Mays v. Hartman

77 N.E.2d 93, 81 Ohio App. 408, 49 Ohio Law. Abs. 481, 37 Ohio Op. 228, 1947 Ohio App. LEXIS 605
CourtOhio Court of Appeals
DecidedOctober 20, 1947
Docket6836
StatusPublished
Cited by12 cases

This text of 77 N.E.2d 93 (Mays v. Hartman) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mays v. Hartman, 77 N.E.2d 93, 81 Ohio App. 408, 49 Ohio Law. Abs. 481, 37 Ohio Op. 228, 1947 Ohio App. LEXIS 605 (Ohio Ct. App. 1947).

Opinion

*482 OPINION

By MATTHEWS, PJ.

The plaintiff entered into a written contract with the defendants to do certain work and furnish certain material in making alterations in and additions to a dwelling-house in Cincinnati, as shown on the plans and specifications attached to and made a part of the contract. The plaintiffs agreed that all work would be done in a first-class workmanlike manner, and completed within 90 days from September 6th, 1945t— the date of the contract. They also agreed that the entire cost including material, labor, superintendent’s fees and profits “shall not exceed $4600.00, and the parties of the second part shall not be liable to the party-of the first part for any sum in excess thereof.”

The plaintiffs agreed to carry Workmen’s Compensation and public Liability Insurance, and to strive at all times to keep all costs as low as possible. Within the maximum cost of $4600.00, it was agreed that the plaintiffs were to be paid $2.00 per hour while on the job for superintending and had the right to employ all other workmen at the scale of wages in Cincinnati at the time the contract was made. It was agreed that the plaintiffs should be paid “every two weeks for all costs of material and labor furnished by them or under their supervision, upon delivery of receipted bills therefor.”

Upon completion of the alterations and additions the defendants agreed to pay the plaintiffs ten (10) per cent “for overhead charges and an additional ten (10) per cent for profit.” limited, however, as already noted, to a total cost including fees and profits of $4600.00.

The plaintiffs entered upon the work, and on September 20th, October 8th, October 20th, and November 8th, 19_45 delivered receipted bills for labor and material aggregating $2252.15, and the defendants in each instance paid the amounts to the plaintiffs within a few days after the bills were submitted.

The latter part of November (either the 27th or 30th) the plaintiffs delivered to the defendants receipted bills totaling $1476.59. There is dispute as to the details, but there is no dispute that the defendants did not pay this last item, but *483 after some discussion with the plaintiffs arranged for them to meet in the office of their attorney on December 5th, to dis-euss the situation. At that meeting the plaintiff produced other receipted bills which made the total unpaid to the defendant $1715.35.

There is no dispute that at this meeting of December 5th the plaintiffs asked for payment of the receipted bills and that the defendant Charles Hartman called attention to the status of the work on the dwelling and the possibility of mechanic’s liens being filed against the premises, and the parties made an estimate of what it would cost to complete the work required by the contract. Attention was called to the fact that the plaintiffs had already presented receipted bills for $3967.49, and that left only $632.51 as the maximum to be paid the plaintiffs for full performance of the contract. The total cost of the alterations and additions was estimated by the defendants at $1851.13 above the maximum of $4600.00. In reaching this figure the items were taken up separately and an estimate made. Both plaintiffs and defendants took part in this process, but to what extent the plaintiffs agreed is in dispute. The parties discussed the situation presented by the payments apparently being disproportionate to the progress of the work, but the meeting adjourned without aiiy agreement being reached of any payment being made.

On one hand, it is claimed that defendants refused to pay. On the other, it is claimed that there was no refusal to pay and that the meeting adjourned with the understanding that Ben Mays, who had attended the meeting on behalf of the plaintiffs, was to conclut J. K. Mays in the light of the developments at the meeting, and that another conference should be held thereafter. However, no such meeting was held. On December 6th,. 1945, which was the next day after this meeting, the plaintiffs discontinued all work on the dwelling house, and on March 23rd, 1946, filed this action on the contract to recover not only for the labor and materials actually furnished but also 10% for overhead and 10 % for profit “as provided in said contract” making a total, including $561.19 for extras, of $3020.89. The plaintiffs did not allege full performance of the contract. They alleged that the defendants had failed and refused to pay the amount of the receipted bills and that the plaintiffs had performed all conditions on their part to be performed up to that time.

