Gray v. Petronelli

2017 Ohio 2601
Ohio Court of Appeals·Decided May 1, 2017·No. 2016-T-0030·Published·Cited by 4 cases

Opinion

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT TRUMBULL COUNTY, OHIO

KAREN GRAY, : OPINION

Plaintiff-Appellee, :

CASE NO. 2016-T-0030

- vs - :

DONALD PETRONELLI, :

Defendant, :

PETRONELLI DESIGN : & CONSTRUCTION INC., :

Defendant-Appellant.

Civil Appeal from the Trumbull County Court of Common Pleas. Case No. 2003 CV 00815.

Judgment: Affirmed.

Thomas J. Wilson, Comstock, Springer & Wilson Co., L.P.A., 100 Federal Plaza East, Suite 926, Youngstown, OH 44503-1811 (For Plaintiff-Appellee).

Randil J. Rudloff, Guarnieri & Secrest, P.L.L., 151 East Market Street, P.O. Box 4270, Warren, OH 44482 (For Defendant-Appellant).

TIMOTHY P. CANNON, J.

{¶1} Appellant, Petronelli Design & Construction Inc. (“PDC”), appeals from a judgment of the Trumbull County Court of Common Pleas, which modified and adopted the magistrate’s decision and awarded PDC a judgment in the amount of $6,323.08.

The case arose from a residential construction contract between PDC and appellee, Karen Gray, and her husband, James Gray.

{¶2} Construction began on May 21, 2002. Three different construction contracts were executed: September 1, 2001; April 1, 2002; and September 6, 2002. These contracts were based on architectural plans submitted by David Rockman. The final contract refers to Rockman’s revised plans of April 21, 2002. The April 21 Rockman plans were acknowledged with a handwritten notation by PDC on May 20, 2002, one day prior to the start of construction.

{¶3} The contract was divided into “allowances” (i.e., items the Grays were responsible for paying directly to vendors themselves) and “fixed costs” (i.e., the items PDC would pay for and for which the Grays would provide reimbursement through bank draws). The “fixed costs” included, inter alia, various items of construction jointly referred to in the contract as the “Petronelli Package.” The parties also agreed that any changes to the contract involving extra costs would require a written and signed change order. The final contract provided for $229,382 in “fixed costs” and $3,375 for “allowances.”

{¶4} The Grays eventually terminated PDC from the construction project after significant work had been performed, and they hired other tradesmen to complete the home. The Grays had paid PDC a total of $158,152.

{¶5} On March 31, 2003, Ms. Gray filed a complaint against PDC and Donald Petronelli, individually, asserting causes of action for breach of contract and fraud. She filed a first amended complaint on July 15, 2003, adding a cause of action for slander of title. The trial court granted a motion filed by defendants to join Mr. Gray as an

involuntary plaintiff. The Grays subsequently filed a second amended complaint and an answer to the counterclaim.

{¶6} The Grays alleged PDC breached the contract by failing to comply with the terms of the contract and performing in an unworkmanlike manner. Specifically, they alleged the following items of faulty work: PDC did not follow the April 21 Rockman plans to use 13 courses of block in the basement, rather than 12, which resulted in an exposed, low-hanging steel I-beam over the basement stairs; the kitchen window does not open properly; the balcony floor leaks as a result of poor installation; and water began seeping into the basement within two years of construction.

{¶7} The Grays also claimed they paid other tradesmen to complete the following items not finished by PDC before the contract was terminated: electrical work; carpentry work; maple trim and materials; gutters and downspouts; washed gravel; overhead garage door; underlayment in tile areas; dumpsters; stair system and installation; garage steps; and lot clearing.

{¶8} The Grays further alleged they were entitled to a reduction of the contract price because certain written change orders resulted in reductions in the “fixed cost” portion of the contract.

{¶9} Defendants filed an answer and a counterclaim for money due on the contract and foreclosure on a mechanic’s lien they had filed against the property. Defendants also alleged causes of action for fraud and defamation.

