Standard Acc. Ins. Co. v. Simpson

64 F.2d 583, 1933 U.S. App. LEXIS 4162
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 4, 1933
Docket3396, 3397
StatusPublished
Cited by28 cases

This text of 64 F.2d 583 (Standard Acc. Ins. Co. v. Simpson) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Acc. Ins. Co. v. Simpson, 64 F.2d 583, 1933 U.S. App. LEXIS 4162 (4th Cir. 1933).

Opinion

PARKER, Circuit Judge.

These are appeals from a decree in two cases which were consolidated and heard together below and which involve questions of liability under bonds of a road contractor and •a subcontractor. Tlie contractor was the Carolina Contracting Company, which had entered into a number of contracts covering the construction and paving of roads and streets for the county of Richland and the city of Columbia. The surety on its bonds covering the projects here involved was the Consolidated Indemnity & Insurance Company, hereafter referred to as the Consolidated. The subcontractor, who entered into contracts with the contractor for the grading and drainage work on the various projects, was one F. W. Simpson; and' the surety on the bond which he executed to the contractor was the Standard Accident Insurance Company, hereafter referred to as the Standard. The controversy arises out of claims, aggregating $55,443.28, for materials furnished to the subcontractor, who is now insolvent, for use on the various projects.

The court below held that the bond of $25,000, originally executed by the Standard to guarantee the performance of the first contract awarded to the subcontractor, had been extended to cover subsequent contracts and that the total of its coverage after the extensions was $51,601.40, or 50 per cent, of the amount called for by the contracts. Decree was entered against the Standard for this amount, plus interest in the sum of $916.90 and attorneys’ fees of $800 allowed counsel for the contractor. The court held, further, that the contractor and its bondsman, the Consolidated, were liable for the claims of the materialmen, since the materials in question were used on projects covered by its contracts and the bonds guaranteeing them. Fees of counsel for claimants to the amount of $1,000 were allowed out of a fund in the hands of tho contractor representing retained percentage on contracts of the subcontractor. From this decree one appeal is prosecuted by the Standard and another by the contractor and its bondsmen, the Consolidated. On the appeal of the Standard, tho question presented is the extent of its liability, as it admits liability for $25,000 and has paid this amount into court. On the appeal of the Consolidated and the contractor, the question is their liability for materials and supplies furnished the subcontractor and for the fees allowed attorneys of claimants. *586 < The facts necessary to an understanding of the appeal of the Standard are as follows: About February 20,1930, the county of Rich-land awarded to the contractor a contract for the construction of three sections of improved highway, embracing five miles on the Old Winnsboro Road, three miles on the Asylum Road, and two miles on the Leesburg Road. At the same time, the contractor entered into a, contract with the subcontractor to do the grading and drainage work on these projects at .certain unit prices, which it was estimated would amount to $48,855. The contract between the contractor and the subcontractor provided that the latter should give bond for the faithful performance of his contract in the sum of $25,000; and bond in this amount was duly executed with the Standard as surety. Premium on tills bond was calculated at $15-per $1,000 of the contract price; and a premium of $732.80 was paid at the time of its execution. The application for this bond contained a provision that, upon the completion of the work under the contract, the premium would be adjusted in accordance with the certificate of the engineer in charge of the work. Although it is said that the contract between the contractor and the subcontractor contained a provision as to the extension of same, we find nothing of this sort in the contract, except a provision in the clause as to time, which provides that: “If the satisfactory execution in completion of the contract shall require work or material in greater or lesser amounts or quantities than those set forth in the contract, then the contract, time shall be increased or decreased in the same proportion as the altered amount of work bears to the original work contracted for.” There is nothing in either the contract or the bond to indicate that in executing the latter it was contemplated that any projects would be guaranteed by it other than those embraced in the contract. The bond is captioned as “Assuring execution of contract for construction of approximately five miles, old Winns-boro Road, three miles Asylum Road, and two miles Leesburg Road in Richland County.”