The defendants by answer pleaded the terms of the contract, alleged that the plaintiffs had failed to complete the performance of their contract, and, denied generally the alie- *484 gations of the petition. By cross-petition, the defendants alleged that after the plaintiffs had abandoned the contract without excuse, they were required to expend $1514.20 in excess of the maximum contract price and they prayed judgment for that amount.

By reply to the answer and answer to the cross-petition, the plaintiffs alleged that they abandoned the work only after defendants’ refusal to pay and because thereof, and that the defendants’ interference prevented completion within the ninety days from date of contract.

The jury returned a verdict of $1510.00 for the plaintiffs and judgment was entered thereon. It is from that judgment that this appeal was taken.

Neither the pleadings nor the evidence raised any issue as to the making of the contract. The contract was in writing and the terms were undisputed. The only issues were as to which party had been guilty of a breach of the contract and the damage resulting therefrom.

It should be observed that the evidence is conflicting as to what took place at the conference on December 5th. The defendant, Charles R. Hartman, denied that he refused to pay. His testimony was that he delayed his decision to pay or not until he was informed of the attitude of the plaintiffs on the subject of the disproportion of payment and performance by the plaintiffs, and that the plaintiffs were to notify him thereon; and that without doing so the plaintiffs abandoned the contract.

Section 276 of Restatement of the Law of Contracts is:

“Unless the nature of a contract is such as to make performance on the exact day agreed upon of vital importance, or the contract in terms provides that it shall be so, failure by a promissor to perform his promise on the day stated in the promise does not discharge the duty of the other party.”

Assuming, without deciding’, that the absolute refusal of the defendants to pay would constitute a breach of a condition which would justify the plaintiffs in abandoning the contract, we are of the opinion that no such situation is presented here. As the evidence was conflicting, it became an issue of fact as to whether the first breach was committed by the defendants in refusing to pay, or whether the plaintiffs committed the first breach by abandoning the work the next day, instead of waiting a reasonable time»for the defendants to perform by *485 paying the installment, assuming that the defendants were not justified in so withholding payment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crockett Homes, Inc. v. Tracy
2024 Ohio 1464 (Ohio Court of Appeals, 2024)
Cafaro-Peachcreek Joint Venture Partnership v. Spanggard
2022 Ohio 4468 (Ohio Court of Appeals, 2022)
S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C.
2019 Ohio 55 (Ohio Court of Appeals, 2019)
Savoy Hospitality, L.L.C. v. 5839 Monore St. Assocs., L.L.C.
2015 Ohio 4879 (Ohio Court of Appeals, 2015)
Franklin Mgt. Industries, Inc. v. Far More Properties, Inc.
2014 Ohio 5437 (Ohio Court of Appeals, 2014)
Cranpark, Inc. v. Rogers Group, Inc.
721 F. Supp. 2d 613 (N.D. Ohio, 2010)
Bucher v. Schmidt, Unpublished Decision (8-2-2002)
2002 Ohio 3933 (Ohio Court of Appeals, 2002)
Brown v. Brown
630 N.E.2d 763 (Ohio Court of Appeals, 1993)
Murray v. Marbro Builders, Inc.
371 N.E.2d 218 (Ohio Court of Appeals, 1977)
Karl Kiefer MacHine Co. v. Henry Niemes, Inc.
80 N.E.2d 183 (Ohio Court of Appeals, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
77 N.E.2d 93, 81 Ohio App. 408, 49 Ohio Law. Abs. 481, 37 Ohio Op. 228, 1947 Ohio App. LEXIS 605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mays-v-hartman-ohioctapp-1947.