United States of America v. Best Choice Construction, LLC

CourtDistrict Court, D. South Dakota
DecidedMay 30, 2023
Docket5:21-cv-05042
StatusUnknown

This text of United States of America v. Best Choice Construction, LLC (United States of America v. Best Choice Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America v. Best Choice Construction, LLC, (D.S.D. 2023).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA WESTERN DIVISION

UNITED STATES OF AMERICA, for the 5:22-CV-05001-KES use and benefit of BILLD EXCHANGE, 5:21-CV-05042-KES LLC, a Delaware limited liability company,

Plaintiff, ORDER DENYING PARTIAL SUMMARY JUDGMENT vs.

BEST CHOICE CONSTRUCTION, LLC, a North Dakota limited liability company, and UNITED STATES FIRE INSURANCE COMPANY, a Delaware corporation,

Defendants. Plaintiff, Billd Exchange, LLC (Billd) moves for partial summary judgment against defendants Best Choice Construction, LLC (Best Choice) and United States Fire Insurance Company (USF) on its claims under the Miller Act and quantum meruit assigned to Billd by Vertex Roofing, LLC (Vertex). Docket 47. Defendant USF opposes the motion. Docket 65. Defendant Best Choice did not respond. BACKGROUND I. Factual Background This matter arises from a project by the Bureau of Indian Affairs (BIA) to replace the roof at the Oglala Adult Offenders Facility at Pine Ridge, South Dakota. See Docket 49 ¶¶ 1-2; see Docket 66 ¶ 1. The BIA contracted with Best Choice to replace the roof. Docket 49 ¶ 1; see Docket 66 ¶ 1. Per the BIA Solicitation, Best Choice was required to furnish a payment bond, also called a Miller Act Bond. See Docket 50-2 at 3, 26. On April 16, 2020 Best Choice

executed the Miller Act Bond with its surety, USF, for $1,324,62.20. Docket 49 ¶ 4; Docket 66 ¶ 1. On April 10, 2020, Best Choice entered into a subcontract with Vertex for Vertex to provide work, equipment, and materials for the roof replacement at the Oglala Adult Offenders Facility. Docket 50-1 at 3. The contract specifies that Vertex was to remove the existing roof and install a new roof. See id. at 1- 3. On April 20, 2020, Vertex visited the project site and took core samples of the existing roof. Docket 49 ¶ 9; Docket 66 ¶ 3 (not disputing visit and

collection of samples). Vertex estimated that the roof replacement project would take 37 days to complete. See Docket 50 ¶ 10; Docket 50-5. On June 10, 2020, Vertex’s crew arrived at the project site to begin work. Docket 50 ¶ 11. Shortly after arriving on June 10, Vertex’s crew discovered a coat of asphalt on the existing roof deck. Docket 49 ¶ 12; Docket 66 ¶ 5 (objecting to description of asphalt coat, but not to its discovery). Duro-Last, the manufacturer of the replacement roof, then performed an adhered pull test on the asphalt on the roof “to show the bonding capacity of the Board-Max

insulation adhesive to the existing asphalt.” Docket 50-7 at 2. The results of the test indicated “an average resistance of 790 psf.” Id. In a June 17, 2020 letter, Duro-Last remarked that “[t]his far exceeds the FM 1-90 minimum requirement for the field of the roof, and the enhanced values that are required for the perimeter and corner areas of the roof.” Id. On June 19, 2020, Ed Green, president and CEO of Vertex, sent Ryan

Dalbec, president and CEO of Best Choice, a text that stated they were “in a pickle” regarding the roof. Docket 50-8 at 1. Green also sent Dalbec two pictures of the roof conditions. Id. at 1-2. Dalbec replied “shit.” Id. On June 22, 2020, Green again sent Dalbec a text, this time inquiring about a change order. Id. at 3. Dalbec replied that the BIA “won’t accept a change order if the request isn’t accepted[.]” Id.; Docket 49 ¶ 18; But see Docket 66 ¶ 11. On June 24, 2020, Green asked Dalbec if he “had a discussion with the client mentioning a changed condition that’s the reason [Vertex is] having a

problem in the field.” Docket 50-8 at 4. Dalbec later replied “not until the payment gets approved” which “should be today.” Id. That same day, Dalbec asked Green to draft a proposed request for equitable adjustment that the two would review together. Docket 49 ¶ 23; see generally Docket 66. The next day, June 25, 2020, Green sent a draft of the requested document to Dalbec. See Docket 50-9; Docket 50-8 at 5. Because all communication with the BIA was required to be through Best Choice, only Dalbec could send the request for equitable adjustment to the

