G. A. Mosites Co. of Fort Worth v. Aetna Casualty & Surety Co.

1976 OK 7, 545 P.2d 746, 1976 Okla. LEXIS 365
CourtSupreme Court of Oklahoma
DecidedJanuary 20, 1976
Docket47996
StatusPublished
Cited by29 cases

This text of 1976 OK 7 (G. A. Mosites Co. of Fort Worth v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. A. Mosites Co. of Fort Worth v. Aetna Casualty & Surety Co., 1976 OK 7, 545 P.2d 746, 1976 Okla. LEXIS 365 (Okla. 1976).

Opinion

DAVISON, Justice.

This is an appeal from an order of the District Court of Tulsa County sustaining motions of the appellees, (defendants), for summary judgment. The appellant, (plaintiff), as a supplier under a subcontractor, sued the defendants, W. R. G. Construction Company, prime contractor; Aetna Casualty and Surety Company; and the City of Tulsa; along with defendant, Offutt Construction Company, the subcontractor.

The appellee, W.R.G., made a certain contract with the City of Tulsa covering a public water works improvement for a contract price in excess of $1,000,000.00 The contract included within its terms a performance bond which guaranteed the performance of the work and a separate statutory payment bond which guaranteed payment of laborers and materialmen. The appellee, Aetna, executed both the contract and the statutory payment bond as surety.

Thereafter, the prime contractor, W.R. G., made a subcontract with the defendant, Offutt Construction Company, for a contract price in excess of $400,000.00, which covered a part of the work on the prime contract. The appellant, under a contract with the subcontractor, Offutt, supplied to the project certain material and labor on which the contract consideration was $11,417.00.

All work on the above contracts was completed. The City of Tulsa has paid the prime contractor; the prime contractor has paid the subcontractor; but the subcontractor, Offutt, did not pay Mosites, the appellant. The last material and work supplied by the appellant on this project was in September, 1972. This action was filed in August, 1973.

The trial court sustained the motions of appellees for summary judgment for the reason that the ninety days notice, required in 61 O.S. § 2 by materialmen and laborers not in direct contractual relation with prime contractor, was not given by appellant.

*748 This appeal is from that judgment. The trial court gave summary judgment for appellant against the subcontractor, Offutt, apparently without resistance and that judgment is riot involved in this appeal.

On the record before us, we are sure that if the appellant had given the notice required' by 61 O.S. § 2, the appellant would simply have relied on the statutory bond given under 61 O.S. § 1 and would have received full recovery thereunder. Failing to give .notice, he now urges his right to recover, without said notice, upon two separate and alternative theories. While appellant’s argument takes several approaches, we would somewhat simplify them into two alternative propositions.

First, the appellant contends that this action may be maintained as a third party beneficiary under the prime contract and its included performance bond, without reference to the statutory payment bond and 61 O.S. §§ 1 and 2. Second, this action may be maintained on the statutory payment bond, as a third party beneficiary contract given under the terms of ordinances of the City of Tulsa and this without regard to the notice provision of 61 O.S. § 2.

The trial court held that the appellant’s only action was on the payment bond given under 61 O.S. § 1, being the “statutory bond” called for in the contract. The pertinent provisions of the statutes thereon are as follows:

61 O.S. § 1—

“Before any contract, exceeding One Thousand Dollars ($1,000.00) in amount, for the purpose of making any public improvements or constructing any public building or making repairs to the same is awarded, the person or persons to whom such contract is awarded shall furnish to the State of Oklahoma a bond with good and sufficient sureties to the State of Oklahoma, in a sum not less than the sum total of the contract, conditioned that such contractor or contractors shall pay all indebtedness incurred by such contractors or their subcontractors who perform work in the performance of such contract, for labor and materials and repairs to and parts for equipment used and consumed in the performance of said contract.”

