United States Ex Rel. Bettis v. Odebrecht Contractors of California, Inc.

393 F.3d 1321, 364 U.S. App. D.C. 250, 2005 U.S. App. LEXIS 394, 2005 WL 41419
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 11, 2005
Docket04-5051
StatusPublished
Cited by66 cases

This text of 393 F.3d 1321 (United States Ex Rel. Bettis v. Odebrecht Contractors of California, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Bettis v. Odebrecht Contractors of California, Inc., 393 F.3d 1321, 364 U.S. App. D.C. 250, 2005 U.S. App. LEXIS 394, 2005 WL 41419 (D.C. Cir. 2005).

Opinion

Opinion for the Court filed by Circuit Judge EDWARDS.

HARRY T. EDWARDS, Circuit Judge.

Under the qui tam provisions of the False Claims Act (“FCA” or “Act”), 31 U.S.C. §§ 3729-3733 (2000), any person may initiate a lawsuit in the name of the United States for substantive violations of the Act. The United States, through its relator Alva Bettis (“Bettis”), brought this action in the District Court against Ode-brecht Contractors of California, Inc., et al. (“Odebrecht”), alleging that Odebrecht submitted false claims to the Government in connection with a public works construction contract it had with the U.S. Army Corps of Engineers (“Corps”).

In advancing his claim, Bettis relies on the fraud-in-the-inducement theory of liability under the FCA. Under that theory, every claim submitted under a fraudulently induced contract constitutes a “false claim” within the meaning of the Act (ie., is automatically tainted), even without proof that the claims were fraudulent in themselves. Bettis argues that Odebrecht fraudulently induced the Corps to award it the disputed contract by submitting an intentionally undervalued bid and making other false representations in order to win the contract, with the intention of subsequently obtaining upward modifications to the contract price.

The District Court granted summary judgment for Odebrecht, relying on two alternative grounds. First, the court rejected Bettis’s fraud-in-the-inducement claim as a matter of law. The court held that, where it is alleged that the defendant has submitted a fraudulently deflated bid in order to obtain a contract, a FCA action cannot succeed without proof that one or more requests for payment under the contract were fraudulent in themselves. The United States, as amicus curiae, contests the District Court’s legal analysis on this point, arguing that the fraud-in-the-inducement theory of FCA liability properly applies to allegations of fraudulently deflated bids. In the alternative, the District Court concluded that, as a matter of fact, the evidence presented by Bettis was insufficient to permit the inference that Ode-brecht fraudulently induced the Corps to award it the contract.

We conclude that the evidence presented by Bettis would not permit a reasonable jury to conclude that Odebrecht fraudulently induced the Government to award it the contract. We therefore affirm the judgment of the District Court on this ground alone.

I. Backgkound

On March 1, 1993, the U.S. Army Corps of Engineers (“Corps”) solicited bids for construction of the Seven Oaks Dam and Appurtenances in San Bernardino County, California. In preparing the solicitation, the Corps divided the construction into 150 separate tasks, referred to as bid items, and estimated the quantity of each bid item that would be required during construction. Contractors prepared a unit price for each bid item that included any indirect costs (e.g., labor, equipment, overhead) and a profit margin. The final price for each bid was calculated by multiplying the bidder’s unit price for each bid item by *1324 the Corps’ quantity estimate and then summing the totals of all of the bid items. The final bid price was only an estimate, because the winning bidder was to be paid based on the actual quantities required during construction, not the Corps’ estimated quantities. Bidders were, however, bound by their unit prices and assumed the risk if these prices turned out to be too low.

Odebrecht submitted a bid of $167,777,000. The sealed bids were opened on July 7, 1993, and Odebrecht’s bid was the lowest, coming in about $29 million below the second lowest bid, which had been submitted by a joint venture involving Tutor-Saliba Corporation and others (“Tutor-Saliba”), and almost $36 million below the Corps’ cost estimate (without profit) of $203,771,540.