BIA. Docket 49 ¶ 26; see Docket 66 ¶ 1; see also Docket 50-10 at 1. On June 29, 2020, Green asked Dalbec if Dalbec had sent the report to the BIA. Docket 50-8 at 5. Dalbec did not directly answer, but requested that Green send him the report again. Id. On August 17, 2020, Green again sent Dalbec a text to inform him of additional laborers who had been hired on the project. Docket 50-8 at 6. Dalbec responded that he was “working as hard as [he] can to get [the

adjustment] pushed through” but that “[n]o one answers the phones there[.]” Id.; see also Docket 49 ¶ 29; Docket 66 ¶ 12 (not contesting that message refers to adjustment). The next day, Green asked Dalbec if the BIA had responded to the request for equitable adjustment. Docket 50-8 at 6-7. Dalbec said, “[y]es[,] they said they are working on it[.]” Id. at 7. On August 23, 2020, Dalbec again confirmed that he had sent the request for equitable adjustment “off for review.” Id. at 8. Throughout September, Green twice again asked Dalbec about updates

on the adjustment. Id. at 9-10. Dalbec stated that he was “[w]orking on it.” Id. at 10. On October 26, 2020, Green sent Dalbec an updated request for equitable adjustment with updated payment figures and other attachments. See Docket 50-12; see also Docket 49 ¶ 35; Docket 66. On November 16, 2020, during a conference call between Green, Dalbec, and the BIA, Green learned for the first time that Dalbec had not sent any request for equitable adjustment to the BIA on Vertex’s behalf. Docket 50 ¶ 29; see also Docket 49 ¶ 38; Docket 66. Green confronted Dalbec about their

previous conversations regarding the adjustment request; Dalbec responded that he could not find any emails from either himself or Green to the BIA about the request. Docket 50-8 at 11-13. Green reminded Dalbec that only Dalbec was authorized to contact the BIA directly. Id. at 13-14. Green also recorded a phone call between himself and Dalbec following the conference call. Docket 49 ¶ 42; Docket 66. Dalbec stated on the call that he could not find any emails to the BIA requesting an equitable adjustment on

Vertex’s behalf. Docket 49 ¶ 42; Docket 66. He also suggested that Green may need to “get legal involved” to resolve the situation and said that Green had good documentation to support its request for an equitable adjustment. Docket 49 ¶ 42; Docket 66. Dalbec reassured Green that he would take care of the situation and that Green should not panic. Docket 49 ¶ 42; Docket 66. That same day, Green asked Dalbec by text message “[w]hat’s the game plan if the [BIA] ignores any and all requests for equitable adjustment[.]” Docket 50-8 at 15. Dalbec said “[l]itigation.” Id. at 16. Again on November 17,

2020, Green asked about the equitable adjustment and Dalbec stated that he could not reach the BIA representative. Id. at 17. Dalbec did not respond to similar requests on November 18 or 19, 2020. Id. at 17-18. On November 21, 2020, Green again asked Dalbec what to do if the BIA denied an equitable adjustment and Dalbec again responded “litigation.” Id. at 21. Vertex ultimately worked 223 days beyond what was initially contemplated by the contract before Vertex was directed to vacate the project site. See Docket 50 ¶ 24.

II. Procedural Background This matter originates with a complaint filed by Vertex in the Southern District of Texas in the case Vertex Roofing, LLC v. Best Choice Construction LLC, located at 22-cv-5001. In the complaint, Vertex alleges breach of contract against Best Choice and USF or, in the alternative, quantum meruit. Case No. 22-cv-5001, Docket 1. Under either theory of liability, Vertex asserts a right to recover governed by the Miller Act, which is a federal statute. Id. Thus, this

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Dunes Hospitality, L.L.C. v. Country Kitchen International, Inc.
2001 SD 36 (South Dakota Supreme Court, 2001)
Leonetti's Frozen Foods, Inc. v. Rew Mktg., Inc.
887 F.3d 438 (Eighth Circuit, 2018)
Blue v. Blue
2018 SD 58 (South Dakota Supreme Court, 2018)
Edwin Van Dorn v. Scott Hunter
919 F.3d 541 (Eighth Circuit, 2019)
J.B. Turner v. XTO Energy, Inc.
989 F.3d 625 (Eighth Circuit, 2021)
Erickson Cabin, LLC v. Busey Bank
31 F.4th 1044 (Eighth Circuit, 2022)
Van De Walle & Associates, L.L.C. v. Buseman
2003 SD 70 (South Dakota Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America v. Best Choice Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-v-best-choice-construction-llc-sdd-2023.