Auto-Owners Ins. v. Wheatley, Unpublished Decision (9-2-2005)

2005 Ohio 4650
CourtOhio Court of Appeals
DecidedSeptember 2, 2005
DocketNo. 2004-T-0043.
StatusUnpublished

This text of 2005 Ohio 4650 (Auto-Owners Ins. v. Wheatley, Unpublished Decision (9-2-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Auto-Owners Ins. v. Wheatley, Unpublished Decision (9-2-2005), 2005 Ohio 4650 (Ohio Ct. App. 2005).

Opinion

OPINION
{¶ 1} This lawsuit was filed by Auto-Owners Insurance Company ("Auto-Owners") as a subrogation action to recover the amount of $78,750, which was paid to William Stoneman and Rochelle Stoneman (collectively referred to as "the Stonemans") after the horse arena being constructed for them by John R. Wheatley, d.b.a. Wheatley Construction ("Wheatley") collapsed.

{¶ 2} Wheatley, in turn, sued the Stonemans in the same litigation for the amount due under the contract to construct the horse arena that had collapsed. An additional claim against the Stonemans alleged that they had committed a forgery against Wheatley. Wheatley also sued Auto-Owners for breach of contract and for the wrongful issuance of an IRS Form 1099, which resulted in additional tax liability to him.

{¶ 3} Finally, the Stonemans sued Wheatley for damages to recover for negligent construction of their arena, for breaches of two contracts, and for fraudulent misrepresentations.

{¶ 4} The court below rendered judgment to Auto-Owners in the amount of $78,750 against Wheatley. It also rendered judgment in favor of Wheatley in the amount of $27,468.62 against the Stonemans. It rendered judgment in favor of Auto-Owners with respect to the breach of contract claim and the "1099 claim" against it by Wheatley and rendered judgment against the Stonemans on their claim for negligent construction and breach of contract against Wheatley. Finally, it held that there had been no forgery committed by the Stonemans. For the reasons that follow, we modify the judgment of the trial court and affirm the judgment as modified.

{¶ 5} The matter was heard before a magistrate. The parties had agreed prior to the hearing that the decision of the magistrate would be binding upon them and their rights to file objections to his decision were waived. The court adopted the magistrate's decision, and the matter is now in this court upon an appeal and a cross-appeal.

{¶ 6} The Stonemans contracted with Wheatley for the construction of a horse arena in the spring of 2000. They agreed to pay Wheatley the cost of materials plus $10,000 for his labor as the total price for the construction. On October 8, 2000, the barn collapsed. There was testimony from a civil engineer hired by Auto-Owners that the reason the barn collapsed was due to negligent construction by Wheatley; and the magistrate found that "it was due to [Wheatley's] negligent construction that the building collapsed."

{¶ 7} Auto-Owners calculated the replacement cost of the arena at the time of its collapse to be $76,862; however, its coverage with the Stonemans was limited to $75,000, plus another 5% for cleanup costs, so it determined its total obligation to be $78,750, consisting of $75,000 to replace the arena and $3,750 for removal of debris. Auto-Owners issued two checks in payment of this claim. One check was issued for $50,000, and the other check for $28,750. Both checks had the Stonemans and Wheatley as payees. Auto-Owners also required the parties to memorialize their oral agreement in order to state a sum certain for their agreement. The parties did so and created a document to reflect their agreed upon price for construction of the horse arena to be $83,500.

{¶ 8} Thereafter, the Stonemans and Wheatley entered into a second contract, this time in writing, for construction of the horse arena. This second arena was to cost the Stonemans $60,000. The reason for the difference in price between the first arena project and the second arena project was that much of the material from the first project was still usable in the second project. Two weeks after the contract for the second project was entered into, the Stonemans paid Wheatley the sum of $50,000.

