Equipment World, Inc. v. International Fidelity Insurance Co.

2004 OK CIV APP 47, 90 P.3d 590, 75 O.B.A.J. 1557, 2004 Okla. Civ. App. LEXIS 23, 2004 WL 1161452
CourtCourt of Civil Appeals of Oklahoma
DecidedApril 13, 2004
Docket100,054
StatusPublished

This text of 2004 OK CIV APP 47 (Equipment World, Inc. v. International Fidelity Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equipment World, Inc. v. International Fidelity Insurance Co., 2004 OK CIV APP 47, 90 P.3d 590, 75 O.B.A.J. 1557, 2004 Okla. Civ. App. LEXIS 23, 2004 WL 1161452 (Okla. Ct. App. 2004).

Opinion

Opinion by

RONALD J. STUBBLEFIELD, Judge:

¶ 1 This is an appeal by the surety on a “Statutory and Payment Bond” from sum-' mary judgment entered by the District Court of Tulsa County in favor of an equipment leasing company. The appeal has been assigned to the accelerated docket pursuant'to Okla. Sup.Ct. R. 1.36, 12 O.S.2001, ch. 15, app. 1. Based on our review of the record on appeal and applicable law, we affirm.

FACTS AND PROCEDURAL HISTORY

¶ 2 This lawsuit arises from two separate road construction projects in Tulsa County in which the Oklahoma Transportation Authority contracted with the company Oklahoma Excavation, Inc. (OEI or the contractor). The contractor leased equipment from Equipment World, Inc. (EWI), and that equipment was used on the state projects. However, OEI did not pay all its indebtedness to EWI, and eventually OEI was terminated from the projects. EWI removed its equipment from the job and sought payment from the surety on the statutory performance bond, International Fidelity Insurance Company (Fidelity). Fidelity did not dispute that the equipment had been used on the state road projects and paid EWI for rental fees for the time the equipment was used. However, Fidelity disputed its obligation to pay EWI for post-return repairs on the equipment and for interest accruing on the unpaid balances according to the terms of the contract between EWI and OEI.

¶ 3 EWI filed -this lawsuit, and largely the dispute is a legal one — whether post-return repairs and contractual interest are covered under the statutory bond' posted pursuant to 61 O.S.2001 § 1. We conclude they are.

STANDARD OF REVIEW

¶ 4 The appellate standard of review of a trial court’s grant of summary judgment is de novo. Carmichael v. Better, 1996 OK 48, ¶ 2, 914 P.2d 1051, 1053. On review, this Court will examine the pleadings and eviden-tiary materials submitted by the parties to determine if there is a genuine issue of material fact. Id. All inferences and conclusions to be drawn from the evidentiary materials will be viewed in the light most favorable to the non-moving party. Id. This Court will reverse the grant of summary judgment where it appears from the evidentiary materials that there is a genuine issue as to any material fact or, if the material facts are undisputed, reasonable persons might reach different inferences on conclusions from those facts. Buck’s Sporting Goods, Inc. v. *592 First Nat’l Bank & Trust Co. of Tulsa, 1994 OK 14, ¶11, 868 P.2d 693, 697-98. In a summary judgment review an appellate court has the same power as the trial court to resolve any disputed issues of law. U.S. Mortg. v. Laubach, 2003 OK 67, ¶ 31, 73 P.3d 887, 900.

DISCUSSION OF ISSUES

¶ 5 Fidelity raises several contentions of error on appeal which are posed as questions. These propositions may be summarized as contentions that the Trial Court erred in granting summary judgment to EWI because (1) under 61 O.S.2001 § 1, a performance bond surety is not liable for the post-return repair of leased equipment which is no longer being used on a state project, nor for interest on the debt specified in the lease contracts; (2) the surety is not liable for repairs “in excess of normal wear and tear” or “tort damages” to leased equipment no longer being used for completion of the bonded project; and, (3) the equipment lessor (EWI) should be required to recover the cost of “extraordinary repairs” under liability and property insurance it was required to obtain on a state project. We reject these contentions.

I. Costs of Repair and Interest

¶ 6 61 O.S.2001 § 1 (emphasis added) provides:

Bond, irrevocable letter of credit or affidavit of payment of indebtedness to be furnished on public works contracts
A.Prior to an award of a contract exceeding Twenty-five Thousand Dollars ($25,000.00) for construction or repair of a public building or structure, or improvement to real property, the person that receives the award shall:
1. Furnish a bond with good and sufficient sureties payable to the state in a sum not less than the total sum of the contract; or
2. Cause an irrevocable letter of credit, containing terms the Department of Central Services prescribes, to be issued for the benefit of the state by a financial institution insured by the Federal Deposit Insurance Corporation in a sum not less than the total sum of the contract.
B. The bond or irrevocable letter of credit shall ensure the proper and prompt completion of the work in accordance with the contract and shall ensure that the contractor shall pay all indebtedness the contractor incurs for the contractor’s subcontractors and all suppliers of labor, material, rental of machinery or equipment, and repair of and parts for equipment the contract requires the contractor to furnish.
C. For a contract not exceeding Twenty-five Thousand Dollars ($25,000.00), in lieu of a bond or irrevocable letter of credit, the contractor shall submit an affidavit of the payment of all indebtedness incurred by the contractor, the contractor’s subcontractors, and all suppliers of labor, material, rented machinery or equipment, and repair of and parts for equipment used or consumed in the performance of the contract. The execution of the affidavit with knowledge that any of the contents of the affidavit are false, upon conviction, shall constitute perjury, punishable as provided for by law.

Fidelity acknowledges it is responsible to EWI for “repair of and parts for equipment used or consumed in the performance of the contract,” but argues that this language means only that it is liable for cost of repair of the machinery while it was being used on the state project. It claims that when the machinery was returned to EWI with no intent that the equipment ever be used on the job again, it had no further liability for repair costs. We find this to be a strained construction of the statutory language, and more specifically one that overlooks the most descriptive phrase in the statute in regard to legislative intent.

¶ 7 In defining the scope of the surety’s liability, the Oklahoma Legislature chose to use the phrase “all indebtedness the contractor incurs,” rather than more specific terms such as charges or rents. The use of such a broad term as “all indebtedness” indicates a legislative intent to give considerable protection to subcontractors and suppliers of materials and equipment for construction of state *593 projects. This is in keeping with the basic purpose of the law noted by the Oklahoma Supreme Court in Richards & Conover Steel Co. v. Nielsons, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carmichael v. Beller
1996 OK 48 (Supreme Court of Oklahoma, 1996)
Richards & Conover Steel Co. v. Nielsons, Inc.
1988 OK 48 (Supreme Court of Oklahoma, 1988)
U.S. Mortgage v. Laubach
2003 OK 67 (Supreme Court of Oklahoma, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2004 OK CIV APP 47, 90 P.3d 590, 75 O.B.A.J. 1557, 2004 Okla. Civ. App. LEXIS 23, 2004 WL 1161452, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equipment-world-inc-v-international-fidelity-insurance-co-oklacivapp-2004.