United States v. Wiring, Inc.

646 F.2d 1037, 28 Cont. Cas. Fed. 81,455, 1981 U.S. App. LEXIS 12717
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 1, 1981
Docket80-7060
StatusPublished
Cited by3 cases

This text of 646 F.2d 1037 (United States v. Wiring, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Wiring, Inc., 646 F.2d 1037, 28 Cont. Cas. Fed. 81,455, 1981 U.S. App. LEXIS 12717 (5th Cir. 1981).

Opinion

646 F.2d 1037

28 Cont.Cas.Fed. (CCH) 81,455

UNITED STATES of America, for the Use and Benefit of GENERAL
ELECTRIC SUPPLY CO., a division of the General
Electric Co., Plaintiff-Appellant,
v.
WIRING, INC., et al., Defendants,
United States Fidelity & Guaranty Co., et al., Defendants-Appellees.

No. 80-7060.

United States Court of Appeals,
Fifth Circuit.

Unit B

June 1, 1981.

Sutherland, Asbill & Brennan, Alfred A. Lindseth, Atlanta, Ga., for plaintiff-appellant.

Walter H. Beckham, III, Jessee, Ritchie & Duncan, Karen W. Rowles, Atlanta, Ga., for defendants-appellees.

Appeal from the United States District Court for the Northern District of Georgia.

Before HILL, FRANK M. JOHNSON, Jr., Circuit Judges, and SCOTT*, District Judge.

CHARLES R. SCOTT, District Judge:

This action was brought by use plaintiff General Electric Supply Co. (hereinafter 'GE') against Wiring, Inc. (hereinafter 'Wiring'), an electrical subcontractor, to recover payment for materials supplied to Wiring in connection with two federal construction projects. Also named as defendants were Wiring president Ronald Terrell, who personally guaranteed the debts of Wiring to GE; John M. Murray, Jr. Construction Co. (hereinafter 'Murray'), the general contractor on the two government projects; and United States Fidelity & Guaranty Co. (hereinafter 'USF&G'), a surety company. Murray, as principal, and USF&G, as surety, had furnished a payment bond on each project for the protection of unpaid materials suppliers pursuant to the Miller Act, 40 U.S.C. §§ 270a et seq.

The case was tried without a jury before a United States Magistrate, sitting as a special master pursuant to Fed.R.Civ.P. 53. The special master determined that GE had made out a prima facie case of recovery against all defendants. He also found, however, that Murray and USF&G had established an affirmative defense to GE's claims on the Miller Act bonds and recommended that those claims be dismissed. By order dated September 26, 1979, and judgment dated September 28, 1979, the district court adopted, with one exception, the special master's report and recommendation.1 On December 19, 1979, the district court entered an amended judgment clarifying some minor ambiguities contained in the original judgment.

In 1975, Murray, as general contractor, entered into two separate contracts with the United States to construct United States Army Reserve Centers at Dobbins Air Force Base (hereinafter 'Dobbins') and Chamblee, Georgia (hereinafter 'Chamblee'). In turn, Murray entered into two subcontracts with Wiring, whereby Wiring was to furnish the necessary labor and materials for the electrical systems on each project.

From October 1975 through January 1977, GE furnished Wiring with materials costing $68,909.61 for use on the Chamblee and Dobbins projects.2 During this same time frame, Murray paid Wiring $121,781.94 on the two federal projects. This amount constituted only about 10 to 11 percent of Wiring's total receipts from all sources during the time the Chamblee and Dobbins projects were being constructed. Although GE received $95,732.96 from Wiring throughout this period, most of this amount was applied by GE, at Wiring's direction, to invoices outstanding on accounts other than the two federal projects. Of the $95,732.96 GE received from Wiring, only $5,715.77 was applied to either Chamblee or Dobbins, leaving an unpaid balance of $63,193.84 owing to GE on these projects.

As noted supra, the district court determined that GE had established a prima facie case on its Miller Act bond claims against Murray and USF&G. Nevertheless, the court dismissed those claims in large part, relying upon the equitable rule developed in Miller Act cases that where a materials supplier receives funds from a subcontractor knowing that the source of those funds is the general contractor on a government project, the supplier is obligated to apply those funds to the government project account.

It is well settled that once it has been determined that a supplier has knowingly misapplied funds, the misapplied funds must be reallocated to the proper accounts. See, e.g., United States v. Federal Insurance Co., 483 F.2d 153 (5th Cir. 1973); Graybar Electric Co. v. John A. Volpe Construction Co., 387 F.2d 55 (5th Cir. 1967); R. P. Farnsworth & Co. v. Electrical Supply Co., 112 F.2d 150 (5th Cir.), cert. denied, 311 U.S. 700, 61 S.Ct. 139, 85 L.Ed. 454 (1940). The rationale for this rule is that it would be unfair to the principal and surety on the Miller Act bond to permit a supplier to collect old debts out of monies paid on a current government project, secure in the knowledge that he will be able to collect for the materials furnished on the government project by filing a claim against the bond.

In the instant case, the district court concluded that GE had applied funds received from Wiring to project accounts other than Chamblee and Dobbins, knowing that these funds had their source in payments from Murray on the government jobs. Consequently, the court ordered reallocation of the major portion of such funds to the Chamblee and Dobbins accounts, thereby leaving GE with an unsatisfied claim against Murray and USF&G in the amount of $55,092.69.3 We are of the opinion that such a finding was error in that the record is devoid of evidence tending to prove that any funds derived from the government projects were misapplied.

At the outset of this discussion, it is important to delineate the standard governing our review of the district court's factual determination that a misapplication of funds occurred. Fed.R.Civ.P. 52(a) sets forth the rule that a trial court's findings of fact shall not be disturbed unless found to be "clearly erroneous." The rule provides further that the findings of a master, to the extent adopted by the district court, shall be considered as findings of the court. Under the clearly erroneous standard of review, findings of fact can be set aside "when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed." United States v. United States Gypsum Company, 333 U.S. 364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746, 766 (1948).

Generally speaking, this Court is bound to apply the clearly erroneous standard in reviewing district court factual determinations. Wilson v. Thompson, 638 F.2d 799, at 801, (5th Cir. 1981); Fitzgerald v. Peek, 636 F.2d 943, (5th Cir. 1981).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wynfield Inns v. Edward Leroux Group, Inc.
896 F.2d 483 (Eleventh Circuit, 1990)
Augusta Aviation, Inc. v. United States
671 F.2d 445 (Eleventh Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
646 F.2d 1037, 28 Cont. Cas. Fed. 81,455, 1981 U.S. App. LEXIS 12717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-wiring-inc-ca5-1981.