Beeche Systems Corp. v. D.A. Elia Construction Corp. (In Re Beeche Systems Corp.)

164 B.R. 12, 24 U.C.C. Rep. Serv. 2d (West) 1132, 1994 U.S. Dist. LEXIS 5657, 1994 WL 33364
CourtDistrict Court, N.D. New York
DecidedJanuary 24, 1994
Docket92-CV-1659(FJS)
StatusPublished
Cited by6 cases

This text of 164 B.R. 12 (Beeche Systems Corp. v. D.A. Elia Construction Corp. (In Re Beeche Systems Corp.)) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beeche Systems Corp. v. D.A. Elia Construction Corp. (In Re Beeche Systems Corp.), 164 B.R. 12, 24 U.C.C. Rep. Serv. 2d (West) 1132, 1994 U.S. Dist. LEXIS 5657, 1994 WL 33364 (N.D.N.Y. 1994).

Opinion

MEMORANDUM-DECISION AND ORDER

SCULLIN, District Judge.

I. Background

In November 1990, appellant D.A. Elia Construction Corp. (“Elia”) submitted a bid to the New York State Thruway Authority (“Thruway Authority”) to provide materials and perform services in connection with a pier rehabilitation project at the Castleton Bridge (the “project”). As part of its bid, Elia allocated $62,000 as an estimate for its cost in obtaining scaffolding equipment necessary to access the bridge. Elia was awarded this contract in December 1990. Elia contracted with appellee Beeche Systems Corp. (“Beeche”) to provide this scaffolding equipment (the “contract”) because Beeche had provided a similar scaffolding system to another contractor who had performed work for the Thruway Authority on the same bridge one year earlier. The parties eventually agreed that Elia would purchase the scaffolding from Beeche at a cost approximately twice its rental value, and that Elia had the right to require Beeche to repurchase the scaffolding system at 50% of the contract cost.

On January 9, 1991, Elia executed a purchase order with Beeche regarding this equipment for a purchase price of $117,-810.00. Under the terms of such agreement, 12/6% of this price was to be paid by Elia upon execution of the agreement, with the balance due 15 days after delivery of the system and acceptance of the equipment by the Thruway Authority.

On January 15, 1991, apparently unbeknownst to Elia, Beeche filed a voluntary petition for relief under Chapter 11 of the U.S. Bankruptcy Code (the “Code”). This filing for relief was allegedly precipitated by the Internal Revenue Service’s commencement of enforcement proceedings against Beeche to recover purportedly delinquent taxes.

After several delays by Beeche in submitting design proposals to the Thruway Authority regarding the scaffolding equipment, Elia’s project manager sent Beeche a letter dated February 28, 1991 that demanded that Beeche comply with the terms of the parties’ agreement and advised Beeche that it may be liable for backcharges if it failed to perform in accordance with the agreement. Beeche in turn demanded a modification of the agreement. Under the terms of this modification, Beeche was entitled to accelerated payments regarding the scaffolding apparatus. Even though Elia allegedly viewed Beeche’s proposal as “extortion,” Elia agreed to these modifications and to accelerated payment under the contract. Thereafter, the value of this contract was subsequently increased to $138,518.22 in April 1991, reflecting change orders requested by Elia. 1

On April 2, 1991, Beeche provided Elia with the scaffolding equipment in accordance *15 with the modified contract and as directed by Elia. On May 7, 1991, Elia acknowledged receipt of the equipment purchased and indicated that it would pay the balance due on the equipment in 15 days. Shortly after sending this letter, Elia claims that it became aware, for the first time, of Beeche’s status as a party in bankruptcy.

