United States v. Grubb

358 F.2d 508, 1966 U.S. App. LEXIS 6873
CourtCourt of Appeals for the First Circuit
DecidedMarch 15, 1966
Docket19337
StatusPublished
Cited by8 cases

This text of 358 F.2d 508 (United States v. Grubb) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Grubb, 358 F.2d 508, 1966 U.S. App. LEXIS 6873 (1st Cir. 1966).

Opinion

358 F.2d 508

The UNITED STATES of America, for the Use of J. W. BRIGGS, Appellant and Cross-Appellee,
v.
Floyd R. GRUBB, United Pacific Insurance Company, a corporation, First Doe, Second Doe, Third Doe, Black Corporation, White Corporation, Blue Co., a partnership, and Gray Co., a partnership, Appellees and Cross-Appellants.

No. 19337.

United States Court of Appeals Ninth Circuit.

March 15, 1966.

COPYRIGHT MATERIAL OMITTED Laurence W. Carr, Redding, Cal., Gardiner Johnson, Thomas E. Stanton, Jr., San Francisco, Cal., Carr & Kennedy, Redding, Cal., Johnson & Stanton, San Francisco, Cal., for appellant.

Harold J. Chase, of Maloney, Chase, Fisher & Hurst, San Francisco, Cal., for appellees.

Before BARNES, HAMLIN and JERTBERG, Circuit Judges.

BARNES, Circuit Judge:

This is an appeal and cross-appeal from a judgment of the United States District Court for the Northern District of California, Northern Division. The district court had jurisdiction pursuant to the terms of the Miller Act, 40 U.S.C. §§ 270a-270d. This court has jurisdiction pursuant to 28 U.S.C. § 1291.

In June 1959, Floyd R. Grubb was the successful bidder for a contract with the Bureau of Reclamation for the relocation of a road in connection with the Trinity Dam project being conducted by the Bureau in Northern California. On July 10, 1959, Grubb executed a performance bond and a payment bond with United Pacific Insurance Company, as required by the Miller Act. Pursuant to the requirements of the Miller Act, the performance bond guaranteed that Grubb would properly perform his contract with the Bureau of Reclamation, and the payment bond guaranteed that Grubb would make prompt payment to all persons supplying labor and material in the prosecution of the construction contract.

Grubb was an Oregon contractor and had never undertaken a California job, nor a job as large as his Trinity Dam contract. Although he began work on the contract near the beginning of July, 1959, he had made very little progress by the end of August 1959. As a result, Grubb sought assistance from J. W. Briggs, a contractor with offices in Redding, California, who had been an unsuccessful bidder on the same Trinity Dam road contract. Several meetings were held between the two contractors in August and early September 1959, the most definite result of which was that Grubb refused an offer from Briggs to subcontract part of the job to Briggs at a price of forty cents per yard. The parties finally reached an agreement, the significance of which is disputed in this litigation, which was incorporated into two documents under dates of September 3 and September 17, 1959 (Exhibits 4 and 5). By the September 3, 1959 agreement Briggs had assumed for all practical purposes the entire management of the job. He subsequently transferred Grubb's employees to his (Briggs') own payroll, took over receiving and paying for most of the labor and materials used on the job, and assumed full management of the job. The September 17, 1959 agreement provided that Grubb would pay $10,000 to the Hardesty Construction Company, a firm entirely owned by Briggs. Briggs contends that the $10,000 agreement represented a fixed fee for the performance of his services and that it was paid to the Hardesty Company for tax reasons. The terms of the September 3, 1959 agreement and the evidence adduced at the trial indicate, however, that further compensation for Briggs was contemplated.

At the time of his September 1959 agreements with Briggs, Grubb was in serious financial difficulty. At the time he undertook the Trinity Dam road contract Grubb was completing another contract in Ashland, Oregon, bonded by the Peerless Casualty Company on which he suffered a loss, and had other obligations coming due during the course of the Trinity project. In September, 1959 Grubb entered into an arrangement with the Bank of America by the terms of which the bank advanced him $50,000 secured by the monthly progress payments from the Bureau of Reclamation. Loans of $50,000 were made and repaid on three occasions between September and December 1959. United Pacific alleges that Briggs knew of these loans, but Briggs denies such knowledge.

After the agreements of September 1959 between Briggs and Grubb, and after Briggs had assumed virtually complete control of the construction project, the work progressed rapidly. Large progress payments were paid by the Bureau of Reclamation on the contract from September-January, 1959-1960. According to Grubb's testimony, Grubb supplied copies of the progress payments to Briggs as they came due. Grubb did not pay over the full amount of the progress payments to Briggs, however, but instead diverted a portion of each such payment to the satisfaction of bills on other unrelated jobs. Furthermore, while Briggs applied the portion of each progress payment turned over to him by Grubb to the payment of material and labor bills on the Trinity Dam job, and took assignments of the Miller Act claims from each laborer and materialman, a number of materials accounts were left in the hands of Grubb for payment and were not paid. United Pacific alleges that all of this was done with the full knowledge of Briggs and with the purpose of allowing Grubb to bail himself out of his financial difficulties by diverting funds from the Trinity Dam project progress payments.

In early December 1959, Briggs notified United Pacific that Grubb had been borrowing money from the Bank of America on the strength of the progress payments from the Bureau of Reclamation. Briggs contends that this was the first notice he had had of Grubb's financial manipulations and that he notified the surety as soon as he learned of the bank loans. At this time Briggs held assignments from laborers and materialmen for $76,729.13 which he had paid and for which he had not yet been reimbursed by Grubb from the progress payments, and there were, in addition, between $100,000 and $150,000 worth of bills owing on the Trinity Dam job which Grubb had the responsibility to pay and had not yet paid. On December 15, 1959 United Pacific stepped in, and on December 22, 1959 the job was shut down temporarily due to weather conditions.

United Pacific took over the prosecution of the construction contract and received progress payments already accrued for adjustments and work performed in December 1959. These payments due at the time United Pacific took over totaled $86,322.91. United Pacific continued performance of the contract, using Grubb as job superintendent, and completed the job in September 1960. In October 1960 Grubb filed a petition in bankruptcy and was a bankrupt at the time of trial in this case. United Pacific paid all labor and material claims on the project, incurred both before and after it assumed management of the job, with the exception of Briggs' claims of $75,793.40.

On November 2, 1960, Briggs brought suit against United Pacific on the Miller Act payment bond, alleging two causes of action. First, to recover $75,793.40 due for labor and material supplied by Briggs pursuant to a subcontract between Briggs and Grubb. Second, to recover $67,455.22 as assignee of persons who had furnished labor or material used on the project. On March 16, 1961 United Pacific filed a cross-complaint stating two causes of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toporoff Engineers, P.C. v. Fireman's Fund Insurance
371 F.3d 105 (Second Circuit, 2004)
US EX REL. JOHNSON PUGH MECH. v. Landmark Const. Corp.
318 F. Supp. 2d 1057 (D. Colorado, 2004)
American Oil Co. v. Brown Paving Co.
298 F. Supp. 528 (D. South Carolina, 1969)
American Casualty Co. of Reading, Pennsylvania v. Assiran
289 F. Supp. 645 (D. Massachusetts, 1968)
Ingalls Iron Works Co. v. Fehlhaber Corp.
275 F. Supp. 623 (N.D. New York, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
358 F.2d 508, 1966 U.S. App. LEXIS 6873, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-grubb-ca1-1966.