Kirkland v. Archbold

113 N.E.2d 496, 68 Ohio Law. Abs. 481, 1953 Ohio App. LEXIS 950
CourtOhio Court of Appeals
DecidedFebruary 2, 1953
DocketNo. 22671
StatusPublished
Cited by5 cases

This text of 113 N.E.2d 496 (Kirkland v. Archbold) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kirkland v. Archbold, 113 N.E.2d 496, 68 Ohio Law. Abs. 481, 1953 Ohio App. LEXIS 950 (Ohio Ct. App. 1953).

Opinion

OPINION

By SKEEL, PJ.

This appeal comes to this court on questions of law from a judgment for the plaintiff in the sum of Two Hundred Dollars ($200.00) entered by the court without the interven[482]*482tion of a jury. The action is founded on a written contract dated August 2, 1949, whereby the plaintiff agreed to construct certain alterations and to do certain repairs to a dwelling house located at 2321 East 88th St., in the City of Cleveland for the sum of $6000.00.

The plaintiff claims to have started the work called for by said contract about August 5, 1949, and to have continued therewith until November 5, 1949, when he was forceably and wrongfully ejected from the premises by the defendant’s agent. It is plaintiff’s claim that at the time he was wrongfully prevented from proceeding further with the work, the reasonable value of the work and materials expended by him and his sub-contractors, in repairing the building at 2321 East 88 Street, was $2985.00; that only $800.00 had been paid thereon, leaving a balance due of $2185.00, which he claims as the amount of his damages.

The defendant’s defense is that her agent, as he had the right to do under the contract, tried to stop the plaintiff from proceeding to plaster the house until he. had replaced all wood lathe with rock lathe as called for by the contract and also before the outside walls were lined with rock wool. It is the claim of defendant that plaintiff was attempting to plaster the house in direct violation of paragraph 4 of the contract, which provides:

“All outside walls are to be lined with rock wool and rock lathe, superimposed thereon.”

It was the claim of the defendant that such work, of necessity, must be done before proceeding to plaster. Defendant also claims that much of the other work accomplished by the plaintiff was unsatisfactory and performed in an unworkmanlike manner, and was of no value.

The trial was almost completely conducted by the court on the premises of the building being repaired, except for short periods when they gathered in a neighborhood settlement house. The record clearly shows that the court considered as evidence the things observed by him during the trial in the building, and that no attempt was made to describe what was thus observed into the bill of exceptions. This fact is demonstrated many places in the bill. We quote from page 127 as typical:

“Q. What did you do in the hall, if anything?
“A. Well, along the hallway, £>ut in a partition, you know Then I straightened out this partition. This partition was originally there (indicating).
“Q. What partition is that?
“A. This partition here (indicating).
“Q. Between two bedrooms downstairs?
[483]*483“A. Well, this is a partition, comes across the building from the front, made a living room and a bedroom here. Come down this hallway into this bedroom and there is a door here (indicating).”

The court, in rendering judgment for the plaintiff, held that the plaintiff was in default under the provisions of the contract in that he was attempting to install the plaster before the rock wool was put in the outside walls, and the wood lathe was replaced by rock lathe, as called for by Paragraph 4 of the contract above quoted, and that the defendant acted within her rights in preventing plaintiff from proceeding with the plastering until such work had been completed.

Paragraph 20 of the contract provides:

“The Owner agrees to pay the Contractor, as follows: $1,000.00 when satisfactory work has been done for ten days; an additional $1,000.00 when twenty days work has been completed; an additional $1,000.00 when thirty days work has been completed, and $1,000.00 on completion of the contract. $2000.00 shall be paid within thirty days after the completion of the contract.”

The court held that paragraph 20 of the contract provided for progressive payments and that such provisions “are sever-able from the remainder of the contract and if there has been full or substantial compliance with these provisions, the plaintiff is entitled to recover such progress payment.” The court further held that the defendant having paid $800.00 on the first payment provided for, was an admission that ten days of satisfactory work had been done and therefore rendered judgment for $200.00, the balance due on the first payment.

The plaintiff claims the following errors:

“1. The judgment of the court below for plaintiff in the amount of only $200.00 was inadequate.
“2. The judgment of the court below, in limiting recovery to $200.00 is manifestly against the greater weight of the evidence.
“3. The judgment of the court below, in limiting recovery to $200.00 is contrary to law.
“4. The trial court erred in overruling plaintiff’s motion for a new trial.
“5. Errors in the exclusion and admission of evidence.
“6. Other errors apparent from the face of the record.”

The court committed error prejudicial to the rights of plaintiff in holding that the provisions of the contract were sever-able. The plaintiff agreed to make certain repairs and improvements on the defendant’s property for which he was to be paid Six Thousand Dollars. The total consideration was to be paid for the total work specified in the contract. The fact [484]*484that a schedule of payments was set up based on the progress of the work does not change the character of the agreement. (Lumber Co. v. Purdum, 41 Oh St 373.)

The court found that the plaintiff and not the defendant breached the agreement, leaving the job without just cause, when the work agreed upon was far from completed. In fact, the plaintiff by his pleadings and evidence does not attempt to claim substantial performance on his part. The question is, therefore, clearly presented on the facts as the court found them to be, as to whether or not the plaintiff being found in default can maintain a cause of action for only part performance of his contract.

The earlier case law of Ohio has refused to permit a plaintiff to found an action on the provisions of a contract where he himself is in default. The only exception to the rule recognized is where the plaintiff has substantially performed his part of the agreement.

In the case of Larkin v. Buck, 11 Oh St 562, the syllabus provides:

“B. agreed to work for L. on his farm ‘for six months certain, at eleven dollars per month,’ no time being specified in the agreement when payment was to be made. B left the service of L. at the expiration of the first month, without cause, and against the wish of L. and brought suit to recover of L. for the month’s service. Held, that the contract was entire and that suit could not, under the circumstances, be maintained by L. for such partial performance.”

Also in the case of Ashley v. Henahan, 56 Oh St 559, parag. 1 of the syllabus provides:

“1. The general rule is, that one who seeks to recover on a contract must show substantial performance on his part, and this rule applies to a ‘building contract’ as to any other.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blue Ribbon Remodeling Co. v. Meistrich
709 N.E.2d 1261 (Hamilton County Municipal Court, 1999)
State v. Lane
397 N.E.2d 1338 (Ohio Supreme Court, 1979)
Murray v. Marbro Builders, Inc.
371 N.E.2d 218 (Ohio Court of Appeals, 1977)
DiMario v. Heeks
351 A.2d 837 (Supreme Court of Rhode Island, 1976)
Bainum v. McGrady
117 A.2d 462 (District of Columbia Court of Appeals, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
113 N.E.2d 496, 68 Ohio Law. Abs. 481, 1953 Ohio App. LEXIS 950, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kirkland-v-archbold-ohioctapp-1953.