Johnson v. Advanced Engineering & Planning Corp.

292 F. Supp. 2d 846, 2003 U.S. Dist. LEXIS 20794, 2003 WL 22739161
CourtDistrict Court, E.D. Virginia
DecidedNovember 17, 2003
DocketCIV.A. 03-652-A
StatusPublished
Cited by3 cases

This text of 292 F. Supp. 2d 846 (Johnson v. Advanced Engineering & Planning Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Advanced Engineering & Planning Corp., 292 F. Supp. 2d 846, 2003 U.S. Dist. LEXIS 20794, 2003 WL 22739161 (E.D. Va. 2003).

Opinion

MEMORANDUM OPINION

ELLIS, District Judge.

In this appeal from a decision of the Armed Services Board of Contract Appeals (“the Board”), Hansford T. Johnson, Acting Secretary of the Navy (hereinafter “the Navy”), seeks reversal of the Board’s decision allowing Advanced Engineering and Planning Corporation, Inc. (“AEP-CO”) to recover preparation costs for its submission of a Request for Equitable Adjustment (“REA”) to the contracting officer (“CO”). At issue is whether AEPCO’s September 29, 2000 REA was a claim within the meaning of the Contract Disputes Act (“CDA”), for which the costs of preparation are not recoverable.

I.

The facts relevant to this appeal were found by the Board 1 and, for the most part, are undisputed. This case arises from a contract between the Naval Sea Systems Command Supervisor of Shipbuilding, Conversion, and Repair (“Navy”) and AEPCO, Contract No. N0024-94-H-8687, Job Order No. 0072. Under the contract, AEPCO was to perform twenty ship alteration work items on the USS MT. WHITNEY for the firm fixed price of $1,340,242.

*848 In the course of contract performance, seventy-seven (77) formal contract changes, known as “sequences,” were initiated by either AEPCO or the Navy. Each sequence required AEPCO to propose a price for the additional work. Once a proposal was submitted, the parties sought to negotiate a price for the sequence. Of the 77 sequences initiated, four were voided and 44 were incorporated into bilateral modifications. The remaining twenty-nine (29) sequences were negotiated, but not finalized into bilateral modifications. Although a number of sequences remained to be negotiated and settled, the Navy on April 30, 2000 issued a “Certificate of Completion and Acceptance of Work” for the work performed on the contract.

In July 2000, Edward Stroud, the Navy’s CO and Cameron Potter, AEPCO’s production manager, met to negotiate the remaining 29 sequences and successfully settled 26. The sequence settlements were reflected in separate “settlement sheets” initialed by Potter and setting forth the date and amount of settlement.

On August 4, 2000, AEPCO’s counsel retained C. Leonard Willis to assist AEP-CO in preparing an REA on the contract. Thereafter, on August 11, 2000, before the Navy issued formal contract modifications relating to the Stroud-Potter settlement of the 26 sequences, AEPCO returned the settlement sheets and by letter notified the Navy that it reserved the issue of impact costs such as delay, disruption and loss of efficiency. 2 In its letter, AEPCO explained that these significant impact costs were attributable to various factors that it was in the process of analyzing. AEPCO further noted that this analysis, when completed, would be submitted to the Navy, after which AEPCO would seek a meeting to settle all open issues in order to close the contract. AEPCO asked that the Navy, in the meantime, process the agreed direct charges relating to the 26 settled sequences. The Navy declined to do so.

The parties, it appears, dispute the scope of their settlement on the 26 sequences. According to CO Stroud, the settlement of these 26 sequences included consideration for all costs, including payment for any delay and disruption caused by the changes. Yet, according to AEP-CO, in July 2000, CO Stroud and Potter reached a verbal agreement on reimbursement for direct costs associated with the 26 sequences and AEPCO later sought to confirm that this agreement did not waive its right to recover an equitable adjustment for the indirect consequences of these changes. 3

On October 2, 2000, AEPCO submitted an REA dated September 29, 2000, seeking compensation in a sum certain for the 29 formal change orders and for alleged constructive changes. The REA was certified in accordance with Department of Defense Federal Acquisition Regulation (“DFARS”) 252.243-7002 (Requests for Equitable Adjustment); it was not certified in accordance with Federal Acquisition Regulation (“FAR”) 33.207, the regulation applicable to contractor claims submitted under the Contract Dis *849 putes Act of 1978 (“CDA”). AEPCO’s REA included a section entitled “Scoping and Pricing,” setting out costs incurred in preparing the REA, including attorney and consultant fees. 4

After submission of the REA, the parties engaged in settlement negotiations from approximately October 2000 until April 2001. On April 6, 2001, AEPCO asked the CO to issue a final decision because negotiations had reached an impasse. By letter dated April 12, 2001, AEPCO appealed from the failure of the CO to render a final decision on the REA.

On June 18, 2001, AEPCO forwarded to CO Stroud an “updated” REA dated April 30, 2001. This updated REA incorporated new forward pricing rates and was certified in accordance with FAR 33.207 (Contractor Certification) as a CDA certified claim.

The Board docketed AEPCO’s appeal on May 1, 2001. AEPCO moved for partial summary judgment on Count I (Formal Change Orders), Count II (Constructive Change Order), and Count VI (Scoping and Pricing), while the Navy cross-moved for summary judgment with respect to Count VI and two other issues unrelated to this appeal. 5 In its decision, the Board (1) granted the Navy’s summary judgment motion on the two unrelated issues; (2) granted AEPCO’s motion for partial summary judgment as to entitlement on Count I, except as to one sequence; (3) denied AEPCO’s motion for partial summary judgment as to entitlement on Count II; and (4) granted AEPCO’s motion for partial summary judgment on Count VI, awarding AEPCO its REA preparation costs, except to the extent any such costs related to updating the REA and converting it into a CDA claim. See ASBCA Opinion at 24. The Navy appeals here the Board’s decision on Count VI. 6

Under Count VI, AEPCO sought $270,017 for preparing and submitting its September 29, 2000 REA to the Navy to serve as a basis for a negotiated settlement. The amount claimed also included the costs of AEPCO’s efforts in amending and supplementing the original REA after negotiations proved unsuccessful. AEPCO argued that the costs it claimed in preparing the September 29, 2000 REA were allowable under FAR 31.205-33, and were not post-claim legal or litigation costs precluded under FAR 31.205-47. The Navy, in opposition, argued that by October 2000, when the September 29, 2000 REA was submitted, the parties were in a claim status and as such, AEPCO was not entitled to recover costs incurred in preparing and submitting its September 29, 2000 REA because it was, in fact, a CDA claim. Faced with these conflicting contentions, the Board held that AEPCO’s September 29, 2000 REA was not a CDA claim and hence the preparation costs were allowable under FAR 31.205-33(b) 7 as such costs were incurred for the purpose of seeking a *850 comprehensive resolution of the entire job order. 8 It is this finding that the Navy-challenges.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2016
Sab Construction, Inc. v. United States
66 Fed. Cl. 77 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
292 F. Supp. 2d 846, 2003 U.S. Dist. LEXIS 20794, 2003 WL 22739161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-advanced-engineering-planning-corp-vaed-2003.