Some time after this, the contractor was awarded three separate contracts covering road projects by the county of Riehland and two covering street work by the city of Columbia. For each of these contracts a separate bond was executed by the contractor just as in the case of the first contract. The contractor sublet to the subcontractor the grading and drainage work under all of these contracts, but no additional written contracts were signed between them; it being understood in each ease that the subcontractor should take the work under the terms set forth in the original contract. No additional bonds were executed by the subcontractor covering the additional work awarded him; but it appears that the local agent of the Standard, one T. P. MeCrae, told him and one of the officers of the contractor that the original bond would'be extended to cover the liability of the subcontractor on these additional contracts to an amount equal to 50 per cent, of the amount to be paid under the contracts. No written application for bond was made as the basis of any extension of liability, no premium was paid therefor, and no assumption of liability or change in the coverage of the original bond was reported to the Standard by MeCrae. No writing was signed by MeCrae evidencing any change in liability except with respect to the second extension of the work on the Old Winnsboro Road, as to which there was a change in the unit prices allowed for the work. To cover this, a “rider” was executed by MeCrae in the form of a letter addressed to the contractor under date of August 20, 1930, as follows:

“Aug. 20th, 1930. “Carolina Contracting Company,
“Columbia, South Carolina.
“Gentlemen: Re: SA-50751-420 — Frank
W. Simpson.
“The Standard Accident Insurance Company as surety on the above captionéd bond hereby consents to the extension of the contract covered by this bond to cover the structures and grading on the Winnsboro road from survey station 284 towards the Fairfield county line as described in letter of award from the Carolina Contracting Company to Frank W. Simpson under date of July 3rd., a copy of which is attached to this letter.
“In consenting to this extension, it is mutually agreed and understood that this in no way changes the company’s liability under the bond as originally written, but extends the liability of this bond to an amount equal to 50% of the amount the contract is extended.
“Standard Accident Insurance Company
“By T. P. MeCrae, Attomey-in-faet. “TPM/R enel. [Seal.]”

With respect to the authority of MeCrae to bind the Standard by the verbal extensions of liability and the provisions of this rider or letter, it appears that he held merely an er- *587

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paige International, Inc. v. Xl Speciality Insurance Company
267 F. Supp. 3d 205 (District of Columbia, 2017)
Hard Hat Workforce Solutions, LLC v. Mechanical HVAC Services, Inc.
750 S.E.2d 921 (Supreme Court of South Carolina, 2013)
Tobacco Technology, Inc. v. Taiga International N.V.
626 F. Supp. 2d 537 (D. Maryland, 2009)
Jurimex Kommerz v. Case Corp
Third Circuit, 2007
Bridas S.A.P.I.C. v. Government of Turkmenistan
345 F.3d 347 (Fifth Circuit, 2003)
Watson v. Harmon
312 S.E.2d 8 (Court of Appeals of South Carolina, 1984)
AMERICAN AIR FILTER CO. INC. v. Innamorati Bros. Inc.
260 N.E.2d 718 (Massachusetts Supreme Judicial Court, 1970)
National Union Fire Insurance v. Denver Brick & Pipe Co.
427 P.2d 861 (Supreme Court of Colorado, 1967)
Berns & Koppstein, Inc. v. Orion Insurance Co.
170 F. Supp. 707 (S.D. New York, 1959)
Nos. 7341-7343
242 F.2d 429 (Fourth Circuit, 1957)
United States v. One 1955 Mercury Sedan
242 F.2d 429 (Fourth Circuit, 1957)
Labor Relations Board v. Compañía Popular de Transporte, Inc.
77 P.R. 1 (Supreme Court of Puerto Rico, 1954)
Junta de Relaciones del Trabajo v. Compañía Popular de Transporte, Inc.
77 P.R. Dec. 1 (Supreme Court of Puerto Rico, 1954)
Farm Bureau Mut. Auto. Ins. Co. v. Bobo
214 F.2d 575 (Fourth Circuit, 1954)
Metallizing Engineering Co. v. B. Simon, Inc.
64 F. Supp. 848 (W.D. New York, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
64 F.2d 583, 1933 U.S. App. LEXIS 4162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-acc-ins-co-v-simpson-ca4-1933.