Harris v. Faris-Kesl Construction Co.

89 P. 760, 13 Idaho 211, 1907 Ida. LEXIS 38
CourtIdaho Supreme Court
DecidedApril 4, 1907
StatusPublished
Cited by4 cases

This text of 89 P. 760 (Harris v. Faris-Kesl Construction Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harris v. Faris-Kesl Construction Co., 89 P. 760, 13 Idaho 211, 1907 Ida. LEXIS 38 (Idaho 1907).

Opinion

SULLIVAN, J.

This is an action brought to recover damages for alleged lost profits for breach of a contract in the sum of $4,504 and for balance due on account of $33.75, and for material furnished of the value of $252. The cause was tried by the court without a jury, and the court found the plaintiff was entitled to recover $3,897.06 as lost profits for the breach of the contract, and found against the plaintiff on the balance of account claimed, and in his favor for the value of the material furnished. No question is raised on this appeal in regard to second and third causes of action. The questions raised by the appeal are based on the judgment rendered for prospective profits. The contract upon which this suit is based was entered into by the plaintiff and defendant on the twenty-fifth day of July, 1905, for the construction of all flumes, trestles, etc., on the Canyon County Canal thereafter to be constructed in Canyon county. The parts of the contract material to a decision of this case are as follows:

“This Agreement, Made and entered into in duplicate, this 25th day of July, A. D., 1905, by and between Phil Harris, of Emmett, Canyon County, State of Idaho, the party of the first part, and Faris-Kesl Construction Company, Limited, a corporation, of Boise, County of Ada, State of Idaho, the party of the second part, Witnessed:

‘ ‘ That the said party of the first part, for and in consideration of the covenants, promises and agreements hereinafter contained, on the part and behalf of the said party of the second part, does hereby covenant, promise and agree to and with said party of the second part, that commencing with the 25th day of July, 1905, that he will, at his own cost, charge and expense, furnish all nails, bolts and washers of every nature and kind required and will do and perform all labor and work whatsoever required and necessary in the building and construction of all flumes, trestles, bridges, culverts, drain boxes, driving of piling, cutting of piling and preparing piling for trestles and bridges (except excavations, which shall be made by second party) on the Canyon Canal, in Boise and Canyon Counties, State of Idaho, in strict conformity with the plans and specifications furnished by the [216]*216Chief Engineer of the Canyon Canal Company, and to the satisfaction and acceptance of the said Engineer, and have the same completed and ready for use on or before the first day of April, A. D., 1906.

“The party of the second part, for and in consideration of the covenants, promises and agreements hereinbefore contained on the part and behalf of the said party of the first part, hereby agrees to and with said first party, that it will at the time and place desired by said first party, and when needed by said first party, furnish all lumber requisite and necessary for the construction of said flumes, trestles, bridges, culvert and drain boxes, and will deliver the same to said first party within 200 feet of each piece of work. The same' to be delivered, at option of said first party (if so ordered at the time of delivery) one-half at each end of each piece of work (provided, that if the said second party should run any of such lumber down the Payette River instead of delivering by wagon, then in that case said lumber is to be delivered by said second party within 1,000 feet of the line of the ditch, and where the same is to be used, and from such point said second party is to pay fifty cents per thousand feet on the cost of delivering such lumber from said point to where the same is to be used, and remainder to be paid by said first party; Provided, further, that if said second party should deliver any such lumber within said 200 feet as hereinbefore stated, then in that ease the expense thereof is to be wholly borne by said first party) and to make all excavations necessary for the laying of said flumes and trestles, and also to do all filling in around any flume, trestle, culvert or bridge that may be necessary and will pay to the said party of the first part the sum of five dollars and fifty cents for each and every one thousand feet of lumber (board measure) used under this contract.....

“The party of the second part hereby agrees to pay said first party the sums of $5.50 per thousand for lumber used and fifty cents per foot for piling used, at the time and in the manner following, to wit: Ninety (90 per cent) per centum of said contract prices, on the 20th day of each and [217]*217every month, the same to be determined and estimated by the said Engineer of the Canyon Canal Company, and the remainder of said contract prices upon the completion of all of the terms and conditions of this contract by said first party.”

It appears from the record that the appellant had contracted with the Canyon Canal Company for the construction of the Canyon canal, an extensive work, thirty-four miles long, having a large amount of flume and trestle work along the first sixteen miles of its course. The flume and trestle work the respondent had contracted with the appellant to build under said written contract. The contract was entered into July 25, 1905, and about August 1st, following, the respondent commenced work, and he stopped work about February, 1906.

The contract required the respondent to furnish all hardware and to do the work necessary in the building and construction of all flumes, trestles, etc., required to be constructed on said canal and required the appellant to furnish and deliver the lumber therefor. It appears from the record that after the respondent had placed in such flumes and trestles about two hundred and forty-eight thousand.feet of lumber, that, at the point at which he was then at work, there was not sufficient lumber to complete the work there, but there was lumber at other points on the canal, and it was suggested that respondent move his camp to the point where there was lumber, and a dispute arose between the manager of the appellant and the respondent as to who should pay the cost of moving the camp, and the respondent finally claimed under the terms of his contract that appellant was to furnish him the lumber “at the time and place desired by” him, and thereupon demanded that the lumber be furnished him at the point where he was then at work, known as the Plowman flume, and was informed by the appellant that they could not furnish him the lumber at that point, but that they had a great many thousand feet of lumber at other points along the line of the canal ready to be put in. The respondent [218]*218thereupon quit the contract and brought suit to recover prospective or future profits.

That provision of the contract on which the respondent particularly relies is as follows: “The said party of the second part hereby agrees to and with the said first party that it will at the time and place desired by said first party, and when needed by said first party, furnish all lumber requisite and necessary for the construction of said flumes, trestles,” etc.; and the allegation of the plaintiff in regard to the violation of that provision of the contract is as follows: “That the defendant failed to comply with said agreement in the following particular: The defendant did not furnish, and failed to deliver, to plaintiff the lumber, board measure, necessary, requisite and of sufficient amount and quantity so as to enable the plaintiff to construct or complete all flumes, trestles, bridges, culverts and drain boxes as was required to be constructed and completed under the terms of the said agreement.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Orlando v. Murphy
94 F.2d 426 (Fifth Circuit, 1938)
Molyneux v. Twin Falls Canal Co.
35 P.2d 651 (Idaho Supreme Court, 1934)
Arkansas Short Leaf Lumber Co. v. Hemler
281 F. 914 (Eighth Circuit, 1922)
Holmes County v. Burton Const. Co.
267 F. 769 (Fifth Circuit, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
89 P. 760, 13 Idaho 211, 1907 Ida. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harris-v-faris-kesl-construction-co-idaho-1907.