Sms Data Products Group, Inc. v. The United States, Federal Data Corporation, Intervenor

900 F.2d 1553, 36 Cont. Cas. Fed. 75,845, 1990 U.S. App. LEXIS 5285
CourtCourt of Appeals for the Federal Circuit
DecidedApril 11, 1990
Docket89-1504, 89-1505
StatusPublished
Cited by34 cases

This text of 900 F.2d 1553 (Sms Data Products Group, Inc. v. The United States, Federal Data Corporation, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sms Data Products Group, Inc. v. The United States, Federal Data Corporation, Intervenor, 900 F.2d 1553, 36 Cont. Cas. Fed. 75,845, 1990 U.S. App. LEXIS 5285 (Fed. Cir. 1990).

Opinion

MICHEL, Circuit Judge.

SMS Data Products Group, Inc. (SMS) appeals the decisions of the General Services Administration Board of Contract Appeals (Board), denying SMS’ two protests of the award of a contract by the Administrative Office of the United States Courts (AO) to Federal Data Corporation (FDC) for the provision of microcomputer hardware, software, and support services. SMS Data Prods. Group, Inc. v. Administrative Office of U.S. Courts, GSBCA No. 9834-P, 89-1 BCA ¶ 21,567 (protest one); SMS Data Prods. Group, Inc. v. Administrative Office of U.S. Courts, GSBCA No. 9894-P, slip op. (Feb. 9, 1989) (protest two). We affirm.

BACKGROUND

A full statement of the facts of this case is contained in the Board’s decision reported at 89-1 BCA 1121,567, at 108,610-13. Presented here is a summary of only the facts relevant to this decision.

The Solicitation

The AO issued a solicitation requesting proposals to provide microcomputer hardware, software, and support services to the 'federal judiciary for one year with annual extensions at the option of the AO, for a total duration of 108 months. Seven offer-ors submitted proposals and each proposal was evaluated on the basis of cost, user demonstration, support, system capabilities, and corporate experience/contract management. The AO evaluated the best and final offers and determined that FDC had the highest overall score. FDC was thereafter awarded the contract.

SMS filed two protests of the award. In the first protest SMS alleged FDC’s proposal was mathematically and materially imbalanced and therefore the award was in violation of the solicitation and federal regulation. The Board denied this protest, finding no mathematical or material imbalance, and no consequent violation of the solicitation or federal regulation. In its second protest SMS alleged the AO engaged in improper conduct in evaluating SMS’ and FDC’s offers and in ultimately awarding the contract to FDC. The Board dismissed this protest as “frivolous” because SMS was “unable to demonstrate ... a credible factual predicate for this [second] protest.” SMS Data, GSBCA No. 9894-P, slip op. at 3.

SMS filed appeals of both decisions and the two appeals were consolidated by Order of this court. Order, SMS Data, Nos. 89-1504,-1505 (Fed.Cir. Sept. 20, 1989). Five days prior to the Order, SMS filed its initial brief, referencing only the first protest. The AO and FDC, however, discussed the merits of each protest in their respective briefs, as is prudent in a consolidated appeal. During oral argument SMS stated it was abandoning an appeal of the second protest.

FDC’,S Proposal

FDC’s prices for hardware and software are highest in the first contract year, then *1555 decrease for each of the next four option years. They then increase slightly in option years six through nine. FDC’s maintenance and training prices increase annually through year three, decrease until year seven, and then remain constant through year nine.

The AO evaluated prices over the nine potential contract years and determined that the cost to the government of purchasing from FDC becomes the lowest, relative to the other offerors, in option year four. SMS Data, 89-1 BCA 11 21,567, at 108,611 (Finding of Fact 10). The Board found that the AO anticipates exercising all of its options under the contract. Id. (Finding of Fact 11). The Board found that FDC’s proposal does not contain any separate charges nor does it, in comparison to the other proposals, contain any implicit charges for the AO’s failure to exercise options. Id. (Finding of Fact 7).

ISSUE PRESENTED

Whether FDC’s offer is imbalanced so that acceptance of the bid is prohibited by Solicitation Provision M.2.5 and 41 C.F.R. § 201-32.205-3(g)(3)(d) (1989).

