Molyneux v. Twin Falls Canal Co.

35 P.2d 651, 54 Idaho 619, 94 A.L.R. 1264, 1934 Ida. LEXIS 64
CourtIdaho Supreme Court
DecidedJune 29, 1934
DocketNo. 5963.
StatusPublished
Cited by39 cases

This text of 35 P.2d 651 (Molyneux v. Twin Falls Canal Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Molyneux v. Twin Falls Canal Co., 35 P.2d 651, 54 Idaho 619, 94 A.L.R. 1264, 1934 Ida. LEXIS 64 (Idaho 1934).

Opinion

*624 SUTPHEN, D. J.

This is an action to recover lost profits on account of an alleged breach of a drainage tunnel contract. The appellant, a Carey Act operating company, advertised for bids in September 1929, for the construction of several tunnels to be drilled from the face of canyon walls back toward lands on its project which had seeped, the purpose being to drain such seeped lands by means of such tunnels. The tunnel involved in the instant case was advertised to be 2,000 feet, more or less, in length.

The respondent was the successful bidder and on September 14, 1929, appellant and respondent entered into a written contract for the construction of the tunnel, by the terms of which respondent was to drill the tunnel according to the specifications made a part of the contract. The contract price was $9 per lineal foot for the first hundred feet, the price increasing 75$ per foot for every consecutive one hundred feet of tunnel thereafter constructed. Provision was made for monthly estimates as the work progressed and for the retention by appellant of fifteen per cent of the amount earned until the satisfactory completion of the contract. The following quotations from the specifications attached-to and made a part of said contract are particularly pertinent to this controversy:

“This contract is not assignable and after the contractor has signed the attached contract he will be liable for its construction. ' Said tunnel to be driven to an indefinite length, which is to be determined by the Twin Falls Canal Company.”

“Purpose of Tunnel Extension.

“This tunnel is being driven for the purpose of releasing seepage water at a level to be indicated by the Twin Falls Canal Company and will be terminated at the point where sufficient quantity of water is released according to the judgment and requirements of the Twin Falls Canal Company. The length of said tunnel cannot be determined for the reason that it is impossible to determine exactly where the desired flow of water will be obtained.”

*625 Respondent in bis complaint sets forth the execution of said contract and alleges that he began the construction of the tunnel and completed 879.4 lineal feet thereof, when on May 8, 1930, appellant ordered him to stop work. Respondent further alleges that said contract and specifications provide that said work was to be continued and the tunnel driven until the defendant should determine that a sufficient quantity of drainage water was released thereby and that when appellant ordered respondent to stop work it had not in good faith so determined but' that appellant continued to thereafter drive said tunnel a distance of 1109.6 lineal feet over and above the number of lineal feet of tunnel constructed by respondent, and that had appellant permitted respondent to proceed with the construction of the tunnel to the same length to which it was then constructed by appellant the respondent would have made a profit of $13,397.25, in which sum respondent sought damages.

Appellant’s demurrer to the complaint was overruled and it made answer admitting that the exhibit attached to the complaint is a copy of the contract entered into between appellant and respondent on September 14, 1929; admitting that respondent began construction of 'said tunnel and continued to work on the same until May 8, 1930, and drove said tunnel a distance of 879 feet; and generally denying all the allegations of respondent’s complaint not so admitted. As affirmative defenses appellant alleged that respondent voluntarily ceased work and with the consent of appellant surrendered all his rights under the contract to appellant, and that on May 8, 1930, and prior thereto, respondent and appellant agreed that ’said contract should be construed to mean and did mean that work on said tunnel might be stopped at any time by the appellant and that the question of whether water was released by the construction of the tunnel was not a determining factor as to when respondent should cease work under said contract, and that pursuant to the construction placed upon *626 said contract, on May 8, 1930, said contract was terminated by mutual consent.

During the trial respondent was permitted to amend his complaint to conform to the proof by increasing the alleged distance from 1109.6 to 1460.6 lineal feet, representing the amount of tunnel constructed by appellant after it ordered respondent to stop work, and by increasing the amount of damages claimed from $13,397.25 to $19,309.25. The jury rendered a verdict for respondent in the latter amount and judgment was entered thereon, and a motion for a new trial' denied. Appellant appeals both from the judgment and from the order denying the motion for a new trial.

Appellant contends that under the terms of the contract it had the absolute right to determine the length of the tunnel, and, therefore could terminate the contract at will without liability on its part for such termination.

