Puget Sound Energy, Inc. v. Pacific Gas & Electric Co. (In Re Pacific Gas & Electric Co.)

271 B.R. 626, 47 U.C.C. Rep. Serv. 2d (West) 598, 2002 U.S. Dist. LEXIS 1350, 2001 WL 1705108
CourtDistrict Court, N.D. California
DecidedJanuary 4, 2002
DocketC-01-2451 MHP
StatusPublished
Cited by15 cases

This text of 271 B.R. 626 (Puget Sound Energy, Inc. v. Pacific Gas & Electric Co. (In Re Pacific Gas & Electric Co.)) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puget Sound Energy, Inc. v. Pacific Gas & Electric Co. (In Re Pacific Gas & Electric Co.), 271 B.R. 626, 47 U.C.C. Rep. Serv. 2d (West) 598, 2002 U.S. Dist. LEXIS 1350, 2001 WL 1705108 (N.D. Cal. 2002).

Opinion

*629 MEMORANDUM AND ORDER

PATEL, Chief Judge.

On June 25, 2001, appellant Puget Sound Energy, Inc. (“Puget”) filed an emergency motion for expedited appeal of the Bankruptcy Court’s denial of Puget’s Motion for Relief from Stay or Alternative Relief and Judgment Thereon, entered on June 20, 2001. On July 3, 2001, the court issued a revised expedited briefing schedule and the parties submitted briefs and voluminous supporting materials. On July 31, 2001, the court held a hearing on the matter. Having considered the parties’ arguments and submissions, and for the reasons set forth below, the court enters the following memorandum and order.

BACKGROUND

In October 1991, Puget and Appellee Pacific Gas and Electric Company (“PG & E”) entered into a Capacity and Energy Exchange Agreement (“Agreement”) under which each party agreed to transmit 413,000 megawatts of energy to the other each year. See PG & E Exh. A. Puget was required to send electricity to PG & E between June and September each year and PG & E reciprocated between November and February. Id. at §§ 1.24, 1.31, 3.1, 3.2. The periods correlate with the respective recipient utility’s peak demand season. The Agreement provides that the parties may request up to 300 megawatts per hour during the relevant four months. Id. at §§ 3.1, 3.2. The 413,000 total megawatts is calculated by calendar year. Id. at § 1.3. The electricity may be delivered either across the California-Oregon border, or across the Nevada-Oregon border at Malin, Oregon, “if and to the extent both parties have access to such point.” Id. § 1.20.

Section 6.1 of the Agreement provides that either party may

interrupt, suspend, curtail or allow fluctuation in any service under this Agreement, if such interruption, suspension, curtailment or fluctuation results from any of the following:
(e) actions taken in good faith by a Party to prevent, reduce or eliminate ... (ii) unsatisfactory, or jeopardy to conti *630 nuity of, electric service within that Party’s service area. 1

PG & E Exh. A § 6.1.

Section 6.2 of the Agreement states:

Except in cases of emergency or automatic actions, including the operation of automatic devices, each Party shall endeavor to give reasonable notice of any interruption, suspension, curtailment or fluctuation permitted by paragraph 6.1, and of its probable duration.

Id. § 6.2.

Section 6.3 of the Agreement provides:

If any interruption, suspension, curtailment or fluctuation permitted by paragraph 6.1 causes ... a Delivering Party to deliver, or a Receiving Party to receive, less energy that the amount of energy to which the Receiving Party is otherwise entitled under this Agreement and has been scheduled in accordance with [the Agreement], the Delivering Party shall deliver to the Receiving Party at the Point of Delivery and the Receiving party shall accept delivery of an amount of energy equal to the difference as soon as is practicable thereafter as scheduled by the Receiving Party pursuant to [the Agreement],

Id. § 6.3.

Either party is permitted to unilaterally terminate the Agreement, but only after providing five years’ notice. See id. § 2.2.

