Zimmerview Dairy Farms, L.L.C. v. Protege Energy III., L.L.C.

2022 Ohio 1282
CourtOhio Court of Appeals
DecidedApril 11, 2022
Docket21CA1
StatusPublished
Cited by1 cases

This text of 2022 Ohio 1282 (Zimmerview Dairy Farms, L.L.C. v. Protege Energy III., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zimmerview Dairy Farms, L.L.C. v. Protege Energy III., L.L.C., 2022 Ohio 1282 (Ohio Ct. App. 2022).

Opinion

[Cite as Zimmerview Dairy Farms, L.L.C. v. Protege Energy III., L.L.C., 2022-Ohio-1282.]

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT WASHINGTON COUNTY

ZIMMERVIEW DAIRY FARMS, : LLC, ET AL., : : Case No. 21CA1 Plaintiffs-Appellees, : : v. : DECISION AND JUDGMENT : ENTRY PROTÉGÉ ENERGY III : LLC, : : Defendant-Appellant. : _____________________________________________________________ APPEARANCES:

J. Kevin West, Dallas F. Kratzer, III, Steptoe & Johnson PLLC, Columbus, Ohio, Robert L. Paddock, Buck Keenan LLP, Houston, Texas, Pro Hac Vice, for Appellant.

Matthew C. Carlisle, Adam J. Schwendeman, Thiesen Brock, LPA, Marietta, Ohio, for Appellees. _____________________________________________________________

Smith, P.J.

{¶1} Defendant-Appellant Protégé Energy III LLC, “Protégé,”

appeals the December 18, 2020 Decision and Judgment Entry of the

Washington County Court of Common Pleas. Protégé conducted gas and oil

operations on property owned by Plaintiffs-Appellees Zimmerview Dairy

Farms, LLC and Zimmerview Properties, LLC, collectively “Zimmerview,” Washington App. No. 21CA1 2

in 2015. Later, Zimmerview brought various claims against Protégé,

including breach of contract, conversion, and trespass.

{¶2} After a bench trial, the trial court found in favor of Zimmerview

and awarded Zimmerview $819,093.00 on the above claims. Protégé

challenges the trial court’s findings on Zimmerview’s claims and the

damage awards. However, based upon basic principles of contract law in

Ohio and our review of the evidence presented at trial, we find no merit to

the arguments offered in Protégé’s five assignments of error. We find there

is competent and credible evidence to support the trial court’s judgment in

this matter. Accordingly, we overrule all assignments of error and affirm the

judgment of the trial court.

FACTUAL AND PROCEDURAL BACKGROUND

{¶3} The following facts were adduced at a bench trial in the

Washington County Court of Common Pleas on September 29, 2020. Dean

Zimmer and his brother Brent Zimmer are the members of Zimmerview

Dairy Farm, LLC. Zimmerview owns land and maintains a farming

operation at 700 Zimmer Road in Washington County. The farm has been in

the Zimmer family since 1926. Dean Zimmer has worked the family farm

his entire life, and before that, his father and grandfather worked and

managed the farm. The farm started out as a dairy farm, switched to beef, Washington App. No. 21CA1 3

and currently is a beef-feeding operation. The Zimmers grow corn,

soybeans, hay, and alfalfa.

{¶4} In January 2014, Dean Zimmer, on behalf of Zimmerview, and

MNW Energy LLC, entered into an Oil and Gas Lease. James Vuksic, who

testified at trial, owned shares in MNW Energy LLC. The Oil and Gas

Lease was eventually assigned to Protégé.

{¶5} Tarah Fagan represented Protégé’s interests in the subsequent

contract negotiations. Due to difficulty in the negotiations, Dean Zimmer

asked James Vuksic to mediate the contract negotiations. Vuksic had

assisted Protégé with negotiations in the past. Vuksic has been involved in

the oil and gas industry for 30 to 40 years. In addition to the original Oil and

Gas Lease, the parties eventually entered into three additional contracts:

1. The Supplemental Agreement of the Parties;

2. The Surface and Subsurface Use Agreement1; and,

3. The Damage Release Agreement.

The above four contracts were admitted as joint exhibits at trial. Additional

information regarding the pertinent contract negotiations will be set forth

below.