{¶ 9} Wheatley and his crew walked off the second project on January 23, 2001, and the Stonemans expended the sum of $23,972.50 to finish the project. The magistrate found this amount to be "reasonable and necessary to complete the construction of the horse arena and remedy some of the negligent aspects of Wheatley's construction." He also found that the Stonemans' total out-of-pocket expense for both construction projects was $56,031.38.

{¶ 10} In awarding Wheatley the sum of $27,468.62 on his breach of contract claim against the Stonemans, the magistrate deducted the Stonemans' out-of-pocket expense, or $56,031.38, from the original contract price for the construction of the horse arena, which it considered to be $83,500, and computed the net figure as the award.

{¶ 11} The Stonemans' first assignment of error is as follows:

{¶ 12} "The trial court erred by granting judgment to Wheatley on his breach of contract claim against the Stonemans."

{¶ 13} As a reviewing court, we will uphold the judgment of the trial court and will not find it to be contrary to the weight of the evidence if there is some competent and credible evidence to support the judgment.1

{¶ 14} We note at the outset that there is a discrepancy between the amount found by the magistrate to have been expended out of pocket by the Stonemans and the amounts comprising that total in the testimony at trial. The magistrate found that the Stonemans had out-of-pocket expenses for the two arenas of $56,031.38, whereas the unchallenged testimony was that the Stonemans paid Wheatley a $15,000 down payment, paid $10,318.88 for steel, paid $3,500 for crane rental, paid $6,540 for debris removal, and an additional $23,972.50 to complete construction of the second arena after Wheatley walked off the job. The total of these figures is $59,331.38, and not $56,031.38.

{¶ 15} The Stonemans emphasize the fact that Wheatley sued them only pursuant to the first agreement, and that because his negligence caused the first arena to collapse, this same negligence put him in breach of the first agreement and, therefore, he is not entitled to any recovery, citing W. Wagner G. Wagner Co., L.P.A. v. Block.2 The Stonemans argue that they contracted for a new horse arena and received in return only a pile of rubble, so Wheatley should recover nothing, because they got nothing for their money.

{¶ 16} In order to properly analyze this assignment of error, we invoke certain principles of contract law to assist us.

{¶ 17} First of all, we invoke the principle of quantum meruit to prevent unjust enrichment of the Stonemans, at the expense of Wheatley:

{¶ 18} "Quantum meruit is an equitable doctrine based upon the concept that a party should not be unjustly enriched at the expense of another."3

{¶ 19} The court in the Blue Ribbon case, with a fact situation similar to the one in this case, discussed various approaches considered by the courts to apply the doctrine of quantum meruit and to determine the amount of contract damages where there is less than full performance:

{¶ 20} "The traditional rule is that where a party has partially but not substantially performed his promise contained in an entire contract, and the failure to perform the balance of the contract is not excused, no recovery can be had upon a quantum meruit theory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murray v. Marbro Builders, Inc.
371 N.E.2d 218 (Ohio Court of Appeals, 1977)
W. Wagner G. Wagner Co., L.P.A. v. Block
669 N.E.2d 272 (Ohio Court of Appeals, 1995)
Maloney v. General Tire Sales, Inc.
296 N.E.2d 831 (Ohio Court of Appeals, 1973)
Pennant Moldings, Inc. v. C & J Trucking Co.
464 N.E.2d 175 (Ohio Court of Appeals, 1983)
Walter v. National City Bank
330 N.E.2d 425 (Ohio Supreme Court, 1975)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Shear v. West American Insurance
464 N.E.2d 545 (Ohio Supreme Court, 1984)
Paugh & Farmer, Inc. v. Menorah Home for Jewish Aged
472 N.E.2d 704 (Ohio Supreme Court, 1984)
Fantozzi v. Sandusky Cement Products Co.
597 N.E.2d 474 (Ohio Supreme Court, 1992)
Blue Ribbon Remodeling Co. v. Meistrich
709 N.E.2d 1261 (Hamilton County Municipal Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 4650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/auto-owners-ins-v-wheatley-unpublished-decision-9-2-2005-ohioctapp-2005.