Elia claims that on June 4, 1991, due to Beeche’s failure to disclose the fact that it had filed for bankruptcy and Beeche’s delays in submitting design proposals to the Thruway Authority, it determined that Beeche had acted in bad faith and that there were serious questions raised about Beeche’s ability or willingness to comply with its contractual obligations. Therefore, rather than pay Beeche the $46,913.48 balance due under the contract, Elia sent Beeche a letter demanding that Beeche repurchase the scaffolding equipment for $69,259.11 — 50% of the purchase price. Elia also determined that it had the right to either set-off or recoup the $46,-913.48 which it owed Beeche against Beeche’s $69,259.11 obligation to repurchase the scaffolding system.

By letter dated July 22, 1991, Beeche demanded final payment from Elia under the contract and the return of the scaffolding equipment.

On March 27, 1992, Beeche commenced a suit to compel Elia to turn over the scaffolding equipment and pay the balance due under the contract, plus consequential damages. Elia’s answer to such complaint contained a counterclaim which sought judgment in the sum of $69,259.11 against Beeche, with interest.

On September 3, 1992, this matter was tried before Chief Judge Mahoney of the U.S. Bankruptcy Court for the Northern District of New York. In his decision' dated November 6, 1992, Judge Mahoney ordered Elia to turn the scaffolding equipment over to Beeche and denied Beeche’s further claim for damages. That court also determined that Elia’s claim with respect to the buy-back provision in the contract had been forfeited by Elia by its own actions. See Memorandum-Decision of the Bankruptcy Court (11/6/92) (“Mem.”) at 6. The instant appeal was filed on November 17, 1992.

In its appeal, Elia argues that Beeche’s insolvency and subsequent bankruptcy filing, as well as its failure to disclose such bankruptcy or to offer adequate assurance of performance constituted an anticipatory breach of the contract under the Uniform Commercial Code (“U.C.C.”) as adopted by New York. It also argues that it was entitled to either offset or recoup the amount due Beeche under the contract with the amount Beeche owed Elia under the buyback provision of the contract. It next contends that Beeehe’s failure to disclose its insolvency at the time of the contracting constituted fraud requiring rescission of the agreement. Elia further argues that the Bankruptcy Court improperly required Elia to turn over the scaffolding equipment without requiring Beeche to fully perform its repurchase obligation. Finally, Elia contends that Judge Mahoney “manifested a judicial intolerance and hostility towards Elia” which colored the lower court’s decision against Elia.

Beeche argues that the Bankruptcy Court’s decision should be affirmed, however it claims that it is entitled to the damages sought in its complaint, or that, at a minimum, Elia should be required to assure Beeche that the scaffolding equipment is in good working order at the time Elia turns over the equipment.

II. Discussion

(a) Anticipatory repudiation.

(i) Under U.C.C. § 2-610.

Elia claims that Beeche’s insolvency and subsequent bankruptcy constituted an anticipatory repudiation of the contract under U.C.C. § 2-610. This statute provides, in part, that:

When either party repudiates a contract with respect to a performance not yet due the loss of which will substantially impair the value of the contract to the other, the aggrieved party may:
[[Image here]]
b. resort to any remedy for breach even though he has notified the repudi *16 ating party that he would await the latter’s performance and has urged retraction; and
c. in either case suspend his oitm performance ...

(Emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koursa, Inc. v. Manroland, Inc.
971 F. Supp. 2d 765 (N.D. Illinois, 2013)
Validsa, Inc. v. PDVSA Services Inc.
632 F. Supp. 2d 1219 (S.D. Florida, 2009)
Bank of New York v. River Terrace Associates, LLC
23 A.D.3d 308 (Appellate Division of the Supreme Court of New York, 2005)
In Re Asia Global Crossing, Ltd.
326 B.R. 240 (S.D. New York, 2005)
In Re Economy Lodging Systems, Inc.
226 B.R. 840 (N.D. Ohio, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
164 B.R. 12, 24 U.C.C. Rep. Serv. 2d (West) 1132, 1994 U.S. Dist. LEXIS 5657, 1994 WL 33364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beeche-systems-corp-v-da-elia-construction-corp-in-re-beeche-systems-nynd-1994.