OPINION

The standard by which we review decisions of the Board is set by statute. The Board’s findings of fact are final unless “fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.” 41 U.S.C. § 609(b) (1982). Conclusions of law are reviewed de novo, however, and some deference is given to the Board’s expertise in interpreting contract regulations. This court has stated that “legal interpretations by tribunals having expertise are helpful to us, even if not compelling.” Erickson Air Crane Co. v. United States, 731 F.2d 810, 814 (Fed.Cir.1984).

I.

In the proceedings before the Board, the AO conceded FDC’s bid is mathematically imbalanced. SMS Data, 89-1 BCA ¶ 21,567, at 108,614. Due to the AO’s concession, the Board stated, “we will not hear evidence ... regarding mathematical imbalance which has been admitted by [the AO].” Joint Appendix, SMS Data, Nos. 89-1504,-1505, at 112-13 (Fed.Cir. filed Dec. 21, 1989) (transcript). Despite the admission by the AO and the Board’s refusal to hear evidence on mathematical imbalance, the Board held that although the record shows that FDC’s prices vary from year to year, “we cannot find that they are in excess of the value of the fiscal year requirements in question” and therefore “we do not consider them — [AO’s] admission notwithstanding — to be mathematically unbalanced.” SMS Data, 89-1 BCA ¶ 21,567, at 108,615.

The concept of “mathematical imbalance” is rooted in Comptroller General Decisions and Board precedent. See Storage Tech. Corp., GSBCA No. 9345-P, 88-2 BCA 11 20,667, at 104,445; SMC Information Sys., Inc., GSBCA No. 8071-P, 85-3 BCA ¶ 18,388, at 92,236; Fidelity Moving & Storage Co., 86-1 CPD ¶ 476, at 3; Crown Laundry and Dry Cleaners, Inc., 83-1 CPD 11438, at 4. Mathematical imbalance occurs “if each bid item fails to carry its share of the cost of the work (or supplies) plus the bidder’s profit/overhead or if the bid is based upon nominal prices for some items and enhanced prices for others.” SMS Data, 89-1 BCA ¶ 21,567, at 108,614 (quoting Storage Tech., 88-2 BCA ¶ 20,667, at 104,445); see, e.g., SMC Information, 85-3 BCA ¶ 18,388, at 92,236; Fidelity Moving, 86-1 CPD ¶ 476, at 3; Crown Laundry, 83-1 CPD ¶ 438, at 4.

SMS argues that mathematical imbalance, alone, violates the solicitation, and federal regulation 41 C.F.R. §§ 201-32.-205-3(g)(c)(3) & (d) (1989) (separate charges prohibition and fixed price option, respectively). 1 The regulation reads:

*1556 (c)(3) Separate Charges. Separate charges, in any form, are not solicited. Offerors [sic] containing any charges for failure to exercise any option will be rejected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zoeller v. McHugh
626 F. App'x 983 (Federal Circuit, 2015)
Westech International, Inc. v. United States
79 Fed. Cl. 272 (Federal Claims, 2007)
Tennyson v. Opm
Federal Circuit, 2007
Ravens Group, Inc. v. United States
78 Fed. Cl. 390 (Federal Claims, 2007)
Johnson v. Advanced Engineering & Planning Corp.
292 F. Supp. 2d 846 (E.D. Virginia, 2003)
Vantage Associates, Inc. v. England
25 F. App'x 859 (Federal Circuit, 2001)
J & D Maintenance & Services v. United States
45 Fed. Cl. 532 (Federal Claims, 1999)
Envirocare of Utah, Inc. v. United States
44 Fed. Cl. 474 (Federal Claims, 1999)
Ryan Co. v. United States
43 Fed. Cl. 646 (Federal Claims, 1999)
Anderson Columbia Environmental, Inc. v. United States
43 Cont. Cas. Fed. 77,466 (Federal Claims, 1999)
Advanced Data Concepts, Inc. v. United States
43 Cont. Cas. Fed. 77,453 (Federal Claims, 1999)
United International Investigative Services, Inc. v. United States
42 Cont. Cas. Fed. 77,394 (Federal Claims, 1998)
Allied Technology Group, Inc. v. United States
41 Cont. Cas. Fed. 77,179 (Federal Claims, 1997)
Hydro Engineering, Inc. v. United States
41 Cont. Cas. Fed. 77,135 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
900 F.2d 1553, 36 Cont. Cas. Fed. 75,845, 1990 U.S. App. LEXIS 5285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sms-data-products-group-inc-v-the-united-states-federal-data-cafc-1990.