Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

176 F.3d 776, 1999 U.S. App. LEXIS 9312, 1999 WL 308587
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 17, 1999
Docket98-1037
StatusPublished
Cited by963 cases

This text of 176 F.3d 776 (Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company, 176 F.3d 776, 1999 U.S. App. LEXIS 9312, 1999 WL 308587 (4th Cir. 1999).

Opinion

*780 Affirmed in part, reversed in part, and remanded for proceedings consistent with this disposition by published opinion. Judge MURNAGHAN wrote the opinion, in which Judge WILLIAMS and Judge BLAKE joined.

OPINION

MURNAGHAN, Circuit Judge:

Relator Harrison (“Harrison” or “Appellant”) brought a claim under the False Claims Act, 31 U.S.C.A. §§ 3729-3733 (West Supp.1998), against Westinghouse Savannah River Corp. (“WSRC”) alleging that WSRC made false and fraudulent statements to the government in connection with claims for payment to a subcontractor hired by WSRC for a Department of Energy (“DOE”) contract. Harrison alleged, inter alia, that WSRC misrepresented the cost and duration of the proposed subcontract in order to get DOE approval for the subcontract, and that WSRC falsely certified that there was no conflict of interest with the subcontractor. The district court granted WSRC’s motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), finding that no false claim had been made, either because Harrison’s complaint amounted only to allegations of inefficiency, or because the allegedly false statements were not made in connection with a “claim” under the False Claims Act. We affirm in part and reverse in part.

I.

A.

Since 1989, WSRC has been the management and operations contractor for the United States Department of Energy at the Savannah River Site (“SRS”), a nuclear facility near Aiken, South Carolina. WSRC’s contract with the government provides that WSRC is entitled to receive the allowable costs it incurs on the project in addition to an award fee.

As a part of its contractual responsibilities, and pursuant to policy and regulations, when WSRC decides to subcontract certain tasks necessary for the operation and management of the SRS, WSRC provides the technical requirements to the DOE for review before releasing a solicitation or request for proposals (“RFP”) for that subcontracting action. See Department of Energy Acquisition Regula-tion (“DEAR”) § 970.7108, 48 C.F.R. § 970.7108 (1988). 1 Once the technical review is complete, WSRC releases an RFP for the work and selects the subcontractor in a manner consistent with the provisions of the RFP. WSRC then sends a “Procurement Under Review” or “PUR” package to the DOE, which includes a copy of the technical requirements, the solicitation, the Justification for Award, the subcontractor-awardee’s proposal, and the proposed subcontract. The DOE reviews the information in the package and decides whether it will approve the request to subcontract the work out. If the DOE approves, WSRC enters into a subcontract with the selected subcontractor.

Count l: 2 False-Statements About Need for Subcontractor and Price of Subcontract

In July 1992, WSRC identified a need for training related to in-tank precipitation process operations, known as “ITP Training” (hereinafter “ITP Training Project”). As part of its standard practice, WSRC included in the technical package that was sent to the DOE for review a “Make or *781 Buy Analysis” (“MBA”), which analyzed the cost-effectiveness of buying the ITP Training services as opposed to providing those services in-house. (Amended Complaint at ¶ 24.) The MBA stated that while WSRC had the capacity to provide the service, WSRC did not have personnel available. The MBA stated further that since the service was of a one-time variety and of a short-term nature (1.5 years), it was not practical for WSRC to hire full-time staff to meet the need.

WSRC’s MBA also represented to the government that in the aggregate, WSRC estimated that the cost for WSRC to provide the ITP Training would be $1,579,500, while the cost for a subcontractor to perform the work would be substantially more — $2,750,000. The DOE reviewed and signed off on the technical package, including the MBA. After receiving the DOE’s approval, WSRC released a request for proposals for the ITP Training Project and ultimately subcontracted the project to General Physics Corporation (hereinafter “GPC subcontract”).