On the other hand the respondent contends that under the contract the tunnel was to be driven until the appellant should in good faith determine that a sufficient quantity of drainage water was released thereby, and that even if the appellant had the absolute right to determine the length of the tunnel, the appellant could not terminate the contract before it had in good faith terminated the tunnel.

In construing a written instrument to determine what is intended by it the court must examine the whole instrument and if the meaning is clear and unambiguous and involves no absurdity or contradiction, the contract must be enforced according to the plain import of the language used. (Meir-Nandorf v. Milner, 34 Ida. 396, 201 Pac. 720; Hinsch v. Mothorn, 44 Ida. 539, 258 Pac. 540; Mark P. Miller Co. v. Butterfield-Elder Co., 32 Ida. 265, 181 Pac. 703; Naylor v. Simmons, 33 Ida. 320, 194 Pac. 94; Messinger v. Cox, 33 Ida. 363, 194 Pac. 473.)

The determination of the meaning and legal effect of such a contract is for the court alone (Mark P. Miller Co. v. Butterfield-Elder Co., supra; Messinger v. Cox, supra; First Nat. Bank v. Cruickshank, 38 Ida. 789, 225 Pac. 142), but if the court is unable to determine the meaning of the *627 contract from its terms, it should then hear testimony of witnesses to determine the meaning and intention of the parties as expressed by the contract (Wood River Power Co. v. Arkoosh, 37 Ida. 348, 215 Pac. 975; Tilden v. Hubbard, 25 Ida. 677, 138 Pac. 1133) and if there is a conflict in the evidence the question is for the jury under proper instructions from the court. (Miller Cattle Co. v. Francis, 35 Ariz. 535, 281 Pac. 211; Clark v. Herbert, 132 Okl. 272, 270 Pac. 329; Standard Acc. Ins. Co. v. Goldberg, 120 Okl. 108, 250 Pac. 892; Mitchell v. Vogele, 125 Okl. 176, 256 Pac. 906; Durand v. Heney, 33 Wash. 38, 73 Pac. 775.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Asbury Park, LLC v. Greenbriar Estate Homeowners' Ass'n
271 P.3d 1194 (Idaho Supreme Court, 2012)
Maslow v. Vanguri
896 A.2d 408 (Court of Special Appeals of Maryland, 2006)
CASTRINGO v. McQuade
106 P.3d 419 (Idaho Supreme Court, 2005)
Idaho State Bar v. Topp
925 P.2d 1113 (Idaho Supreme Court, 1996)
Sullivan v. Bullock
864 P.2d 184 (Idaho Court of Appeals, 1993)
Idaho State Bar v. Jenkins
816 P.2d 335 (Idaho Supreme Court, 1991)
Matter of Jenkins
816 P.2d 335 (Idaho Supreme Court, 1991)
Johnson v. Allied Stores Corp.
679 P.2d 640 (Idaho Supreme Court, 1984)
Werry v. Phillips Petroleum Company
540 P.2d 792 (Idaho Supreme Court, 1975)
Thomas v. Ballou-Latimer Drug Co.
442 P.2d 747 (Idaho Supreme Court, 1968)
Smith v. Sherwood & Roberts, Spokane, Inc.
441 P.2d 158 (Idaho Supreme Court, 1968)
Rogers v. Hendrix
438 P.2d 653 (Idaho Supreme Court, 1968)
Osborne v. Locke Steel Chain Co.
218 A.2d 526 (Supreme Court of Connecticut, 1966)
King v. Beatrice Foods Company
402 P.2d 966 (Idaho Supreme Court, 1965)
Minidoka County Ex Rel. Detweiler Bros. v. Krieger
399 P.2d 962 (Idaho Supreme Court, 1965)
Boesiger v. DeModena
399 P.2d 635 (Idaho Supreme Court, 1965)
Talisman Sugar Corp. v. Farmland Development Co.
156 So. 2d 392 (District Court of Appeal of Florida, 1963)
Ore-Ida Potato Products, Inc. v. Larsen
362 P.2d 384 (Idaho Supreme Court, 1961)
Williams v. Williams
354 P.2d 747 (Idaho Supreme Court, 1960)
Wohlschlegel v. Holst
346 P.2d 1051 (Idaho Supreme Court, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
35 P.2d 651, 54 Idaho 619, 94 A.L.R. 1264, 1934 Ida. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/molyneux-v-twin-falls-canal-co-idaho-1934.