Shasta Indus. v. Comm'r

1986 T.C. Memo. 377, 52 T.C.M. 190, 1986 Tax Ct. Memo LEXIS 229
CourtUnited States Tax Court
DecidedAugust 14, 1986
DocketDocket No. 28705-84.
StatusUnpublished

This text of 1986 T.C. Memo. 377 (Shasta Indus. v. Comm'r) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shasta Indus. v. Comm'r, 1986 T.C. Memo. 377, 52 T.C.M. 190, 1986 Tax Ct. Memo LEXIS 229 (tax 1986).

Opinion

SHASTA INDUSTRIES, INC., Petitioner v. COMMISSIONER OF INTERNAL REVENUE, Respondent
Shasta Indus. v. Comm'r
Docket No. 28705-84.
United States Tax Court
T.C. Memo 1986-377; 1986 Tax Ct. Memo LEXIS 229; 52 T.C.M. (CCH) 190; T.C.M. (RIA) 86377;
August 14, 1986.
John F. Daniels, III, for the petitioner.
Martha J. Combellick, for the respondent.

GOFFE

MEMORANDUM FINDINGS OF FACT AND OPINION

GOFFE, Judge: The Commissioner determined a deficiency in petitioner's Federal income tax for the taxable year ending January 31, 1981, 1 in the amount of $134,649. After concessions by respondent, the issue for decision is whether the use of the LIFO method for valuing work-in-process inventory by petitioner is compatible with the use of the completed contract method.

FINDINGS OF FACT

Some of the facts have been stipulated. The stipulation of facts and accompanying exhibits are so found and incorporated by reference.

*232 At the time the petition was filed, Shasta Industries, Inc. (hereinafter referred to as Shasta or petitioner) was an Arizona corporation with its principal place of business in Phoenix, Arizona. Shasta was incorporated in Arizona in 1962. Its principal business, conducted under the name "Master Pools," involved the construction of commercial and residential in-ground swimming pools. Approximately 75 percent of the petitioner's total sales resulted from the construction of residential swimming pools during the taxable year at issue. Petitioner constructed approximately 1,500 to 2,000 swimming pools per year, approximately 10 percent of which were not completed at the end of any one taxable year. The average time for completion of a contract to build a residential swimming pool was 30-35 days. The average time for completion of a contract to build a commercial swimming pool was 2 months. An average pool weighs approximately 40 tons. Shasta was also engaged in the wholesale and retail sales of pool equipment, supplies, chemicals, landscaping, and spas.

A standardized set of two documents was used to formalize the contractual relationship between Shasta and its customers. Petitioner*233 used a Sales Contract as the preliminary contract. The portion of paragraph 7 of the Sales Contract that deals with risk of loss and ownership provides:

Any pool equipment or appurtenances subject to this contract delivered to the job site are the Owner's property and if removed or stolen are Owner's responsibility.

* * *

Owner agrees that during construction of the swimming pool, he will be liable for any damage to any part of the swimming pool by irrigation water, vandals, or any other persons or things not within the control of the Contractor.

The initial Sales Contract established terms of payment as follows: 40 percent on the day of excavation, 30 percent on the day that the steel and plumbing were installed, 25 percent on the day that the gunite (a form of concrete) was applied, and the remaining 5 percent before plastering.

After the customer and petitioner executed the Sales Contract, an employee of petitioner was sent to the site where the pool was to be constructed to lay out the size and shape of the pool on the site. After the layout was completed and acceptable to the customer, the customer or an authorized representative executed the Pool Layout Acceptance*234 Form which, together with the Sales Contract and any addenda, constituted the legal agreement between the customer and Shasta. The Pool Layout Acceptance Form, exclusive of filled-in items that were peculiar to each job, read as follows:

After careful examination of our site with the layout foreman, I/we accept the layout, elevation, location, contour, size, and shape of the pool to be constructed in our yard.

I agree that the signing of this accepts, without recourse, all of the above listed conditions.

It is further expressly agreed by and between Master Pools and buyer herein that all right, title, possession and interest in the pool, plumbing equipment, fixtures and accessories shall remain in Master Pools until the entire purchase price of said pool has been paid and purchaser herein expressly grants permission to Master Pools to retake possession of said items for failure to complete full payment of the purchase price and does waive any claim for damages arising from said repossession. I acknowledge receipt of copied documents which include contract, plan, N.S.P.I. disclosure Arizona Chapter, and all addendums (if any).

Construction did not begin until after the execution*235 of this form.

Upon completion of the pool, the customer was presented with a form called a Completion Certificate which was to be signed and returned to petitioner. These three documents, the Sales Contract, the Pool Layout Acceptance Form, and the Completion Certificate, were the primary documents signed by the customer unless the job entailed unusual costs of construction that required the execution of addenda authorizing additional costs.

The construction process used by Shasta was as follows: First, a layout man measured the pool location and staked out where the pool was to be constructed and determined if any utility rerouting was required. The customer executed the Pool Layout Acceptance Form at this time. The physical construction then began. At each stage of the pool construction, a construction coordinator selected the crews to perform the particular function and scheduled their projects. The layout site was excavated including dynamiting or other special techniques if necessary. The plumber installed the filter, pump, motor, and the skimmer. Steel reinforcing bars were used to form a metal basket to fit the excavation and form the shape of the pool. Wiring was*236 then added to the pool site. The necessary electrical work was done before the concrete was poured, covering the steel, plumbing and electrical work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welch v. Helvering
290 U.S. 111 (Supreme Court, 1933)
Commissioner v. Hansen
360 U.S. 446 (Supreme Court, 1959)
Thor Power Tool Co. v. Commissioner
439 U.S. 522 (Supreme Court, 1979)
Spang Industries, Inc. v. The United States
791 F.2d 906 (Federal Circuit, 1986)
People v. Seymour
128 P.2d 726 (California Court of Appeal, 1942)
Williams v. Long
402 P.2d 1006 (Court of Appeals of Arizona, 1965)
Fish v. Valley Nat. Bank of Phoenix
167 P.2d 107 (Arizona Supreme Court, 1946)
Frank G. Wikstrom & Sons, Inc. v. Commissioner
20 T.C. 359 (U.S. Tax Court, 1953)
Sam W. Emerson Co. v. Commissioner
37 T.C. 1063 (U.S. Tax Court, 1962)
Fox Chevrolet, Inc. (Maryland) v. Commissioner
76 T.C. 708 (U.S. Tax Court, 1981)
Primo Pants Co. v. Commissioner
78 T.C. No. 47 (U.S. Tax Court, 1982)
W. C. & A. N. Miller Dev. Co. v. Commissioner
81 T.C. No. 34 (U.S. Tax Court, 1983)
Reco Industries, Inc. v. Commissioner
83 T.C. No. 49 (U.S. Tax Court, 1984)
Molsen v. Commissioner
85 T.C. No. 28 (U.S. Tax Court, 1985)
Spang Industries, Inc. v. United States
6 Cl. Ct. 38 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
1986 T.C. Memo. 377, 52 T.C.M. 190, 1986 Tax Ct. Memo LEXIS 229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shasta-indus-v-commr-tax-1986.