Harrison alleges that WSRC made the following misrepresentations to the government as part of its “plan and scheme” to obtain DOE approval for WSRC’s use of a subcontractor rather than use of WSRC’s own personnel to develop and implement the ITP Training Project:

a. That the project was “short term” such that subcontract personnel would be needed for no more than 1.5 years; WSRC knew that developing and implementing the ITP Training Project would take at least several years, (Amended Complaint ¶ 24(a));
b. That providing the ITP Training was not “a continuing need” but rather was a “one time variety” project; WSRC knew that the ITP Training Project would be a continuous on-going need for many years, (Amended Complaint ¶ 24(b));
c. That there was no need to hire permanent staff to fulfill the ITP Training requirement; WSRC knew that the ITP Training Project would require qualified trainers for a decade or more, (Amended Complaint ¶ 24(c));
d. That “Other Costs” for such things as computers, etc., would be zero; WSRC knew that the subcontractor would need to purchase computers to perform the subcontract work, (Amended Complaint ¶ 24(e)); (See also Amended Complaint ¶ 33); and
e. That the ITP Training services could be obtained on a firm-fixed price basis at a “total cost” of $2,750,000; WSRC intended to subcontract the ITP Training Project on a cost-plus-fixed-fee basis and knew that the training would cost substantially more than $2,750,000, (Amended Complaint ¶¶ 24(d), 22(a)).

Count %: False Certification of No Conflict of Interest

General Physics Corporation (“GPC”), a subcontractor company doing business with WSRC at SRS, employed Relator Harrison as one of its vice-presidents. He worked for GPC in Aiken, directing some of GPC’s subcontract work with WSRC at SRS. On August 12, 1992, GPC received from WSRC a RFP for the ITP Training Project.

During the next several weeks, Harrison alleges that he became aware that GPC personnel developing GPC’s proposal were requesting and improperly receiving insider information from WSRC’s Subcontract Technical Representative (“STR”). Harrison allegedly found that WSRC’s STR, who would later participate in the technical evaluation of the bids on the ITP Training Project, was supplying insider information not available to other bidders. He also alleges that he learned that WSRC’s STR had permitted GPC employees to participate in preparation of portions of the RFP. 3 (Amended Complaint 28.) WSRC awarded the ITP Training subcontract to GPC.

*782

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Wells Fargo Bank, N.A.
972 F. Supp. 2d 593 (S.D. New York, 2013)
Tepeyac v. Montgomery County
779 F. Supp. 2d 456 (D. Maryland, 2011)
Duncan Services, Inc. v. ExxonMobil Oil Corp.
722 F. Supp. 2d 640 (D. Maryland, 2010)
Johnson v. MV TRANSPORTATION INC.
716 F. Supp. 2d 410 (D. Maryland, 2010)
United States Ex Rel. Thomas v. Siemens AG
708 F. Supp. 2d 505 (E.D. Pennsylvania, 2010)
Randolph v. ADT SECURITY SERVICES, INC.
701 F. Supp. 2d 740 (D. Maryland, 2010)
United States v. Purdue Pharma L.P.
600 F.3d 319 (Fourth Circuit, 2010)
United States Ex Rel. Baker v. Community Health Systems Inc.
709 F. Supp. 2d 1084 (D. New Mexico, 2010)
San Francisco Unified School District Ex Rel. Contreras v. Laidlaw Transit, Inc.
182 Cal. App. 4th 438 (California Court of Appeal, 2010)
Johnson v. University of Rochester Medical Center
686 F. Supp. 2d 259 (W.D. New York, 2010)
Johnson v. THE UNIVERSITY OF ROCHESTER MEDICAL CENTER
686 F. Supp. 2d 259 (W.D. New York, 2010)
Robledo v. Chertoff
658 F. Supp. 2d 688 (D. Maryland, 2009)
United States v. Science Applications International Corporation
653 F. Supp. 2d 87 (District of Columbia, 2009)
Mann v. Heckler & Koch Defense, Inc.
639 F. Supp. 2d 619 (E.D. Virginia, 2009)
Fraternal Order of Police v. Prince George's County
645 F. Supp. 2d 492 (D. Maryland, 2009)
CoStar Realty Information, Inc. v. Meissner
604 F. Supp. 2d 757 (D. Maryland, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
176 F.3d 776, 1999 U.S. App. LEXIS 9312, 1999 WL 308587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edwin-p-harrison-and-united-states-of-america-party-in-interest-v-ca4-1999.