On December 18, 2000, PG & E filed an 8-K report with the New York Stock Exchange. See Puget Tr. Exh. 8. The report stated that Moody’s and Standard & Poor’s had both begun to scrutinize PG & E’s securities for possible downgrades, citing “concerns about the escalating finan-dal burdens placed on the Utility and the absence of short-term or long-term regulatory or statutory mechanisms for recovery of the under-collections [of revenues from consumers].” Id. at 4. PG & E also reported that “[although the Utility currently has approximately $1.2 billion of short-term investments, without obtaining additional financing, the Utility will be unable to continue paying its net power purchase costs. There is no assurance that the Utility will be able to obtain such additional financing.” Id.

On January 10, 2001, PG & E filed an 8-K report announcing even more dire circumstances. PG & E reported:

The recent rate increase approved by the California Public Utilities Commission (CPUC) on January 4, 2001, will raise approximately $70 million in cash per month for three months. Even if all this cash were made available to the Utility immediately, $210 million represents approximately one week’s worth of net power purchases at current prices. Thus, the rate increase does not raise enough cash for the Utility to pay its ongoing procurement bills or make further borrowing possible.
The utility currently is unable to borrow more money, and is foreclosed from the capital markets because of its financial condition. Absent immediate regulatory, legislative or judicial relief, the Utility will default on its payment obligations and faces the risk of being forced into bankruptcy.

Puget Tr. Exh. 10.

On January 11, 2001, the California Independent System Operator (“ISO”), the *631 entity overseeing and regulating the entirety of California’s power grid, declared a Stage Three Emergency from 8:50 A.M. until midnight. See Puget Tr. Exh. 37 at 9. The Stage Three declaration was only the second such occurrence ever. See Barrington Dec. ¶ 3.

A Stage 3 Emergency may be declared any time it is clear that a critical Operating Reserve shortfall (i.e., less than 1/& %) is unavoidable, or is forecast to occur within the next two hours. Stage 3 is the most severe Stage of Emergency and indicates that, without significant ISO intervention, the electric system is in danger of imminent collapse. Involuntary curtailment of service to consumers (i.e., “rolling blackouts”) is required during a Stage 3 Emergency in amounts as needed to maintain Operating Reserve above 1%%.

ISO Alerts, Warnings, and Emergencies, February 1999, PG & E Exh. R at 6.

Jim McIntosh, Director of Grid Operations for the ISO and the person in charge of declaring Stage Three Emergencies, describes a system collapse as “voltage instability and blackout in the entire ... WSSC [Western System Coordinating Council] region, which has 14 states and two provinces of Canada and Mexico .... ” McIntosh Dep. at 7:22-8:5. One of the steps the ISO takes to avoid a system collapse is requesting utilities to curtail exports out of state. See id. at 8:19-24, 9:6-9; ISO Operating Procedure at 5, PG & E Exh. T.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sears Holdings Corporation
S.D. New York, 2023
In re Escalera Resources Co.
563 B.R. 336 (D. Colorado, 2017)
Koursa, Inc. v. Manroland, Inc.
971 F. Supp. 2d 765 (N.D. Illinois, 2013)
In re PMC Marketing Corp.
501 B.R. 17 (D. Puerto Rico, 2013)
GFI Wisconsin, Inc. v. Reedsburg Utility Commission
440 B.R. 791 (W.D. Wisconsin, 2010)
Klamath Off-Project Water Users, Inc. v. PacifiCorp
240 P.3d 94 (Court of Appeals of Oregon, 2010)
In re Erving Industries, Inc.
432 B.R. 354 (D. Massachusetts, 2010)
In Re Pilgrim's Pride Corp.
421 B.R. 231 (N.D. Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
271 B.R. 626, 47 U.C.C. Rep. Serv. 2d (West) 598, 2002 U.S. Dist. LEXIS 1350, 2001 WL 1705108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puget-sound-energy-inc-v-pacific-gas-electric-co-in-re-pacific-gas-cand-2002.