Mancuso v. Southern California Edison Co.

232 Cal. App. 3d 88, 283 Cal. Rptr. 300, 91 Daily Journal DAR 8460, 15 U.C.C. Rep. Serv. 2d (West) 49, 1991 Cal. App. LEXIS 780
CourtCalifornia Court of Appeal
DecidedJuly 11, 1991
DocketB043903
StatusPublished
Cited by13 cases

This text of 232 Cal. App. 3d 88 (Mancuso v. Southern California Edison Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mancuso v. Southern California Edison Co., 232 Cal. App. 3d 88, 283 Cal. Rptr. 300, 91 Daily Journal DAR 8460, 15 U.C.C. Rep. Serv. 2d (West) 49, 1991 Cal. App. LEXIS 780 (Cal. Ct. App. 1991).

Opinion

Opinion

CROSKEY, J.

—The defendant and appellant Southern California Edison Company (Edison) appeals a judgment entered in favor of the plaintiff and respondent Anthony Mancuso following the trial court’s summary adjudication of the issue of liability and a jury verdict as to damages. Plaintiff’s damages arose from the destruction of his business by a fire caused by an excessive amount of electrical current conducted to plaintiff’s premises through Edison’s facilities. Although it is undisputed that the excessive electrical current was the result of a lightning strike upon Edison’s facilities, the trial court determined that Edison was liable to plaintiff, as a matter of law, on a product liability theory. As we conclude that lightning generated electricity is not a “product” for purposes of strict liability, we hold that the trial court’s determination was erroneous. We therefore reverse the judgment and remand for further proceedings.

*92 Factual and Procedural Background 1

Plaintiff owned and operated an upholstery and furniture shop in Torrance, California. He conducted his business in a wood building which measured approximately 30 feet by 30 feet and was routinely stocked with such items as cloth, wood materials, glue and cleaning solvents. Electrical service was supplied to plaintiff’s building by Edison.

Adjacent to plaintiff’s building was an Edison utility pole which supported 16-kilovolt (KV) primary electrical conductors and a transformer. Electrical service to plaintiff’s building was supplied by secondary service conductors from the transformer to two meter panels located on plaintiff’s premises. The transformer stepped down the 16-KV primary voltage generated by Edison to a service voltage for use by customers after passing through an Edison meter. 2 The facilities owned by Edison by which such service is provided include the primary conductors; utility pole and cross-arms, insulators, fuses, transformer, secondary service conductors and meter panels.

On April 27, 1984, the Torrance area experienced an electrical storm of unusual intensity. During the course of this storm, a severe lightning stroke hit the Edison facilities adjacent to plaintiff’s business. Eyewitnesses described the stroke as hitting the Edison pole or transformer, causing the transformer to explode into flames. The lightning also generated electricity which, in seeking a path to ground, traversed the service conductors to plaintiff’s building and caused sparks and flames to be emitted along the entire length of the service wires. When the lightning generated electricity reached plaintiff’s building its extraordinarily high level of energy caused one of the meter panels on the premises to explode. The resulting fire on the premises was apparently caused by heated material from the explosion coming into contact with combustible items in plaintiff’s shop. The fire totally destroyed the premises and its contents.

The record before us reflects that the Edison distribution system, as designed, contained excess voltage or lightning protection features, including the use of wooden poles, insulators and fuses. The transformer was grounded and rated to withstand a 95-KV impulse. 3 However, the facilities *93 immediately adjacent to plaintiff’s premises were not constructed with any additional lightning arrester equipment. Edison makes its determination whether to install such additional equipment at any given location upon a cost benefit analysis. Historical data of electrical activity in a particular area is weighed against the cost of installing arresters. Another factor considered by Edison is that such installations involve additional equipment on a functioning electrical distribution system, thus increasing the risk of failure and customer service interruption. Edison regarded the area where plaintiff’s business was located as involving low lightning activity. 4

On July 30, 1984, plaintiff filed this action against Edison seeking damages for the property loss which he had sustained. In this first pleading plaintiff sought recovery on the theories of negligence and product liability. Subsequently, on April 26, 1988, the trial court permitted plaintiff to file a first amended complaint in which he added a third cause of action for breach of the implied warranty of fitness.

On December 12, 1988, the trial court heard and considered in limine motions filed by both plaintiff and Edison. Each party conceded in their moving papers that the fire had been caused by a lightning stroke on Edison’s facilities. However, they took diametrically opposite positions on the consequences of this undisputed fact. Edison asked the court not to submit the case to the jury on a product liability theory. Edison argued that the evidence would establish that the electricity which caused the fire was not generated by Edison, but rather by a naturally caused stroke of lightning. Plaintiff responded that Edison should not be permitted to make this argument since it was, in effect, the assertion of the defense of “act of God” which, under the facts of this case, had no application. Plaintiff’s position, concurred in by the trial court, was that the “act of God” defense cannot be raised if the particular natural event was foreseeable.

The trial court agreed with plaintiff on both points. It denied Edison’s motion and held that plaintiff could proceed on a product liability theory. It further ruled that since Edison had not raised an issue of fact as to whether a lightning strike was foreseeable, then such an event could not be the intervening superseding cause required to establish an “act of God” defense.

Based upon these rulings, plaintiff filed a motion for summary adjudication of the issue of liability on the product liability claims contained in the *94 second and third causes of action of the first amended complaint. On January 11,1989, the court granted the motion, thus holding that Edison was liable to plaintiff, as a matter of law, for the damages which he had sustained. 5 The court then continued the matter for a jury trial on that issue of damages. 6 On May 24, 1989, the jury returned a special verdict awarding damages to plaintiff in the sum of $100,295, to which $9,408.90 in prejudgment interest was added. Judgment was entered on December 6, 1989, and Edison filed a timely appeal. 7

*95 Contentions on Appeal

Essentially, Edison asserts four principal arguments: 8

1. Strict product liability is not a proper theory of recovery to be applied against a regulated public utility;
2. The distribution of electricity by a public utility is a service, not a sale of a product, and therefore a product liability theory is inappropriate;
3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garcia v. Roberts CA5
California Court of Appeal, 2013
In re Erving Industries, Inc.
432 B.R. 354 (D. Massachusetts, 2010)
Buxbaum v. Aetna Life and Casualty Company
126 Cal. Rptr. 2d 682 (California Court of Appeal, 2002)
Joe Kennedy v. Southern California Edison Company
219 F.3d 988 (Ninth Circuit, 2000)
Kennedy v. Southern California Edison Co.
219 F.3d 988 (Ninth Circuit, 2000)
Balke v. Central Missouri Electric Cooperative
966 S.W.2d 15 (Missouri Court of Appeals, 1998)
Recorded Picture Co. [Prods.] Ltd. v. Nelson Entm't, Inc.
53 Cal. App. 4th 350 (California Court of Appeal, 1997)
Curtiss v. Northeast Utilities, No. Cv92-0511572-S (Dec. 5, 1994)
1994 Conn. Super. Ct. 12247 (Connecticut Superior Court, 1994)
Stein v. Southern California Edison Co.
7 Cal. App. 4th 565 (California Court of Appeal, 1992)
North Bay Schools Insurance Authority v. Industrial Indemnity Co.
6 Cal. App. 4th 1741 (California Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
232 Cal. App. 3d 88, 283 Cal. Rptr. 300, 91 Daily Journal DAR 8460, 15 U.C.C. Rep. Serv. 2d (West) 49, 1991 Cal. App. LEXIS 780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mancuso-v-southern-california-edison-co-calctapp-1991.