S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C.

2019 Ohio 55
CourtOhio Court of Appeals
DecidedJanuary 8, 2019
Docket17CA1058
StatusPublished
Cited by6 cases

This text of 2019 Ohio 55 (S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C., 2019 Ohio 55 (Ohio Ct. App. 2019).

Opinion

[Cite as S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C., 2019-Ohio-55.]

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT ADAMS COUNTY

S.P. DRILLING SERVICES, INC., : : Case No. 17CA1058 Plaintiff-Appellant, : : vs. : DECISION AND JUDGMENT : ENTRY COOPER'S EXCAVATING LLC, : : Defendant-Appellee. : Released: 01/08/19 _____________________________________________________________ APPEARANCES:

Jeff Corcoran, Goshen, Ohio, for Appellant.

David E. Grimes, Law Office of David E. Grimes, West Union, Ohio, for Appellee. _____________________________________________________________

McFarland, J.

{¶1} This is an appeal from an Adams County Court judgment

denying Appellant, S.P. Drilling Services, Inc.'s, breach of contract claim

filed against Appellee, Cooper's Excavating LLC. On appeal, Appellant

contends that 1) the magistrate abused his discretion by adding a

performance requirement as a condition/term of the contract; 2) Appellee,

not Appellant, breached the contract; and 3) Appellant is entitled to

expectancy damages as a result of Appellee's breach. However, because we

have concluded that the trial court properly determined time was of the Adams App. No. 17CA1058 2

essence with respect to Appellant's performance of his obligations under the

contract, and that Appellant, rather than Appellee, breached the contract, we

find no merit to Appellant's first and second assignments of error and they

are overruled. Further, in light of our disposition of Appellant's first two

assignments of error, Appellant's third assignment of error has been rendered

moot and we do not address it. Accordingly, the decision of the trial court is

affirmed.

FACTS

{¶2} A review of the record reveals that Appellant filed a complaint

against Appellee alleging breach of contract and unjust enrichment on

September 26, 2016. Appellant thereafter filed an answer and also a

counterclaim alleging breach of contract. The litigation stems from a

construction contract dispute that arose in early April 2016, in which

Appellant was a subcontractor and Appellee was a general, or prime,

contractor, on a roadway improvement project involving the Ohio

Department of Transportation (hereinafter "ODOT").

{¶3} Appellee was awarded a contract by ODOT, as a general

contractor, and Appellant submitted a bid as a subcontractor for Appellee.

Appellant was awarded the bid, which involved the drilling of holes for

excavation bracing, in connection with the construction of a concrete box Adams App. No. 17CA1058 3

culvert, or bridge, in Adams County, Ohio. In addition to email and oral

communications between the parties regarding the work to be performed by

Appellant as the subcontractor, Appellee issued a purchase order to

Appellant on March 29, 2016 to install drilled shafts for excavation bracing

at a price of $14,000.00. The purchase order contained no other terms,

conditions or specifications.

{¶4} The record reveals that Appellant mobilized his equipment and

arrived at the job site at around noon on Tuesday, April 5, 2016, the day

after a traffic control device was installed to provide for a lane closure.

Appellant, however, delivered his equipment and left without beginning the

drilling operations that day, with a plan to return on Friday. In response,

Appellee obtained the services of another subcontractor who was able to

perform the work to completion the next day, at a substantially lower price.

Appellant was notified on Thursday, April 7, 2016, that the work had been

completed by someone else, and he was directed to remove his equipment

from the job site. Appellant thereafter sent Appellee an invoice for

$12,204.92 for "Mobilization costs and Profit caused by Cooper's

Excavating LLC breach of contract." Appellee's refusal to pay the invoice

led to the filing of Appellant's complaint. Adams App. No. 17CA1058 4

{¶5} The matter proceeded to a bench trial on November 15, 2017.

Dale Roe, Tammy Pschesang, and Sam Pschesang all testified on behalf of

Appellant. Dale Roe testified of his experience in the construction industry

and the fact that delays due to weather, approvals and steel deliveries are

common in the industry. The testimony was accepted by the trial court, over

the objection of Appellee, for purposes of educating the court. Tammy

Pschesang, the president and owner or S.P. Drilling Services, Inc. also

testified. She testified regarding the contents of the purchase order that was

provided by Appellee, and stated that although no other documents were

provided, she understood that eight holes were to be drilled as part of the

agreement. She also testified that Appellee knew that Appellant could not

be present on the job site on Wednesday, April 6 - Thursday, April 7, 2016,

and had approved Appellant's to return to work on Friday, April 8, 2016.

She testified that Appellant arrived at the job site at noon on Tuesday, April

5, 2016 for what was planned to be a two man/one day job.

{¶6} Sam Pschesang, the general superintendent of Appellant also

testified during the trial. He testified that he communicated with Edmund

McVey, who is employed by Appellee, regarding the job to be performed.

He testified that initial communications began in January of 2016 and that

although timing was discussed, the discussion was that the work would need Adams App. No. 17CA1058 5

to be performed the end of March or beginning of April. He testified that

after he received the purchase order from Appellee, McVey told him he

would be needed the first week of April, and that McVey understood

Appellant could not work Wednesday or Thursday of that week. He testified

that he had his equipment delivered to the job site on Tuesday of the week at

issue, because Appellee told him it would be unwise to bring it prior to

having traffic control in place, which was put into place on Monday.

{¶7} Mr. Pschesang testified that he could not begin the drilling work

on Tuesday for reasons that changed throughout the course of his testimony.

He initially testified that he could not begin drilling because he did not have

his auger bit with him on that day. He testified that he had to have his

equipment towed to the job site and the equipment and the auger bit could

not be towed at the same time. He later testified that the steel had not been

delivered to the site at the time he arrived on Tuesday, and that the industry

standard was that drilled holes need to be filled, with steel, on the same day

they were drilled. However, upon cross examination he agreed that he was

only contracted to drill holes and had no responsibility for filling the holes

with steel. Overall, his testimony indicated his understanding was that he

would mobilize and deliver his drilling equipment on Tuesday, be off

Wednesday and Thursday, and then return to begin drilling on Friday. Adams App. No. 17CA1058 6

{¶8} Edmund McVey testified on behalf of Appellee. He stated that

Appellee was a prime contractor for ODOT and mostly performed roadway

construction. He testified that although an email from Appellee to Appellant

in February estimated Appellant's portion of the job to begin the end of

March or beginning of April, he had later telephone conversations with Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. Canup
2025 Ohio 2443 (Ohio Court of Appeals, 2025)
United Assn. Local 168, Apprentice Educational Fund v. Robinson
2025 Ohio 2421 (Ohio Court of Appeals, 2025)
Chuma v. Patterson
2023 Ohio 1128 (Ohio Court of Appeals, 2023)
Zimmerview Dairy Farms, L.L.C. v. Protege Energy III., L.L.C.
2022 Ohio 1282 (Ohio Court of Appeals, 2022)
In re Adoption of T.C.W.
2020 Ohio 1484 (Ohio Court of Appeals, 2020)
Lawless v. Lawrence Cty. Bd. of Edn.
2020 Ohio 117 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sp-drilling-servs-inc-v-coopers-excavating-llc-ohioctapp-2019.