Tutor-Saliba commenced a series of bid protests seeking to prevent Odebrecht from being awarded the contract. On March 29, 1994, following the resolution of the bid protests, Odebrecht was awarded the contract. The Corps issued Odebrecht a notice to proceed with construction on April 20, 1994, and Odebrecht began construction shortly thereafter.

During the course of construction, Odebrecht requested and received a number of “equitable adjustments” to the contract price. Equitable adjustments are used to keep a contractor whole when the Government modifies the contract or, under some Government contracts, for changed circumstances. See 48 C.F.R. §§ 52.243-4, 52.243-5 (2003). They are not available for reasons unrelated to a change, such as to compensate a contractor who has underestimated his bid or encountered unanticipated expenses or inefficiencies. Pac. Architects & Eng’rs Inc. v. United States, 203 Ct.Cl. 499, 491 F.2d 734, 739 (1974). Ultimately, by August 31, 2003, the Government had paid Odebrecht nearly $268 million, an amount that exceeded the bid price by more than $100 million. Even so, Odebrecht maintains that it sustained a loss in excess of $30 million on the project.

It is undisputed that the Corps was satisfied with Odebrecht’s work on the project. Indeed, in 1999, the Corps awarded Odebrecht its Civil Works Construction Contractor of the Year award for Ode-brecht’s “exceptional performance” on the project.

In 1999, relator Alva Bettis, who had been employed as a project scheduler by a consulting firm retained by the Corps to monitor the dam’s progress, commenced this action in the District Court, alleging that Odebrecht violated the FCA. The complaint was filed under seal and in the name of the United States, pursuant to the qui tam provisions of the FCA. See 31 U.S.C. § 3730(b). After the Government declined to exercise its right to intervene and proceed with the action under § 3730(b), the complaint was unsealed and served.

In' June 2002, Bettis filed his Third Amended Complaint, which included seven counts in which he claimed that Odebrecht violated the FCA. In Count I (the only count relevant to this appeal), Bettis pressed a fraud-in-the-inducement claim, alleging that Odebrecht fraudulently induced the Corps to award it the contract. Specifically, Bettis alleged that Odebrecht violated the Act by submitting an intentionally low bid — at which price Odebrecht knew or should have known that it could not have completed the project — with the intention of seeking adjustments to the price after winning the contract. On October 24, 2002, the District Court issued an order dismissing the count without prejudice. See United States ex rel. Bettis v. Odebrecht Contractors of Cal., Inc., Civ. A. *1325 No. 99-2879, slip op. at 4-13 (D.D.C. Oct. 24, 2002) (“Mem. Op.”), reprinted in Joint Appendix (“J.A.”) at 39, 42-51.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fuchs v. Johns Hopkins University
District of Columbia, 2025
Brent Berry v. Native American Services Corporation
109 F.4th 1297 (Eleventh Circuit, 2024)
Morsell v. Symantec Corporation
District of Columbia, 2023
Scollick v. Narula
District of Columbia, 2022
Marsteller v. Tilton
N.D. Alabama, 2021
United States v. Strock
982 F.3d 51 (Second Circuit, 2020)
United States ex rel. Carmichael v. Gregory
270 F. Supp. 3d 67 (District of Columbia, 2017)
United States v. Dyncorp International, LLC
253 F. Supp. 3d 89 (District of Columbia, 2017)
United States ex rel. Reeves v. Mercer Transportation Co.
253 F. Supp. 3d 1242 (M.D. Georgia, 2017)
Scutellaro v. Capitol Supply, Inc.
District of Columbia, 2017
United States Ex Rel. Barko v. Halliburton Co.
241 F. Supp. 3d 37 (District of Columbia, 2017)
United States Ex Rel. Landis v. Tailwind Sports Corp.
234 F. Supp. 3d 180 (District of Columbia, 2017)
United States Ex Rel. Keaveney v. SRA International, Inc.
219 F. Supp. 3d 129 (District of Columbia, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
393 F.3d 1321, 364 U.S. App. D.C. 250, 2005 U.S. App. LEXIS 394, 2005 WL 41419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-bettis-v-odebrecht-contractors-of-california-inc-cadc-2005.