1 Testimony indicates the Surface and Subsurface Use Agreements simply provided for an easement to construct the well pad on the Zimmerview property. Washington App. No. 21CA1 4

{¶6} Protégé used 13.5 acres of the Zimmer farm during construction

of what became known as the Caywood well pad, five for the well pad and

8.5 for the hillside. Core drilling began in January 2015. Brush and tree

removal began in March 2015. Fences were constructed in April 2015.

Topsoil removal began in May 2015. Huge trucks moved the topsoil to a

stockpile at an agreed-upon location.

{¶7} In June 2015, there were multiple extremely heavy rains. Dean

Zimmer identified a photo exhibit showing the extreme runoff of brown

water which took topsoil with it. The topsoil ran into a creek which

bordered the Zimmer farm. Dean Zimmer identified several photographs

which showed how the hillside looked after every rain with the topsoil

stockpile running downhill.

{¶8} Protégé hired Great Lakes Construction Company, “Great

Lakes,” to re-seed the area. However, the rains washed the seed away and

gullies formed. During these efforts, topsoil was not replaced. The topsoil

continued to flow downhill. There were three initial attempts to re-seed the

hillside.2 Each time the rains washed the seed away and gullies formed.

2 Protégé witness Brian Plautz testified that hydroseeding is the process of applying grass seed and fertilizer mixed together with water to slopes using a truck. Washington App. No. 21CA1 5

{¶9} Mr. Zimmer and his brother spoke to Protégé’s CEO about their

concerns in August 2015. Great Lakes left the site in early fall 2015, leaving

some gullies behind. Within a month or two, Zimmer testified there were

four-foot canyons and gullies running through the hillside. Zimmer also

testified that large boulders were left behind.

{¶10} The Zimmers also contacted the Ohio Department of Natural

Resources, “ODNR.” ODNR inspected the well pad area and issued a notice

to Protégé that they needed to reclaim the area.3 On the fourth attempt at

reclamation, Protégé used a company called Hydrogreen.

{¶11} Hydrogreen repositioned some of the boulders and moved them

into piles. Hydrogreen “tracked” the rough spots in the gullies and sprayed

the hillside again. Hydrogreen left in June 2016. After the first rain, the

gullies reappeared even deeper. Zimmer testified that gullies create

problems in farming because animals can get hurt and because it is

dangerous to use farm or heavy equipment near gullies.

3 Oil and gas reclamation begin long before the completion of operations at an oil and gas site. Rather it is an ongoing process, beginning before site construction and continuing through the life of an oil and gas production well and its associated facilities. Following reclamation, an inspector checks for proper re- contouring of the site, the return of topsoil to disturbed areas, and completion of proper re-seeding. Reclamation is successful when it has established a self-sustaining, vigorous, diverse, native plant community that will control erosion and non-native plant invasion. See U.S.Department of the Interior, Bureau of Land Management, Reclamation. https://www.blm.gov/programs/energy-and-minerals/oil-and- gas/reclamation. Accessed December 14, 2021. Washington App. No. 21CA1 6

{¶12} When Protégé left the jobsite, erosion and landscaping issues

still existed.4 Protégé left parts of fence behind. Both water and telephone

lines were exposed. There was unsightly vegetation. Mr. Zimmer described

the well pad area as an “inconvenience and an eyesore.”

{¶13} Zimmer testified he had to remove a three-strand fence placed

by the contractors. When cattle attempted to go through the fence they were

injured.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GigSmart, Inc. v. AxleHire, Inc.
2023 Ohio 3807 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 1282, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zimmerview-dairy-farms-llc-v-protege-energy-iii-llc-ohioctapp-2022.