Murray v. Marbro Builders, Inc.

371 N.E.2d 218, 53 Ohio App. 2d 1, 7 Ohio Op. 3d 8, 1977 Ohio App. LEXIS 6970
CourtOhio Court of Appeals
DecidedJuly 13, 1977
DocketCA 613
StatusPublished
Cited by9 cases

This text of 371 N.E.2d 218 (Murray v. Marbro Builders, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Murray v. Marbro Builders, Inc., 371 N.E.2d 218, 53 Ohio App. 2d 1, 7 Ohio Op. 3d 8, 1977 Ohio App. LEXIS 6970 (Ohio Ct. App. 1977).

Opinion

*2 Pauvier, J.

In March 1973, plaintiff-appellee Carl Murray, a plumbing contractor, contracted with defendant-appellant Marbro Builders, Inc. (Marbro), to install all sewer systems, water lines and concrete curbing in a subdivision being developed by Marbro for an agreed price of $150,265.38. The contract recited that time was of the essence in the performance of the contract, and specified a completion date of November 1, 1973, for all work undertaken by Murray. Murray commenced performance of the contract in May 1973, and immediately encountered numerous delays in construction occasioned by subsurface rock formations and inclement weather. Work on the project nevertheless proceeded, although at a pace much slower than was originally anticipated, until August 29, 1973, when an inspector from the Clermont County Sanitary Engineering Department ordered the work to be stopped, citing Murray’s failure in numerous instances to conform construction of the sanitary sewer system to county depth specifications as the cause. Murray thereafter performed no additional work under his contract with Marbro, and was replaced several months later by another plumbing contractor, who corrected the defects in Murray’s construction of the sewer line and completed the substantial portion of work left unfinished by Murray. In May 1974, Murray, who had received payments totalling $3,172.66 under the contract, brought this action to recover the additional reasonable value of labor and materials conferred by Murray’s partial execution of the construction contract. Marbro, in its answer, denied Murray’s claim and asserted a counterclaim for various damages allegedly resulting from Murray’s breach of his contractual obligation. Following trial without a jury, the trial court awarded a judgment to Murray, on his complaint, for $22,434.04, and a judgment to Marbro, on its counterclaim, in the amount of $5,800. Marbro timely filed this appeal, presenting three assignments of error for review. '

Márbro, in its first assignment, asserts' that the judg *3 ment for Murray is contrary to law, arguing first that Murray’s breach of contract, prior to the performance of any substantial part thereof, precludes his recovery against Marbro. Indeed, a substantial body of early Ohio case law established the general rule that where a party has partially but not substantially performed a contract, and the failure to perform the balance of the contract is not excused, no recovery can be had upon the contract, even upon the theory of quantum meruit. See e. g., Mehurin v. Stone (1881), 37 Ohio St. 49; Abbott v. Inskip (1875), 29 Ohio St. 59; Goldssmith v. Hand (1875), 26 Ohio St. 101. See also Mays v. Hartman (1947), 77 N. E. 2d 93.

This court, however, is inclined to follow the more modern and, we believe, more equitable rule in conformity with that proposed by our brothers in the Eighth Appellate District of Ohio in Kirkland v. Archbold (1953), 68 Ohio Law Abs. 481. After briefly examining the history of the traditional rule in Ohio law, the Kirhland court determined that, as to defaulting contractors:

“An ever-increasing number of decisions of courts of last resort now modify the severity of this rule and permits defaulting contractors, where their work has contributed substantial value to the other contracting party’s property, to recover the value of work and materials on a quantum meruit basis, the recovery being diminished, however, to the extent of such damage as the contractor’s breach causes the other party. These decisions are based-on the theory of unjust enrichment. The action is not founded on the broken contract but on a quasi-contract to pay for the benefits received, which cannot be returned, diminished by the damages sustained because of the contractor’s breach of his contract. * * *
“The drastic rule of forfeiture against a defaulting contractor who has by his labor and materials materially enriched the estate of the other party, should, in natural justice, be afforded relief to the reasonable value of the work done, less whatever damage, the other party lias suffered.” Id., at 485, 486.

*4 See also 5A Corbin on Contracts 11, Sections 1124-1125 (1964); 12 Williston on Contracts 220, Sections 1473, 1475 (3d ed. 1970).

In the instant case, Murray managed to complete, in a workmanlike fashion, certain sections of sewer line which ultimately were incorporated into the subdivision sewer system delivered by Ma,rbro. Murray’s expenditure of the labor and materials involved in such construction thus conferred a substantial and permanent benefit upon Marbro which, in the absence of any payment therefor, Marbro should not in justice retain. We conclude, therefore, that Murray was entitled to recover the reasonable value of the improvements made upon the subdivision property in partial performance of his contract with Marbro, reduced by any damages suffered by the latter as a result of Murray’s subsequent breach. To the extent that certain dicta in Mays v. Hartman, supra, might require us to reach a contrary result, we decline to follow the statement of the rule therein contained.

Marbro additionally argues that, even if Murray is entitled to relief on the basis of quantum meruit, the judgment in the instant case, which was computed at rates varying from $8 to $12.50 per lineal foot of completed sewer line, improperly awarded to Murray a sum greater than he would have received' for equivalent work under the terms of the contract, which, Marbro contends, fix the rate of compensation at $7.50 . per lineal foot of pipe laid. ■ ■ -

However,' while recognizing the general rule that a defaulting contractor is permitted to recover no more for his services than would be allowed under the contract (11 Ohio Jurisprudence 2d 491, Contracts, Section 232), we find no- error in the amount awarded to Murray in the instant case. Thus, the language of the contract itself, which merely recites the: lump sum contract price and provides for paynienft thereof “as. the work progresses” furnishes no basis For Marbro’s assumption-that the rate of compensation owed to Murray may be determined by simply dividing the total contract price by the lineal footage of con *5 struction work to. be performed. 1 To the contrary, the record reflects that, dne to the recognized varying geológical characteristics of the subdivision property, certain phases of construction would require the expenditure of far more time and effort than others. Moreover, there is abundant evidence in :the record that those areas in which Murray successfully completed installation of the sewer lines contained unusually severe rock conditions not encountered elsewhere in the construction project. ; .

Thus, the trial court could properly conclude that the amount of relief requested by. and ultimately awarded to Murray in the instant case was, in fact, within the limits 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Cty. Bd. of Commrs. v. Hintz
2023 Ohio 1595 (Ohio Court of Appeals, 2023)
Gray v. Petronelli
2017 Ohio 2601 (Ohio Court of Appeals, 2017)
Auto-Owners Ins. v. Wheatley, Unpublished Decision (9-2-2005)
2005 Ohio 4650 (Ohio Court of Appeals, 2005)
Blue Ribbon Remodeling Co. v. Meistrich
709 N.E.2d 1261 (Hamilton County Municipal Court, 1999)
King v. Branch Motor Express Co.
435 N.E.2d 1124 (Ohio Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
371 N.E.2d 218, 53 Ohio App. 2d 1, 7 Ohio Op. 3d 8, 1977 Ohio App. LEXIS 6970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/murray-v-marbro-builders-inc-ohioctapp-1977.