. LEXIS 4241
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 14, 1944
DocketNo. 11130
StatusPublished
Cited by3 cases

This text of 145 F.2d 496 (United States Guarantee Co. v. Colonial Oil Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Guarantee Co. v. Colonial Oil Co., 145 F.2d 496, 1944 U.S. App. LEXIS 4241 (5th Cir. 1944).

Opinion

LEE, Circuit Judge.

In the court below appellee sued appellant, as surety on a public contractor’s bond, for a balance alleged to be due by F. M. Jones and Leo T. Barber, co-contractors, for gasoline and oil furnished by appellee on the order of E. M. Jones.

The bond was furnished under the provisions of Georgia Code Ann. 1933, Section 23-1705 et seq., to secure performance of the contract entered into between F. M. Jones and Leo T. Barber and the State Highway Board of Georgia, and to secure “the payment as they become due of all just claims for work, tools, machinery, skill, and materials furnished by persons under, or for the purpose of, such contract.”

The case was tried to the court without a jury, and, from a judgment against it in the amount sued on, appellant prosecutes this appeal.

Two questions are before us for consideration :

1. Was it necessary for the appellee to allege and prove that the materials sued for were used and consumed in the completion of the contract covered by the bond sued on, or that the materials went into or contributed to the execution of the contract and nothing else?

2. Did appellee have the right to credit a remittance of $3,000 from the proceeds of the project covered by the bond to a pre-existing debt of Jones, one of the co-contractors, which debt was unrelated to the source of payment?

Appellee sued for materials furnished at the agreed price of $10,287.71, upon which there had allegedly been paid $4,494.22, leaving a balance of $5,793.49. The facts, largely stipulated, are as follows: On or about December 2, 1938, F. M. Jones and Leo T. Barber entered into a contract with the State Highway Board of Georgia for [498]*498construction of part of a State Highway-project in Glynn County, Georgia, referred to in this litigation as Project D-l, and gave a bond with appellant as surety. At about the same time, the same principals entered into another contract with the State Highway Board of Georgia for the construction of another part of the same highway, referred to in this litigation as Project B-l, and gave a bond with the St. Paul Mercury & Indemnity Company as surety. The two projects, B-l and D-l, were contiguous and formed when completed a continuous stretch of highway.

Appellee charged all deliveries on Projects B-l and D-l, until April 2, 1940, to F. M. Jones. The account did not designate against which project charges were made, all charges being made against both projects. The total account between January 10, 1939, when work on the two projects was started, to November 2, 1939, when work on Project B-l ceased, was $13,510.90.

Gasoline was delivered into a single tank used by the contractor, Jones, from which it was pumped into equipment employed on both projects. Oil and grease bought from appellee were likewise used in equipment which was employed on both projects. Neither plaintiff nor defendant nor Jones nor Barber knew how much of the gasoline, oil, and grease bought from the appellee by Jones was actually consumed in work on each of- the projects prior to November 2, 1939, when work on Project B-l was completed. All materials purchased by Jones after November 2, 1939, were used on and went into the construction of Project D-l.

On April 2, 1940, Jones and a Mr. Jarrell, an employee of appellee, had a conference at which they went over the account as it then stood on appellee’s books against both projects. Jones divided these charges between the two projects, allotting $4,845.60 of the total charges to November 2, 1939, to Project D-l.

Appellant contends that under Georgia law it is only those materials going into the work or especially contributing to the execution of the contract that are covered by the bond; that, in order to make out its case, it was necessary for appellee not only to allege and prove that it “furnished to F. M. Jones. and Leo T. Barber gasoline and oil for use on said project,” but further to allege and prove that said materials went into the work or especially contributed to the execution of the contract covered by the bond sued on and nothing else; and this appellee had failed to do.

The objection to the pleading is in the nature of a general demurrer, and, we think, has been disposed of by the Court of Appeals of Georgia in Motor Supply Co. v. St. Paul Mercury & Indemnity Co., 67 Ga.App. 236, 19 S.E.2d 737, 739. In that case Motor Supply Company had sold Jones and Barber various items for use in vehicles working on Project B-l and D-l. Suit was brought against Jones and Barber and the St. Paul Mercury & Indemnity Company, surety for Jones and Barber on Project B-l, for a percentage of the total bill for materials and supplies furnished and consumed on both projects, on the theory that such percentage had been used on Project B-l. The trial court sustained a general demurrer on the ground urged here, namely, that the petition did not show that the materials had been consumed on Project B-l. On appeal, the Court of Appeals reversed the trial court saying:

“It does not appear that the plaintiff is seeking to recover for any materials used on his highway work except that portion used to complete the contract involved here. The fact that the petition does not identify the particular and specific tools and materials furnished and used on the work under the contract involved in this case does not render it subject to general demurrer. There is nothing in Yancey Brothers Inc. v. American Surety Company, supra [43 Ga.App. 740, 160 S.E. 100], to the contrary of what is now held in the present case. If on the trial it appears that any of the tools, machinery, and materials furnished by the plaintiff were not used in incidental and current repairs to the equipment and machinery of Jones and Barber, under the contract here involved; but were used elsewhere, or were such as to amount to substantial additions to the equipment of these defendants, and involved major repairs and replacements of old with new parts, the plaintiff can not recover therefor under the rule laid down in the Yancey case.”

The total amount of materials furnished by appellee to Jones and Barber for use on Project D-l was $10,287.71, made up of materials furnished after November 2, [499]*4991939, in the amount of $5,442.06, which admittedly went into Project D-l, and of charges amounting to $4,845.60, representing items designated by Jones as chargeable to Project D-l out of the total charges of $13,510.90 for materials delivered for use on both projects prior to November 2, 1939.

When F. M. Jones, a principal who was in charge of the work, designated from items charged against both projects which of those items should be charged against Project D-l, we think, as did the court below, that appellee made out a prima facie case for recovery of the $4,845.60 against the surety.1

It is true that in the stipulation it was set forth that neither appellee nor defendant nor Jones nor Barber knew how much of the gasoline, oil, and grease bought from the appellee by Jones was actually consumed in work on either one of these projects prior to November 2, 1939, when work on Project B-l was completed. We take this statement, however, to mean that these parties did not know the “exact” amount of the gasoline, oil, and grease bought from the plaintiff which was used on each project Since Jones, who admittedly was constantly on

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amoco Oil Co. v. Capitol Indemnity Corp.
291 N.W.2d 883 (Court of Appeals of Wisconsin, 1980)
Acoustics, Inc. v. American Surety Co. of New York
320 P.2d 626 (Nevada Supreme Court, 1958)

Cite This Page — Counsel Stack

Bluebook (online)
145 F.2d 496, 1944 U.S. App. LEXIS 4241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-guarantee-co-v-colonial-oil-co-ca5-1944.