61 O.S. § 2—

“Such bond shall be filed in the office of the agency, institution, department, commission, municipality or government instrumentality that is authorized by law and does enter into contracts for the construction of public improvements or buildings, or repairs to the same; and the officer with whom the bond is filed shall furnish a copy thereof to any person claiming any rights thereunder. Any person to whom there is due any sum for labor, material or repair to machinery or equipment, furnished as stated in the preceding section, his heirs or assigns, may bring an action on said bond for the recovery of said indebtedness, provided that no action shall be brought on said bond after one (1) year from the day on which the last of the labor was performed or material or parts furnished for which such claim is made.
Provided, however, that any person having direct contractual relationship with a subcontractor performing work on said contract, but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond only upon giving written notice to said contractor and surety on said payment bond within ninety (90) days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material or parts for which such claim is made stating with substantial accuracy the amount claimed and the name of the party to whom the material or parts were furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered or certified mail, postage prepaid, in' an envelope addressed to the contractor at any *749 place he maintains an office or conducts his business, together with a copy thereof to the surety or sureties on said payment bond.”

With respect to appellant’s first proposition, we note that Oklahoma recognizes third party beneficiary contracts and has fixed by statute the right of the beneficiary to enforce such contracts. 15 O.S. § 29 provides as follows:

“A contract, made expressly for the benefit of a third person, may be enforced by him at anytime before the parties thereto rescind it.”

This Court in a number of cases has recognized such contracts and has enforced rights thereunder of laborers and material-men in construction contracts. Gibbs v. Trinity Universal Insurance Company, Okl., 330 P.2d 1035 (1958).

The question presented by the appellant’s first proposition is whether or not the contract in this case with its included performance bond constituted a third party beneficiary contract in favor of the appellant. The intention of the parties to the contract as they are reflected in the contract must provide the answer to this question. In this connection, we note a general rule set out in 17 Am.Jur.2d, Contracts § 304, pp. 727-728 as follows:

“As a general proposition, the determining factor as to the right of a third party beneficiary is the intention of the parties who actually made the contract. The real test is said to be whether the contracting parties intended that a third person should receive a benefit which might be enforced in the courts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BARFELL v. FREEMAN HEALTH SYSTEM AND GULSHAN UPPAL, M.D.
2025 OK 61 (Supreme Court of Oklahoma, 2025)
GLOVER CONSTRUCTION CO., INC. v. STATE ex rel. DEPT. OF TRANSPORTATION
2014 OK CIV APP 51 (Court of Civil Appeals of Oklahoma, 2014)
Green Tree Servicing, LLC v. Hill
2013 OK CIV APP 62 (Court of Civil Appeals of Oklahoma, 2013)
Lumpkins v. Balboa Insurance
812 F. Supp. 2d 1280 (N.D. Oklahoma, 2011)
Woolard v. JLG Industries, Inc.
210 F.3d 1158 (Tenth Circuit, 2000)
Malicoate v. Standard Life & Accident Insurance Co.
2000 OK CIV APP 37 (Court of Civil Appeals of Oklahoma, 2000)
Warren v. Oberlin Color Press
1998 OK CIV APP 113 (Court of Civil Appeals of Oklahoma, 1998)
Victore Insurance Co. v. Foster
1997 OK CIV APP 23 (Court of Civil Appeals of Oklahoma, 1997)
Shelley v. Kiwash Electric Cooperative, Inc.
1996 OK 44 (Supreme Court of Oklahoma, 1996)
Protein Technologies International/Ralston Purina v. Hammock
876 P.2d 728 (Court of Civil Appeals of Oklahoma, 1994)
Zahorsky v. Community National Bank of Alva
1994 OK CIV APP 104 (Court of Civil Appeals of Oklahoma, 1994)
Barclay v. Special Indemnity Fund
1993 OK CIV APP 160 (Court of Civil Appeals of Oklahoma, 1993)
Shebester v. Triple Crown Insurers
974 F.2d 135 (Tenth Circuit, 1992)
Heiman v. Atlantic Richfield Co.
1991 OK 22 (Supreme Court of Oklahoma, 1991)
Black v. Renshaw Painting
1991 OK CIV APP 1 (Court of Civil Appeals of Oklahoma, 1991)
Richards & Conover Steel Co. v. Nielsons, Inc.
1988 OK 48 (Supreme Court of Oklahoma, 1988)
Alimenta, U.S.A. v. Sawyers
654 P.2d 660 (Court of Civil Appeals of Oklahoma, 1982)
Keel v. Titan Construction Corp.
1981 OK 148 (Supreme Court of Oklahoma, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
1976 OK 7, 545 P.2d 746, 1976 Okla. LEXIS 365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-a-mosites-co-of-fort-worth-v-aetna-casualty-surety-co-okla-1976.