{¶10} Prior to a scheduled jury trial, on December 17, 2004, the case was stayed due to Mr. Gray filing for Chapter 13 bankruptcy status. On October 4, 2010, the case was returned to the trial court’s active docket. The matter was referred to the

magistrate for a trial to the court, which began, following numerous continuances, on December 29, 2014. Prior to trial, Mr. Gray was removed as an involuntary plaintiff due to a bankruptcy discharge. Additionally, following Ms. Gray’s case-in-chief, Donald Petronelli was dismissed as an individual defendant. The sole remaining parties were Plaintiff Karen Gray and Defendant PDC.

{¶11} The magistrate issued a decision, with findings of fact and conclusions of law, on September 1, 2015. The magistrate found PDC breached the contract by installing 12 courses of basement block, rather than 13; not paying for the maple trim and materials as required under the contract; failing to install a subfloor in the tile areas; and failing to install the stair system. The magistrate found PDC owed Ms. Gray damages in the amount of $54,799.92: $5,000 for diminution in value due to the exposed I-beam and $49,799.92 for the cost to complete the project.

{¶12} The magistrate did not find that Ms. Gray breached the contract, but did award PDC damages on a quantum meruit basis as a result of work and materials for which it had not been reimbursed. The magistrate stated: “Petronelli seeks payment for the balance due under the contract. However, the Court has previously found herein that Petronelli breached the contract first by refusing to provide the maple trim and casings which were part of the Petronelli Package. However, Petronelli is still entitled to payment for the work performed.” Using the $49,799.92 amount owed to Ms. Gray for the cost to complete the project, the magistrate found the value of the work performed by PDC was $170,101.08, of which Ms. Gray had already paid $158,152.00. Thus, PDC was entitled to $11,949.08 minus the $5,000 for faulty workmanship. This left a $6,949.08 award in favor of PDC.

{¶13} The magistrate further found that Ms. Gray’s claims for fraud and slander of title and PDC’s claims for fraud and defamation were not supported by any evidence at trial.

{¶14} Both parties filed objections to the magistrate’s decision. The trial court entered its order modifying and adopting the magistrate’s decision on March 3, 2016. The trial court found merit with only one of the objections: the amount of written change orders that reduced the contract price was not properly deducted from the “fixed costs” portion. Ms. Gray was thus entitled to an additional credit in the amount of $626, which reduced PDC’s award to $6,323.08.

{¶15} Regarding the mechanic’s lien filed by PDC, the trial court adopted the magistrate’s recommendation and held it “is a good and valid lien upon the Gray real estate only as to the amount awarded to Petronelli herein; $6,323.08. As to the demand for foreclosure of the mechanic’s lien, the Court finds Petronelli has not filed the appropriate title reports necessary to commence such foreclosure.”

{¶16} PDC appealed from this order and asserts four assignments of error for our review.

{¶17} Its first assignment of error states:

The court erred in failing to award PDC the contract price of $232,757.00, plus change orders of $3,970.00, plus excess allowance expenditures of $1,205.00, for a total of $237,932.00, less payments made by appellee of $158,152.00 and less appellee’s cost to complete the contract of $49,799.92, leaving a net due PDC of $29,980.08.

{¶18} Under its first assignment of error, PDC’s first argument is that “the Magistrate did not use the correct determination of damages in arriving at her decision.”

This is a question of law, which we review de novo. Cleveland Elec. Illum. Co. v. Pub. Util. Comm. of Ohio, 76 Ohio St.3d 521, 523 (1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Gray v. Petronelli, 2017 Ohio 2601 (Ohio Ct. App. 2017).

2017 Ohio 2601 (Gray v. Petronelli) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Olive Oil, L.L.C. v. Cleveland Elec. Illum. Co.
2021 Ohio 2309 (Ohio Court of Appeals, 2021)
Sabath v. Sabath
2020 Ohio 4638 (Ohio Court of Appeals, 2020)
Le v. Li
2019 Ohio 5269 (Ohio Court of Appeals, 2019)
Wildcat Drilling, L.L.C. v. Discovery Oil & Gas, L.L.C.
2018 Ohio 4015 (Ohio Court of Appeals, 2018)