Aetna Casualty & Surety Co. v. American Surety Co.

64 F.2d 577, 1933 U.S. App. LEXIS 4161
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 4, 1933
Docket3424
StatusPublished
Cited by9 cases

This text of 64 F.2d 577 (Aetna Casualty & Surety Co. v. American Surety Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aetna Casualty & Surety Co. v. American Surety Co., 64 F.2d 577, 1933 U.S. App. LEXIS 4161 (4th Cir. 1933).

Opinion

SOPER, Circuit Judge.

This suit in equity was instituted by ¿Etna Casualty & Surety Company, a corporation, against Coss & Otto, copartners engaged in the business of road construction, the state road commission of West Virginia, a corporation, and divers other parties to whom Coss & Otto had assigned certain sums of money to be paid out of any funds that might become due them by the state road commission under a contract for the construction of a highway, known as the river road, in Marshall county in West Virginia. The firm had entered into a contract with the commission under date of June 14,1927, for the construction of a portion of the highway; and the surety company on July 11, 1927, had executed a bond in the sum of $35,204, in which it guaranteed that the firm would faithfully perform the contract and pay all debts incurred for labor and material furnished in and about the construction of the road. In the application to the surety company for the bond, and as part of the contract between them, Coss & Otto assigned to the company all deferred payments and retained percentages arising out of the contract, and any moneys that might be due them thereunder, if at any time they should fail to pay any bills incurred in the work. The funds assigned were to be held by the surety and credited by *579 it upon any loss it might sustain under any bond of suretyship whieh it had executed or might thereafter execute for the firm. The contractors finished their work under the contract prior to June 1, 3929, but they did not fully pay the persons who had furnished material for the job, and they also defaulted in the performance of the other road building contracts, upon whieh the ¿Etna Company was also surety, so that it became liable to pay substantial sums in their behalf. Certain of the defendants holding the assignments above described had furnished material to the river road, while others had furnished material on other projects with whieh the surety company had no connection.

After the completion of the work, a controversy arose between Coss & Otto and the state road commission as to the liability of the commission to pay them additional sums for excavation and piling in connection with the construction of the road; and by an agreement of February 17, 1930, the matter was submitted to the Honorable J. Harold Brennan, judge of the circuit court of Ohio county, W. Va., for arbitration. He held that the state road commission was indebted to the contractors for this work in the sum of $20,-660.25. No part of this sum had been paid to the contractors when the bill of complaint in this ease was filed, and the ¿Etna Company, admitting that the money should be first used to satisfy the claims of’ all persons who had furnished labor or materials in the const ruction of the road, claimed that the surplus should ho paid to it by virtue of the assignment which it held. It therefore prayed that the fund bo so applied by the state road commission. The state road commission filed no answer and as to it the hill was taken pro confess©. The answers of Coss & Otto and of the defendants holding assignments made the contention that these assignments took priority over that of the surety company, even if the assignees furnished no material to this particular work; hut it was decided otherwise by this court in Lacy v. Maryland Casualty Co., 32 F.(2d) 48, 49, and the point is not raised on this appeal.

The American Surety Company of New York, a corporation, filed a bill of intervention in the ease on January 23, 1933, on the ground that it had an interest in the fund in the hands of the state road commission by reason of the facts which are now to ho sot out. At or about the time oC the execution of the road contract above described, the county court of Marshall county, W. Va., also entered into a contract with Coss & Otto for the improvement of an additional portion of the river road whieh, together with that covered by the state contract, constituted one continuous section of the highway. The American Surety Company on July 9, 1927, furnished a bond in the sum of $25,000, whereby it guaranteed to the county court of Marshall county the faithful performance of the county contract; and the application for this bond, as in the case of the ¿Etna Company, contained an assignment by the contractors of deferred payments on any moneys that might be due and payable to them at the time of a default, or that might thereafter become due and paya,ble; and provided that such moneys should he credited upon any claim that might bo made upon the surety by reason of its suretyship. The contractors also failed to pay all of the bills for materials furnished under the county contract, and the American Company consequently became liable therefor.

Although there were separate contracts for the two portions of the road, the prior transactions between the parties were such that the work was done as a single enterprise. In the early part of 1927, a bond issue in the sum of $50,000 had been put out by Marslia.ll county, W. Va., for the purpose of using the proceeds to improve a section of the river roa,d; and while the funds were in its possession on May 12,1927, it entered into an agreement with the state road commission for the joint improvement of the road extending in all for a distance of 6.4 miles. Under the terras of the agreement, the entire construction was to be committed to the supervision of the engineers of the state road commission, and it was designated by the commission as “Road Project 3087-A.” The county was to use- $2,500 of the fund in defraying other costs, and the balance of $47,-500 towards the improvement of the road, while the state commission was to be responsible for the cost of the residue. Bids were solicited and received on the project as a whole, and a proposal of Coss & Otto to do the entire work was found to be the lowest responsible bid and the work was awarded to them. But at this juncture, the parties were advised by the Attorney General of the state that the county authorities could not, lawfully turn over their funds to the state road commission, and accordingly the commission and the county court agreed that the project should he divided between them and that separate contracts with the contractors should he executed. Certain numbered stations or sections of the road wore assigned to each of the contracts. The contractors had bid on the basis of unit prices, the quantity of units be *580 ing estimated. Since the county court had only $47,500 to spend, its liability under its contract was limited to that sum, and the three parties agreed that in,the event that the cost of the construction of the county’s part of the project should exceed the sum of $47,500, the state road commission would pay the excess. By this arrangement, the terms of the original agreement between the state and county authorities were substantially ear-ried into effect.

During the progress of the work, monthly current estimates on both portions of the project were prepared by the engineers of the road commission, and those which related to the county contract were regularly paid by the county court. When the entire work was done, a final estimate was prepared covering the work done under the county portion of the project; but this estimate exceeded the sum of $47,500, and so 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Slavin v. Benson
493 F. Supp. 32 (S.D. New York, 1980)
Rembrandt Industries, Inc. v. Hodges International, Inc.
344 N.E.2d 383 (New York Court of Appeals, 1976)
Dolcater v. Manufacturers & Traders Trust Co.
106 F.2d 30 (Second Circuit, 1939)
State of Washington v. United States
87 F.2d 421 (Ninth Circuit, 1936)
State v. United States
87 F.2d 421 (Ninth Circuit, 1936)
Standard Acc. Ins. Co. v. Simpson
64 F.2d 583 (Fourth Circuit, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
64 F.2d 577, 1933 U.S. App. LEXIS 4161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aetna-casualty-surety-co-v-american-surety-co-ca4-1933.