Complete General Construction Co. v. Kard Welding, Inc.

911 N.E.2d 959, 182 Ohio App. 3d 119, 2009 Ohio 1861
CourtOhio Court of Appeals
DecidedApril 21, 2009
DocketNo. 08AP-556.
StatusPublished
Cited by3 cases

This text of 911 N.E.2d 959 (Complete General Construction Co. v. Kard Welding, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete General Construction Co. v. Kard Welding, Inc., 911 N.E.2d 959, 182 Ohio App. 3d 119, 2009 Ohio 1861 (Ohio Ct. App. 2009).

Opinion

French, Presiding Judge.

{¶ 1} Plaintiff-appellant, Complete General Construction Company (“Complete General”), appeals from the judgment of the Franklin County Court of Common Pleas in favor of defendant-appellee, Kard Welding, Inc., d.b.a. Kard Bridge Products (“Kard”). We affirm.

{¶ 2} On November 20, 2002, the Ohio Department of Transportation (“ODOT”) requested bid proposals for Project No. 020508 (“ODOT project”), which involved the construction of a highway on-ramp and off-ramp for State Route 315, north of King Avenue, in Columbus. Bids were required to be sealed and submitted to ODOT by December 6, 2002, at 10:00 a.m.

{¶ 3} In anticipation of submitting a bid for the ODOT project, Complete General solicited quotes from prospective subcontractors, including subcontrac *121 tors for the project’s structural steel components. On December 5, 2002, at approximately 9:30 p.m., Kard faxed a quote (the “original quote”) to Complete General for the structural steel components, including prices for seven line items set forth in the ODOT project requirements. Of particular relevance to this appeal, Kard’s original quote included a price of $259,260 for line item 0360.

{¶ 4} The original quote stated that it was “FIRM FOR 30 DAYS” from December 6, 2002, included a term requiring payment “NET 30 [days] FROM INVOICE DATE,” and provided that “ALL 863 MATERIAL SHOP DRAWINGS SHALL BE STAMPED AND DATED AS CHECKED AND ACCEPTED BY A REGISTERED PROFESSIONAL ENGINEER HIRED BY [Complete General].” 1 The original quote also included the Kard Group Standard Terms and Conditions of Sale, which provided:

Acceptance of any order from [Complete General] for purchase of materials or services or both is expressly made conditional on [Complete General’s] assent to the terms and conditions of sale contained in [Kard’s] Quotation, in [Kard’s] Acknowledgment, and in these “Kard Group Standard Terms and Conditions of Sale”, and [Kard] agrees to furnish materials and/or services only upon these conditions.

The original quote does not contain a handwritten signature, but contains the following typewritten notation directly above the Kard Group Standard Terms and Conditions: “KENNETH OSTERLOH / VICE PRESIDENT / KARD BRIDGE.”

{¶ 5} On December 6, 2002, at approximately 7:53 a.m., Dave Anderson, a Complete General estimator, spoke with Ken Osterloh, who confirmed Kard’s original quote and confirmed that Kard could meet Complete General’s anticipated delivery schedule. After speaking with Osterloh, and based on Kard’s original quote, Complete General deducted $89,390 from its bid to ODOT. After making this deduction, Complete General submitted its bid to ODOT at approximately 9:45 a.m. on December 6, 2002.

{¶ 6} After ODOT opened the bids on December 6, 2002, Complete General learned that it was the apparent low bidder. ODOT officially awarded Complete General the general contract on December 19, 2002.

{¶ 7} At all relevant times, it was Complete General’s practice to issue a purchase order to a subcontractor when it agreed on terms and wished to enter into a formal contract. On December 18, 2002, Anderson faxed a copy of Complete General’s standard “TERMS AND CONDITIONS” to Osterloh with a *122 cover sheet stating, “[Those terms and conditions] would be made part of our [purchase order] to you and would replace your terms. Please review and advise. Payment would be as we discussed, prompt!” For the next several weeks, Complete General and Kard engaged in negotiations concerning the terms and conditions that would govern a subcontract for the structural steel components. Particular disagreements related to the terms for payment and a term regarding which party bore the risk for the professional engineer’s review of Kard’s shop drawings. Complete General never issued a purchase order or subcontract to Kard in relation to the ODOT project.

{¶ 8} On January 7, 2003, as part of the parties’ continuing negotiations over terms, Osterloh faxed Anderson a set of revised terms and conditions that restated Kard’s prices for the relevant line items and proposed an increase in Kard’s selling price in exchange for Kard’s maintaining continued liability for errors in the shop drawings overlooked during the professional engineer’s review. Upon review of this fax, Anderson noticed that Kard was working off a price for line item 0360 different from that listed in the original quote. After questioning Osterloh, Anderson learned that Kard had submitted a revised quote to Complete General, via fax, shortly after 9:30 a.m. on December 6, 2002, based on a mistake in the original bid. The revised quote increased the price for line item 0360 by $24,890. Anderson did not learn of the revised quote until he received Osterloh’s January 7, 2003 fax, more than 30 days later.

{¶ 9} On January 16, 2003, after learning of the revised quote and of Kard’s refusal to honor the original quote for line item 0360, Complete General submitted a purchase order and entered into a subcontract for the structural steel components of the ODOT project with PDM Bridge, L.L.C. (“PDM”), in the amount of $570,000.

{¶ 10} On March 19, 2003, Complete General filed a complaint against Kard in the Franklin County Court of Common Pleas. After a stipulated dismissal without prejudice on March 3, 2004, Complete General refiled its complaint on March 2, 2005, asserting claims for breach of contract, promissory estoppel, and detrimental reliance. Kard filed an answer on April 22, 2005, along with a counterclaim for a declaratory judgment and breach of contract. On January 25, 2007, the trial court denied a motion for summary judgment filed by Complete General.

{¶ 11} Pursuant to an order of reference, a magistrate conducted a jury-waived trial on several nonconsecutive days between January 31, 2007, and March 16, 2007. On the final day of trial, Kard withdrew its counterclaim. The magistrate issued his decision, including findings of fact and conclusions of law, on April 26, 2007, finding in favor of Kard. The magistrate rejected Complete General’s argument that the original quote was a firm offer under R.C. 1302.08. The *123 magistrate also concluded that Complete General’s promissory-estoppel claim failed because Complete General was not seeking performance from Kard in accordance with the terms of the original quote and because Complete General did not notify Kard within a reasonable time that it was accepting the original quote.

{¶ 12} Complete General filed timely objections to the magistrate’s decision on May 10, 2007, and filed supplemental objections on March 4, 2008. The trial court overruled Complete General’s objections, adopted the magistrate’s decision, and entered judgment in favor of Kard on June 3, 2008. Complete General thereafter filed a timely notice of appeal.

{¶ 13} Complete General asserts the following assignments of error:

Assignment of Error No. 1: Kard’s Original Quote constituted a firm offer under Ohio Revised Code § 1302.08 and was irrevocable.
Assignment of Error No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S.P. Drilling Servs., Inc. v. Cooper's Excavating, L.L.C.
2019 Ohio 55 (Ohio Court of Appeals, 2019)
Weitz Co. v. Hands, Inc.
882 N.W.2d 659 (Nebraska Supreme Court, 2016)
Kelly v. State
452 N.E.2d 907 (Indiana Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
911 N.E.2d 959, 182 Ohio App. 3d 119, 2009 Ohio 1861, Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-general-construction-co-v-kard-welding-inc-ohioctapp-2009.