GFI Wisconsin, Inc. v. Reedsburg Utility Commission

440 B.R. 791, 73 U.C.C. Rep. Serv. 2d (West) 38, 2010 U.S. Dist. LEXIS 122681, 2010 WL 4595508
District Court, W.D. Wisconsin·Decided November 12, 2010·No. 10-cv-388-bbc·Published·Cited by 9 cases

Opinion

OPINION and ORDER

BARBARA B. CRABB, District Judge.

Appellant GFI Wisconsin, Inc., formerly known as Grede Foundries, Inc., appeals an order of the bankruptcy court allowing appellees Reedsburg Utility Commission and Wisconsin Electric Power Company to claim administrative priority status under 11 U.S.C. § 503(b)(9) for the value of electricity they supplied to appellant during the 20 days before appellant filed for bankruptcy. Appellant contends that because electricity is not a “good” within the meaning of § 503(b)(9), the bankruptcy court should have disallowed the claim. In addition, appellant contends that even if electricity is a good for purposes of § 503(b)(9), the bankruptcy court erred by failing to apply the “predominant purpose” test and by allowing appellees to recover the value of services that were bundled with the electricity charges.

This court has jurisdiction over the appeal pursuant to 28 U.S.C. § 158(a). The bankruptcy court entered an order on June 1, 2010, denying appellant’s objection to appellees’ § 503(b)(9) claims. This is a final order for purposes of § 158(a) because there is nothing more to do with respect to appellant’s objection. In re Smith, 582 F.3d 767, 776 (7th Cir.2009) (“An order of the bankruptcy court may be considered final, and thus immediately ap-pealable, when it definitively resolves a discrete dispute within the larger case.”); In re Ross-Tousey, 549 F.3d 1148, 1152 (7th Cir.2008) (“[A]n adjudication by the bankruptcy court is definitive because it cannot be affected by the resolution of any other issue in the proceeding, and therefore no purpose would be served by postponing the appeal to the proceeding’s conclusion.”) (internal quotations omitted).

I agree with the bankruptcy court that appellees may claim administrative priority for the electricity they provided appellant in the 20-day period before appellant filed its bankruptcy petition. Therefore, I will affirm the decision of the bankruptcy court denying appellant’s objection to the claims.

The following summary of relevant facts and proceedings is drawn from the record of the proceedings before the bankruptcy court. (All citations in the background section are to the bankruptcy court’s docket, In re: Grede Foundries, Inc., 09-14337-rdm.)

BACKGROUND

A. Facts before the Bankruptcy Court

On June 30, 2009, appellant GFI Wisconsin, formerly known as Grede Foundries, Inc., filed a chapter 11 bankruptcy petition in this district. Appellant owned several properties in Wisconsin that received electricity from appellees Reeds-burg Utility Commission and Wisconsin Electric Power Company over a time period that includes the 20 days before the petition date.

On September 25, 2009, appellees submitted claims seeking administrative priority status under § 503(b)(9) for the value of the electricity they provided appellant during the 20-day period. Appellant objected to the claims on several grounds, one of which was that electric services are not goods for purposes of § 503(b)(9). Ap-pellees challenged appellant’s objection and the parties agreed to submit the claims and objections to the bankruptcy court on stipulations of facts and briefs, forgoing an evidentiary hearing.

On March 29, 2010, appellant filed motions to disallow the claims, a brief in *795 support of the motions and facts to which the parties had stipulated. Among other things, they stipulated that

• The electricity supplied by [appellees] to [appellant] during the Twenty-Day Period was metered at [appellant’s] premises as it was being drawn and consumed by [appellant]; and
• Given the regulatory requirement that [appellees] make a pro rata estimate of the charges incurred during the Twenty-Day Period, [appellant] does not object to the amount of the Twenty-Day Claim.

Dkt. # 1887 at ¶ ¶ 7, 15 # 1890 at ¶¶ 7, 13. In its brief, appellant argued that appel-lees’ claims were for electrical services, not goods, because electricity is not movable and identifiable at the time of the contract of sale, as required under the definition of goods found in the Uniform Commercial Code, Wis. Stat. § 402.105(l)(c). Dkt. # 1892 at ¶ 4. Appellant also argued that § 503(b)(9) claims are limited to goods capable of being reclaimed by a creditor, and electricity cannot be reclaimed. Id. at 7.

In their responses, appellees also relied on the UCC definition of goods and argued that electricity is both movable and identifiable at the time it is metered and thus, satisfies the definition of goods under the UCC. Dkt. ## 1949, 1950. Appellees relied heavily on In re Erving Industries, Inc., 432 B.R. 354 (Bankr.D.Mass. Apr.7, 2010), in which the bankruptcy court concluded that electricity is a good. Appel-lees cited specifically the following language in Erving Industries:

At the time the electricity is identified to the contract [by passing through the meter], it is literally moving, and it remains movable for some period of time thereafter. The electricity continues to move through the customer’s electrical wiring until it is ultimately put to use. This process may occur at speeds so imperceptible that consumption appears to occur simultaneous with identification, but logic compels the conclusion that electricity is moving (and remains in motion) until it reaches the product sought to be electrified.

Id. at 370.

Appellant filed a reply brief, dkt. # 1956, attempting to distinguish Erving Industries and discredit its conclusion. First, significant differences between the Massachusetts and Wisconsin electricity markets made the case distinguishable. Second, as a matter of physics, electricity is not movable after it has been metered. Appellant submitted the affidavit of Kevin Vesper-man, an engineer, to explain the nature of electricity. Dkt. # 1957. Vesperman described the nature of electricity as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

GFI Wisconsin, Inc. v. Reedsburg Utility Commission, 440 B.R. 791, 73 U.C.C. Rep. Serv. 2d (West) 38, 2010 U.S. Dist. LEXIS 122681, 2010 WL 4595508 (W.D. Wis. 2010).

440 B.R. 791 (GFI Wisconsin, Inc. v. Reedsburg Utility Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sears Holdings Corporation
S.D. New York, 2023
In re Escalera Resources Co.
563 B.R. 336 (D. Colorado, 2017)
Untitled Case
D. Puerto Rico, 2014
Gwendolyn Phillips v. Asset Acceptance, LLC
736 F.3d 1076 (Seventh Circuit, 2013)
In re NE Opco, Inc.
501 B.R. 233 (D. Delaware, 2013)
In re PMC Marketing Corp.
501 B.R. 17 (D. Puerto Rico, 2013)
In re Woller
483 B.R. 886 (W.D. Wisconsin, 2012)