Richards & Conover Steel Co. v. Nielsons, Inc.

1988 OK 48, 755 P.2d 644, 1988 Okla. LEXIS 39, 1988 WL 42527
CourtSupreme Court of Oklahoma
DecidedMay 3, 1988
Docket58722
StatusPublished
Cited by6 cases

This text of 1988 OK 48 (Richards & Conover Steel Co. v. Nielsons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richards & Conover Steel Co. v. Nielsons, Inc., 1988 OK 48, 755 P.2d 644, 1988 Okla. LEXIS 39, 1988 WL 42527 (Okla. 1988).

Opinion

HARGRAVE, Vice Chief Justice.

The extent of coverage of an Oklahoma public works payment bond is the sole issue presented in this appeal from a sustention of a demurrer to a remote supplier’s petition to recover payment for materials used in the Deer Creek waste water pollution control facility.

The appellant, Richards and Conover Steel Company was a supplier to Iola Metal Fabricators, a subcontractor. Richards and Conover Steel Company had supplied $37,166.45 worth of steel to Iola by the time Iola notified them they were unable to pay for the steel furnished for the project. In accordance with 61 O.S.1981 § 2, Richards and Conover Steel Company notified the prime contractor, Nielsons, Inc., and its surety, Insurance Company of North America (appellees), within 90 days of the date materials were last furnished, of their demand for payment of the outstanding balance. Materials were last furnished July 24,1981, and the bond was dated June 27, 1979. Inasmuch as the demand did not produce payment, this action was instituted in the District Court of Oklahoma County. Richards and Conover Steel Company sued Nielsons, Inc., and its surety, Insurance Company of North America, alleging that under 61 O.S.1971 §§ 1 and 2, the prime contractor and its surety were required to pay all indebtedness incurred during construction of the project. The defendants filed demurrers against this petition’s allegations which was sustained. The granting of this demurrer and subsequent dismissal of the action form the subject of this appeal.

The issue presented here is whether the coverage of a statutory payment bond on a public works project extends to a material-man in Richards and Conover Steel Company’s position as a remote supplier under the statutory mandate of 61 O.S.1981 §§ 1 and 2. The question is whether a supplier to a third-tier subcontractor may collect on a bond drawn to comply with the above statutes where only subcontractors are specified as a party able to recover on such a bond. Stated otherwise, is bond coverage limited to only those contractors who have a direct contractual relationship with the prime contractor, or does the coverage extend down to every party who supplies labor or materials on a public works project?

The statutes have been amended since the execution of the bond, although the 1971 and 1981 statutes are similar. 61 O.S.1971 § 1 1 provides:

*646 Before any contract, exceeding One Thousand Dollars ($1,000.00) in amount, for the purpose of making any public improvements or constructing any public building or making repairs to the same is awarded, the person or persons to whom such contract is awarded shall furnish to the State of Oklahoma a bond with good and sufficient sureties to the State of Oklahoma, in a sum not less than the sum of the total of the contract, conditioned that such contractor or contractors shall pay all indebtedness incurred by such contractors or their subcontractors who perform work in the performance of such contract, for labor and materials and repairs to and parts for equipment used and consumed in the performance of said contract....

Recovery rights under the bond are provided for in § 2 of 61 O.S.1971:

Such bond shall be filed in the office of the agency, institution, department, commission, municipality or government instrumentality that is authorized by law and does enter into contracts for the construction of public improvements or buildings, or repairs to the same; and the officer with whom the bond is filed shall furnish a copy thereof to any person claiming any rights thereunder. Any person to whom there is due any sum for labor, material or repair to machinery or equipment, furnished as stated in the preceding section, his heirs or assigns, may bring an action on said bond for the recovery of said indebtedness, provided that no action shall be brought on said bond after one (1) year from the day on which the last of the labor was performed or material or parts furnished for which such claim is made. Provided, however, that any person having direct contractual relationship with a subcontractor performing work on said contract, but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond only upon giving written notice to said contractor and surety on said payment bond within ninety (90) days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material or parts for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material or parts were furnished or supplied or for whom the labor was done or performed....

The trial court sustained a demurrer to the petition alleging the above facts under the law of the quoted statute. In his order dismissing the petition the trial court stated that the coverage of the statutory bond sued upon does not extend to a remote supplier such as plaintiff.

Appellant argues that Oklahoma’s general lien statute should be looked to to determine the intent of the Oklahoma public works bond statutes inasmuch as the statutes are similar. Appellees’ position in this appeal is the act should be construed in the light of the federal authority of the Miller Act, 40 U.S.C.S. §§ 270a and 270b.

Appellant notes the issue of remote ma-terialmen and suppliers has been addressed under the statute preceding §§ 1 and 2 here considered in cases such as Amerman v. State, 111 Okl. 174, 239 P. 146 (1925), citing Lohr & Trapnell v. H.W. Johns-Manville Co., 77 Okl. 6, 185 P. 526 (1919), for the proposition that “ ‘Materials used in the construction of a public work, whether furnished under the contract directly to the contractor, must be deemed within the obligation of the surety company under a bond ... conditioned that the contractor make payments to the parties furnishing the same for all materials used in the work provided for in the contract and all labor performed on such work, whether by subcontractors or otherwise, in view of the manifest purpose of that statute to protect those whose labor or material has contributed to the prosecution of the work’ ”.

*647 In Lohr & Trapnell v. H. W. Johns-Manville Co., supra, the Court spoke on a consideration mentioned in this action as a reason to refuse to extend liability on a public works bond to remote suppliers and subcontractors. That is, the very fact of the subcontractor’s remoteness and the difficulty of supervising payment to suppliers and subcontractors, may actually be unknown to the prime contractor and his surety. Such problems are easily circumvented. Quoting from Illinois Surety Co. v. John David Co., 244 U.S. 376, 37 S.Ct. 614, 61 L.Ed. 1206, in Amerman v. State, supra, this Court reiterated:

“The argument that the surety’s risk ought not to be increased by holding it liable for the default of strangers to the original contract is of no greater force in the case of an assignee than it is in that of the subcontractor. A surety company could protect itself by insisting that the contractor require a bond from all subcontractors and assignees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Equipment World, Inc. v. International Fidelity Insurance Co.
2004 OK CIV APP 47 (Court of Civil Appeals of Oklahoma, 2004)
Boren v. Thompson & Associates
2000 OK 3 (Supreme Court of Oklahoma, 2000)
Unadilla Silo Co. v. Hess Bros.
586 A.2d 226 (Supreme Court of New Jersey, 1991)
Atlantic Sea-Con. Ltd. v. Robert Dann Co.
560 A.2d 592 (Court of Special Appeals of Maryland, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1988 OK 48, 755 P.2d 644, 1988 Okla. LEXIS 39, 1988 WL 42527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richards-conover-steel-co-v-nielsons-inc-okla-1988.