US EX REL. JOHNSON PUGH MECH. v. Landmark Const. Corp.

318 F. Supp. 2d 1057
CourtDistrict Court, D. Colorado
DecidedMay 21, 2004
DocketCIV.01-B-2406(BNB)
StatusPublished

This text of 318 F. Supp. 2d 1057 (US EX REL. JOHNSON PUGH MECH. v. Landmark Const. Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US EX REL. JOHNSON PUGH MECH. v. Landmark Const. Corp., 318 F. Supp. 2d 1057 (D. Colo. 2004).

Opinion

318 F.Supp.2d 1057 (2004)

THE UNITED STATES of America for the Use and Benefit of JOHNSON PUGH MECHANICAL, INC., Plaintiff,
v.
LANDMARK CONSTRUCTION CORPORATION and The Mountbatten Surety Co., Inc., Defendants,
Doug Pourier, William Clary, Kathleen Clary, and PI Construction Corporation, Third-party Defendants.

No. CIV.01-B-2406(BNB).

United States District Court, D. Colorado.

May 21, 2004.

*1058 David L. Shakes, Hendricks, Hendricks & Shakes, P.C., Colorado Springs, CO, for Plaintiff.

Mike F. Pipkin, Sedgwick, Detert, Moran & Arnold, LLP, Dallas, TX, for Defendants, Cross-Claimant and Third-Party Plaintiff.

FINDINGS OF FACT AND CONCLUSIONS OF LAW AND ORDER

BABCOCK, Chief Judge.

This is a Miller Act action. See 40 U.S.C. §§ 3131(a)-(d). A trial to the Court *1059 was held February 23, 2004 through February 26, 2004. Plaintiff Johnson Pugh Mechanical, Inc. ("Johnson Pugh," or "JP") demands payment of $1,158,239.99 plus interest based on payment bonds executed by Defendant Mountbatten Surety Company, Inc. ("Mountbatten") for Defendant Landmark Construction Corporation ("Landmark"), principal on the bonds. Pursuant to the General Indemnity Agreement ("Agreement") executed prior to the issuance of these bonds, Third-party Defendants Doug Pourier, William Clary, Kathleen Clary, PI Construction Corporation ("PI"), and Defendant Landmark-who is also the principal on the bonds-agreed to indemnify Mountbatten against, inter alia, liability, losses, and other costs arising from the payment of these bonds.

Landmark is insolvent. A default judgment was entered against it. A default judgment was also entered against PI. Therefore, Johnson Pugh brought claims against Landmark's payment and performance bonds to recover the amount it alleges is due pursuant to asserted subcontract agreements with Landmark.

In defense, Mountbatten contends that Johnson Pugh is an "insider," or the alter ego of Landmark, Clary, or one or more of the indemnitors on the bonds, so may not make a claim against the bonds. Mountbatten also contends that Johnson Pugh did not perform subcontracts for Landmark in the first place. Mountbatten asserted a cross-claim against Landmark for breach of the indemnity agreement. Mountbatten also brought third-party claims against Pourier, the Clary's and PI for breach of the indemnity agreement. Clary represented himself at trial, and asserted the defense of fraud.

Jurisdiction arises under 40 U.S.C. §§ 270(a)-(d). For the following reasons, I find and conclude that Plaintiff has failed to establish it should receive payment. Therefore, I enter judgment in favor of Defendant Mountbatten, and conclude that Mountbatten's cross-claim and third-party claims are moot.

I. Findings of Fact

I find the following facts based on a preponderance of the evidence. This case involves a web of companies often formed and sometimes owned by Third-party Defendant William Clary. Due to the complex interrelatedness of the companies, questions arose about their true identities, their roles in the circumstances underlying this case, and whether Clary advised, controlled, or otherwise influenced them.

A. Landmark

Defendant Landmark Construction Corporation, a minority § 8(a) construction contractor, contracted with the United States government to renovate barracks at Fort Carson, a U.S. Army base in Colorado Springs, Colorado. See 15 U.S.C. § 637(a) (Small Business Act of 1953). Landmark's sole owner and president, Third-party Defendant Doug Pourier, an American Indian, worked with Clary, sole owner and president of PI Construction Corporation, to obtain payment and performance bonds for the project that were required by the Miller Act, 40 U.S.C. §§ 3131(a)-(d).

According to the credible testimony of Pourier and Michael Adams, a former project manager for PI, in 1988, Landmark subcontracted for PI at Ellsworth Air Force Base in South Dakota. Clary testified at trial that he was in control of PI "at all times." After Landmark initially was turned down for a bond on the Fort Carson project, Pourier approached Adams to determine whether PI would be interested in a joint venture with Landmark at Fort Carson. Adams then introduced Pourier to Clary. Pourier said he approached PI and Clary with the project in order to solicit help with the bonding and reap the *1060 benefit of Clary's experience with government contracting. It is undisputed that Landmark needed PI's help to secure the bonds.

Defendant Mountbatten issued a total of thirteen bonds to Landmark for the Fort Carson job. Of those, Mountbatten bond numbers ALL1-000006 PP, ALL1-000007 PP, ALL1-000008 PP, ALL1-000015 PP and ALL1-000016 PP, all of which had effective dates of March 8, 2001, are at issue here. Landmark, Pourier, Clary, Clary's wife, Kathleen, and PI indemnified all of the bonds obtained by Landmark, and pledged all of their individual assets as required under the indemnification agreements. See Defendant's Ex. A1, A2. Neither Clary nor PI ever owned any interest in Landmark.

Pourier testified that Clary made the major decisions for Landmark after Landmark became an 8(a) contractor. He testified that Clary controlled Landmark's payments to subcontractors. If a payment was not being made, Pourier would talk to Sandy Taylor at the financial accounting company Martin Mink, which performed accounting and financial services for Landmark. Martin Mink was owned wholly by Clary, so Taylor would talk to Clary about Landmark's financial problems. Pourier testified that he was concerned about Landmark's ability to finance and complete its contracts as the company began to grow in Colorado. Pourier talked to Clary and Sandy Taylor on many occasions about this concern, but his concerns were never allayed.

Pourier also testified that Clary moved personnel between PI and Landmark, and that Clary's companies PI, Martin Mink, Johnson Pugh, Baker White, and Mill Shop all had offices at the Pond Springs complex in Texas, along with Landmark. Id. at 38. He also recalled that Landmark, PI, Johnson Pugh, and Clary shared office space.

Clary testified as an adverse witness for Plaintiff, and testified on his own behalf, as well. I find that Clary's testimony was not altogether credible. However, Clary credibly testified he was Landmark's signatory on three accounts with Chase Bank. Clary also held himself out as Secretary of Landmark, had signatory authority for the company, and controlled who else had signatory authority. See Dfdt's Ex. A34.

Clary credibly testified that in January 2001, Landmark assumed the payroll of JP and took over its employees. A report prepared by Nancy Krenek, account manager at Martin Mink, confirms that all but three employees of Johnson Pugh were terminated or received their last paycheck no later than January 26, 2001, and the others were terminated as of February 22, 2001, well before March 8, 2001, the payment and performance bonds date. See Defendant's Ex. O.

Clary admitted that JP could not and did not purchase or supply materials for the Fort Carson project, and that Landmark could not finish the project because it did not have enough credit with the suppliers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
318 F. Supp. 2d 1057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-ex-rel-johnson-pugh-mech-v-landmark-const-corp-cod-2004.