Gray v. Petronelli

2017 Ohio 2601
CourtOhio Court of Appeals
DecidedMay 1, 2017
Docket2016-T-0030
StatusPublished
Cited by4 cases

This text of 2017 Ohio 2601 (Gray v. Petronelli) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gray v. Petronelli, 2017 Ohio 2601 (Ohio Ct. App. 2017).

Opinion

[Cite as Gray v. Petronelli, 2017-Ohio-2601.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

TRUMBULL COUNTY, OHIO

KAREN GRAY, : OPINION

Plaintiff-Appellee, : CASE NO. 2016-T-0030 - vs - :

DONALD PETRONELLI, :

Defendant, :

PETRONELLI DESIGN : & CONSTRUCTION INC., : Defendant-Appellant.

Civil Appeal from the Trumbull County Court of Common Pleas. Case No. 2003 CV 00815.

Judgment: Affirmed.

Thomas J. Wilson, Comstock, Springer & Wilson Co., L.P.A., 100 Federal Plaza East, Suite 926, Youngstown, OH 44503-1811 (For Plaintiff-Appellee).

Randil J. Rudloff, Guarnieri & Secrest, P.L.L., 151 East Market Street, P.O. Box 4270, Warren, OH 44482 (For Defendant-Appellant).

TIMOTHY P. CANNON, J.

{¶1} Appellant, Petronelli Design & Construction Inc. (“PDC”), appeals from a

judgment of the Trumbull County Court of Common Pleas, which modified and adopted

the magistrate’s decision and awarded PDC a judgment in the amount of $6,323.08. The case arose from a residential construction contract between PDC and appellee,

Karen Gray, and her husband, James Gray.

{¶2} Construction began on May 21, 2002. Three different construction

contracts were executed: September 1, 2001; April 1, 2002; and September 6, 2002.

These contracts were based on architectural plans submitted by David Rockman. The

final contract refers to Rockman’s revised plans of April 21, 2002. The April 21

Rockman plans were acknowledged with a handwritten notation by PDC on May 20,

2002, one day prior to the start of construction.

{¶3} The contract was divided into “allowances” (i.e., items the Grays were

responsible for paying directly to vendors themselves) and “fixed costs” (i.e., the items

PDC would pay for and for which the Grays would provide reimbursement through bank

draws). The “fixed costs” included, inter alia, various items of construction jointly

referred to in the contract as the “Petronelli Package.” The parties also agreed that any

changes to the contract involving extra costs would require a written and signed change

order. The final contract provided for $229,382 in “fixed costs” and $3,375 for

“allowances.”

{¶4} The Grays eventually terminated PDC from the construction project after

significant work had been performed, and they hired other tradesmen to complete the

home. The Grays had paid PDC a total of $158,152.

{¶5} On March 31, 2003, Ms. Gray filed a complaint against PDC and Donald

Petronelli, individually, asserting causes of action for breach of contract and fraud. She

filed a first amended complaint on July 15, 2003, adding a cause of action for slander of

title. The trial court granted a motion filed by defendants to join Mr. Gray as an

2 involuntary plaintiff. The Grays subsequently filed a second amended complaint and an

answer to the counterclaim.

{¶6} The Grays alleged PDC breached the contract by failing to comply with

the terms of the contract and performing in an unworkmanlike manner. Specifically,

they alleged the following items of faulty work: PDC did not follow the April 21 Rockman

plans to use 13 courses of block in the basement, rather than 12, which resulted in an

exposed, low-hanging steel I-beam over the basement stairs; the kitchen window does

not open properly; the balcony floor leaks as a result of poor installation; and water

began seeping into the basement within two years of construction.

{¶7} The Grays also claimed they paid other tradesmen to complete the

following items not finished by PDC before the contract was terminated: electrical work;

carpentry work; maple trim and materials; gutters and downspouts; washed gravel;

overhead garage door; underlayment in tile areas; dumpsters; stair system and

installation; garage steps; and lot clearing.

{¶8} The Grays further alleged they were entitled to a reduction of the contract

price because certain written change orders resulted in reductions in the “fixed cost”

portion of the contract.

{¶9} Defendants filed an answer and a counterclaim for money due on the

contract and foreclosure on a mechanic’s lien they had filed against the property.

Defendants also alleged causes of action for fraud and defamation.

{¶10} Prior to a scheduled jury trial, on December 17, 2004, the case was

stayed due to Mr. Gray filing for Chapter 13 bankruptcy status. On October 4, 2010, the

case was returned to the trial court’s active docket. The matter was referred to the

3 magistrate for a trial to the court, which began, following numerous continuances, on

December 29, 2014. Prior to trial, Mr. Gray was removed as an involuntary plaintiff due

to a bankruptcy discharge. Additionally, following Ms. Gray’s case-in-chief, Donald

Petronelli was dismissed as an individual defendant. The sole remaining parties were

Plaintiff Karen Gray and Defendant PDC.

{¶11} The magistrate issued a decision, with findings of fact and conclusions of

law, on September 1, 2015. The magistrate found PDC breached the contract by

installing 12 courses of basement block, rather than 13; not paying for the maple trim

and materials as required under the contract; failing to install a subfloor in the tile areas;

and failing to install the stair system. The magistrate found PDC owed Ms. Gray

damages in the amount of $54,799.92: $5,000 for diminution in value due to the

exposed I-beam and $49,799.92 for the cost to complete the project.

{¶12} The magistrate did not find that Ms. Gray breached the contract, but did

award PDC damages on a quantum meruit basis as a result of work and materials for

which it had not been reimbursed. The magistrate stated: “Petronelli seeks payment for

the balance due under the contract. However, the Court has previously found herein

that Petronelli breached the contract first by refusing to provide the maple trim and

casings which were part of the Petronelli Package. However, Petronelli is still entitled to

payment for the work performed.” Using the $49,799.92 amount owed to Ms. Gray for

the cost to complete the project, the magistrate found the value of the work performed

by PDC was $170,101.08, of which Ms. Gray had already paid $158,152.00. Thus,

PDC was entitled to $11,949.08 minus the $5,000 for faulty workmanship. This left a

$6,949.08 award in favor of PDC.

4 {¶13} The magistrate further found that Ms. Gray’s claims for fraud and slander

of title and PDC’s claims for fraud and defamation were not supported by any evidence

at trial.

{¶14} Both parties filed objections to the magistrate’s decision. The trial court

entered its order modifying and adopting the magistrate’s decision on March 3, 2016.

The trial court found merit with only one of the objections: the amount of written change

orders that reduced the contract price was not properly deducted from the “fixed costs”

portion. Ms. Gray was thus entitled to an additional credit in the amount of $626, which

reduced PDC’s award to $6,323.08.

{¶15} Regarding the mechanic’s lien filed by PDC, the trial court adopted the

magistrate’s recommendation and held it “is a good and valid lien upon the Gray real

estate only as to the amount awarded to Petronelli herein; $6,323.08. As to the demand

for foreclosure of the mechanic’s lien, the Court finds Petronelli has not filed the

appropriate title reports necessary to commence such foreclosure.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Olive Oil, L.L.C. v. Cleveland Elec. Illum. Co.
2021 Ohio 2309 (Ohio Court of Appeals, 2021)
Sabath v. Sabath
2020 Ohio 4638 (Ohio Court of Appeals, 2020)
Le v. Li
2019 Ohio 5269 (Ohio Court of Appeals, 2019)
Wildcat Drilling, L.L.C. v. Discovery Oil & Gas, L.L.C.
2018 Ohio 4015 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 2601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gray-v-petronelli-ohioctapp-2017.