Blue Ribbon Remodeling Co. v. Meistrich

709 N.E.2d 1261, 97 Ohio Misc. 2d 8, 1999 Ohio Misc. LEXIS 3
CourtHamilton County Municipal Court
DecidedJanuary 21, 1999
DocketNo. 97CV03566
StatusPublished
Cited by1 cases

This text of 709 N.E.2d 1261 (Blue Ribbon Remodeling Co. v. Meistrich) is published on Counsel Stack Legal Research, covering Hamilton County Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Ribbon Remodeling Co. v. Meistrich, 709 N.E.2d 1261, 97 Ohio Misc. 2d 8, 1999 Ohio Misc. LEXIS 3 (Ohio Super. Ct. 1999).

Opinion

Elizabeth B. Mattingly, Judge.

This matter came on for tidal on plaintiffs complaint for damages pursuant to a contract that it entered with defendant to install some concrete piers at his apartment buildings located on a hillside in the Hyde Park area of Cincinnati. Plaintiff Blue Ribbon asserts that it is entitled to a recovery based on contract and, in the alternative, based on quantum meruit for the work it performed in the amount of $9,000. Defendant Meistrich urges the court to. award a refund of the $3,000 down payment he paid on the contract, asserting that the contract was void because it was not timely completed. Moreover, since the work was only partially completed, defendant urges that Blue Ribbon is not entitled to any recovery under the theory of quantum meruit.

Sometime in the fall of 1994, defendant Meistrich obtained an estimate from plaintiff Blue Ribbon Remodeling (hereinafter referred to as “Blue Ribbon”) to fix foundation cracks that had developed in some apartment buildings he owned at 5015, 5009 and 5025 Shattuc Avenue. The President of Blue Ribbon is Mr. Fred Haboush. Haboush had twenty-eight years’ experience in remodeling and underpinning. He inspected the hillside and concluded that piers were needed to stabilize the foundations of the buildings. Blue Ribbon submitted a bid to do the necessary work; defendant Meistrich accepted the bid, since it was the lowest bid for completing the job.

On November 7, 1994, defendant Meistrich entered a contract with plaintiff Blue Ribbon pursuant to which Blue Ribbon agreed to install concrete piers to shore up the foundations of defendant’s apartment building at 5015 Shattuc Avenue. This contract called for Blue Ribbon to reinforce the foundation with the installation of seven piers, each five to six feet deep.1 The cost of the piers was $900 each, for a total due of $6,300. Defendant Meistrich paid plaintiff a $3,000 deposit on the work. The contract set no specific date for completion of the project; however, defendant Meistrich was told that the job could be completed in a few weeks.

Sometime in November 1994, plaintiff began digging holes for the piers. When four of the piers were already dug, an inspector from the city of Cincinnati told the workers- to stop working because he had determined that the permit and engineer’s drawings required by the city of Cincinnati had not been secured, and the piers that Blue Ribbon proposed to install did not meet code requirements. The inspector told Blue Ribbon that 4x4x6 piers were required and no more [11]*11work could be done until the necessary permits and drawings were submitted to the city. Meeting these requirements would cost additional money.

At that point, Blue Ribbon went to defendant and informed him that it could not do the work as now required by the city of Cincinnati for the price stated in the contract. Defendant Meistrich, concerned that holes had already been dug and dirt moved, agreed to a second contract, dated December 29, 1994, to get the job completed as expeditiously as possible. The second contract required Blue Ribbon to install additional piers as specified in the engineer’s drawings and the requirements of the building inspector. All work would be inspected by the engineer and building inspector, with all work to pass inspection and Blue Ribbon to provide all necessary materials. The new agreement called for installation of twelve piers for $12,000 with the original down payment applied against all sums due under the new contract.2

Work on the project proceeded, and there were concrete pours in January and February 1995. Soon thereafter, Harry Waggers and Bob Noble, the two subcontractors of Blue Ribbon who were digging the holes on the job, quit the work, citing the slippery and dangerous condition of the hillside on which the apartments were located. They did not work on the project after early February.3 Haboush testified that there were “snow and rain,” explaining that when it rains, it is impossible to dig with a backhoe, especially in a hillside area. The weather was typical for the Cincinnati area in January and February.

In late February or early March 1995, Blue Ribbon got another subcontractor, Bill Richardson, to work on the project. Richardson had worked for Blue Ribbon as a subcontractor on several occasions over two years on fifteen or twenty jobs. Richardson worked on the Shattuc project until June 6, 1995 at the latest. Although he continued to work there sporadically, and several dates were set for concrete to be poured, no concrete was poured after February 1995.4 Haboush did pay Richardson after the January 29, 1995 deadline had passed. It has not been established by a preponderance of the evidence what Richardson specifically [12]*12accomplished during this period.5 The parties agree that the work was not completed by January 29, 1995, the date specified for completion in the contract.

On July 1, 1995, defendant Meistrich hired Richardson to complete the work of installing the piers and to do additional work as well.6 When Blue Ribbon demanded full payment on its contract later in the summer, defendant Meistrich refused to pay the balance due under the December 29, 1995 contract, since the agreement was void, the plaintiff not having completed the work by the time required in the contract. Moreover, he had already paid Richardson for his work on the job.7

Blue Ribbon was unaware until after this lawsuit was filed that Richardson had entered into a contract with Meistrich to finish the job.8 Plaintiff states that when defendant hired Richardson, he violated a specific term of the agreement they had entered.

Twenty-five checks drawn on Blue Ribbon were presented as evidence in court of the expenses paid by Blue Ribbon on the job at issue. The court notes that only eighteen of the checks reference the Shattuc Avenue job, and some of the checks contradict testimony adduced at trial.9

What seems clear from the testimony of both Haboush and defendant Meist-rich is that from and after late February or early March 1995 when Richardson began to work on the job for Blue Ribbon, neither party spoke to the other about the legal status of the contract. Defendant Meistrich did not inform Blue Ribbon that he considered their agreement void at any time prior to entering an agreement with Richardson.10 Both parties maintain they were ultimately unable [13]*13to contact the other party despite numerous attempts.

Two specific provisions of the December 29, 1994 contract are relevant to the main issues for decision here. The first that governs the completion date of the work is as follows:

“Contractor agreed to complete the work set forth herein on or about [the] 29[th] day of January, 1995 subject to the availability of material, labor, weather condition or other circumstances beyond the control of Blue Ribbon Remodeling Company, Inc. Otherwise, the contract is void.”

The second provision deals with defendant’s inability to contract directly with any employees or agents of plaintiff. This section states in part as follows:'

“Owner shall not contract with employees or agents of Contractor to perform work (whether or not said work is covered by this contract) for them while any condition of this contract remains to be performed by either Contractor or Owner.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Auto-Owners Ins. v. Wheatley, Unpublished Decision (9-2-2005)
2005 Ohio 4650 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
709 N.E.2d 1261, 97 Ohio Misc. 2d 8, 1999 Ohio Misc. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-ribbon-remodeling-co-v-meistrich-ohmunicthamilto-1999.