United States Casualty Co. v. Noland Co.

286 F. Supp. 333, 1968 U.S. Dist. LEXIS 9798
CourtDistrict Court, M.D. North Carolina
DecidedMay 27, 1968
DocketNo. C-37-WS-66
StatusPublished
Cited by5 cases

This text of 286 F. Supp. 333 (United States Casualty Co. v. Noland Co.) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Casualty Co. v. Noland Co., 286 F. Supp. 333, 1968 U.S. Dist. LEXIS 9798 (M.D.N.C. 1968).

Opinion

MEMORANDUM OPINION

GORDON, District Judge.

This case is before the Court on motions for summary judgment filed by the plaintiff, United States Casualty Company, and the defendant, Noland Company, Inc., and is a controversy between the plaintiff, a surety company, which bonded certain construction contracts for a now defunct electrical construction company, and the defendant, a wholesale distributor who supplied the electrical equipment on account to the defunct electrical construction company. The dispute is over the application of funds from construction jobs bonded by the plaintiff. The plaintiff asserts that funds from its jobs were improperly applied by the defendant to pay for supplies for jobs bonded by another surety company, the third party defendant in this action. The defendant, Noland Company, Inc., asserts that this has not been proved by the evidence, and even if proved, is not the law in this case.

The following facts are not in substantial dispute:

Findings of Fact

1. United States Electric Company, Inc., (Electric), at all times pertinent was a North Carolina corporation organized in 1961 with its principal office and place of business in High Point, North Carolina. Electric, now bankrupt, and not a party to this action, was in the business of constructing the electrical systems for various building projects around North Carolina. As such, Electric was known in the trade as an “electrical contractor,” because Electric bid on the portions of these building contracts dealing with electricity. A major portion of its work was on the construction of public buildings.

2. On thirty-five projects, during the time under consideration, United States Electric Company was required to give a surety bond conditioned upon payment for all labor and materials reasonably required for use in the performance of its part of the contract. Seventeen of such contracts entered into by Electric before September 15, 1963, were bonded by Hartford Accident & Indemnity Company (Hartford). Eighteen of the contracts were entered into after September 15, 1963, and were bonded by plaintiff, U. S. [335]*335Casualty Company (Casualty). During this period, Electric contracted to do more than forty projects which were not bonded.

3. Defendant, Noland Company, Inc., (Noland), is a Virginia corporation doing business as a wholesale distributor of electrical and plumbing supplies in numerous states in the southeastern United States, including North Carolina. No-land was one of the several suppliers who sold and delivered electrical supplies to Electric for use in the performance of the seventy-five contracts in which Electric was engaged.

4. In October and November of 1962, Electric began to go into debt at a substantially greater rate to the Noland Company than it had for the previous four or five months, as reflected in the accounts receivable trial balances of No-land. It was about this time that John C. Hayworth became connected with Electric as an “inside man:” the man in the office who supervised the estimation and bidding on the construction contracts. The Noland records began to reflect also an increase in the amount of Electric’s debt over thirty days past due. Until January 31, 1963, Electric’s debt to No-land increased at a rate something less than 10 per cent per month. However, one month later the debt began jumping at the rate of 30 per cent per month and accounts became sixty days past due.

5. By June 30, 1963, Electric owed Noland over $82,000.00, of which over $8,000.00 was ninety days past due. During July and August, 1963, the total indebtedness remained around $80,000.00, but the amounts past due sixty and ninety days were steadily increasing. During September and October, 1963, Electric appeared to be holding its own in keeping the debts overdue sixty and ninety days down to the previous levels. However, the amount past due thirty days increased to a total of over $68,-000.00.

6. By July, 1963, the district credit manager of Noland had became aware of the increase in the Electric account. He stated that he only became “concerned” about the account in “late ’63.”

7. The plaintiff, Casualty, began to issue the surety bond for Electric jobs on September 15, 1963. Around this time Hartford and Electric had a misunderstanding on the bond on one of the electric jobs and Hartford stopped bonding Electric jobs. On November 21, 1963, the bond superintendent of Casualty requested financial information about Electric from the Noland Office in Winston-Salem. Mr. Futrell, the local credit manager for Noland in Winston-Salem, replied, obviously using the figure found on the October 31, 1963, trial balance, that the amount owing at the present time was $76,440.59, that his general opinion of Electric was that it was “aggressive and capable,” and his response to the question “Method of Payment (Prompt, slow) ?” was “job basis.”

8. By February 29,1964, Noland’s accounts receivable from Electric had grown to over $95,000.00, with over $69,-000.00 thirty days past due, $67,000.00 sixty days past due, and over $40,000.00 ninety days past due. By July 31, 1964, the Electric account had grown to over $143,000.00, with $90,000.00 thirty days past due, $67,000.00 sixty days past due, and close to $50,000.00 ninety days past due.

9. At this juncture, Casualty’s bond superintendent again wrote the Noland office in Winston-Salem, on August 5, 1964, relative to issuing suretyship for Electric. This time the Noland credit manager responded, apparently using the figure on the July 31, 1964, trial balance, that the amount owing at the present time was $143,615.65, and that the method of payment was “slow.” In response to the question “Have you ever had occasion to limit their credit purchases ?” his response was “fulfilling existing commitments.” The Noland credit manager’s general opinion of Electric was “Know the electrical business — apparently need counseling on financial side.”

10. As the Electric accounts grew increasingly large in late 1963 and early 1964, Noland began to press Electric for [336]*336the payment of those accounts running past due. In June and July, 1964, No-land put pressure on Electric to pay up certain jobs or Noland would have to seek its protection under the surety bonds. This would have meant that the surety company would be apprised of the financial straits of Electric. Noland was merely trying to protect itself. This led to Electric’s paying off these old accounts out of funds which partially came from jobs distinct from those giving rise to these old accounts. Thus, money coming from jobs bonded by Casualty was used to pay debts to Noland which had arisen on Hartford jobs. Noland’s own local credit manager stated that he was more interested in getting money paid on the accounts than where the money came from. Therefore, Noland had reason to know that the funds being paid on the old accounts had a source distinct from the job giving rise to the old account. Noland, thus, had notice that funds were being misapplied to pay for jobs distinct from those from which the funds came. This confusion of job source and payment on account was contrary to the normal procedure in the construction trade. The normal procedure is to be paid on a “job basis:” the supplier gets paid for supplies used on a particular job out of the funds and progress payments coming to the contractor from that particular job.

11. In early August, 1964, Casualty began to realize that Electric was in trouble.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

UHL Construction v. Fidelity & Deposit Co. of Maryland
538 A.2d 562 (Superior Court of Pennsylvania, 1988)
Uhl Const. v. FID. & DEP. CO. OF MD.
538 A.2d 562 (Supreme Court of Pennsylvania, 1988)
United States v. Sentry Insurance
774 F.2d 80 (Fourth Circuit, 1985)
American Oil Co. v. Brown Paving Co.
298 F. Supp. 528 (D. South Carolina, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
286 F. Supp. 333, 1968 U.S. Dist. LEXIS 9798, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-casualty-co-v-noland-co-ncmd-1968.