Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission

502 A.2d 130, 509 Pa. 324, 1985 Pa. LEXIS 442
CourtSupreme Court of Pennsylvania
DecidedDecember 9, 1985
Docket31 and 32 M.D. appeal docket 1984
StatusPublished
Cited by18 cases

This text of 502 A.2d 130 (Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 502 A.2d 130, 509 Pa. 324, 1985 Pa. LEXIS 442 (Pa. 1985).

Opinion

OPINION OF THE COURT

FLAHERTY, Justice.

This is an appeal from an order of the Commonwealth Court which affirmed orders of the Pennsylvania Public Utility Commission (PUC) in certain electric utility rate-setting cases. Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 78 Pa.Commw.Ct. 402, 467 A.2d 1367 (1983). The cases arose as repercussions of the 1979 accident at the Three Mile Island nuclear generating station near Harrisburg, Pennsylvania. The accident involved the near melt-down of a nuclear reactor, and was the most serious in the history of nuclear power generating facilities in the United States. The Three Mile Island incident has had nationwide implications, not only with respect to the future of nuclear power generation in the United States, but also in relation to the resultingly imperiled financial viability of some of our nation’s largest public utility companies. It is with this latter aspect of the incident, as regards the diminished financial viability of the companies that own the Three Mile Island station, that the instant appeal is concerned.

The appellants, Metropolitan Edison Company and Pennsylvania Electric Company, own 50% and 25% interests, respectively, in the Three Mile Island station. In 1979, shortly after the nuclear accident, the PUC set reduced permanent rates for these companies, and these new rates reflected the removal from the rate base of all costs associated with Unit 2, the unit involved in the accident, on the basis that Unit 2 had been so severely damaged as to render it no longer useful in the public service. This action was in accord with well-established principles that rates charged the public for utility services are to provide a return upon only such property of the utility as is used and useful in the public service. See 66 Pa.C.S.A. § 1310(d) (utility entitled to “fair return upon the fair value of the property of such *327 public utility, used and useful in its public service....”); Scranton v. Scranton Steam Heat Co., 405 Pa. 397, 401, 176 A.2d 86, 88 (1961). See also Denver Union Stock Yard Co. v. United States, 304 U.S. 470, 475, 58 S.Ct. 990, 994, 82 L.Ed. 1469, 1475-1476 (1938) (Under the due process clause of the Fifth Amendment, a regulated utility “is entitled to rates, not per se excessive and extortionate, sufficient to yield a reasonable rate of return upon the value of property used, at the time it is being used, to render the services. But it is not entitled to have included any property not used and useful for that purpose.” (citations omitted)).

At the time of the accident at Unit 2, another nuclear reactor at Three Mile Island, Unit 1, had been shut down for refueling. Following the accident at Unit 2, Unit 1 remained shut down by order of the Federal Nuclear Regulatory Commission. Shortly after ordering reduced rates based on the lack of continued usefulness of Unit 2, the PUC, in 1980, made a determination that Unit 1 was likewise no longer useful in the public service, because its return to service was not “imminent” or “certain,” and, accordingly, the PUC established temporary reduced rates, reflecting the exclusion of all costs associated with Unit 1 from the companies’ rate bases. These temporary reduced rates for Metropolitan Edison and Pennsylvania Electric were, on an annual basis, $26.9 million and $11.7 million less, respectively, than their existing rates. The companies filed complaints alleging that these new rates were unjust and unreasonable, and filed tariffs seeking substantial rate increases. In these tariffs, the companies sought to include in their rate bases costs and investments related to Unit 1, but the companies have not sought in this case to do the same with respect to the damaged reactor, Unit 2. Hearings were held before an Administrative Law Judge, and the decisions recommended by the Administrative Law Judge were adopted, with only minor modifications, by the PUC in 1981. The final PUC orders allowed Metropolitan Edison a rate increase, over and above the challenged temporary rates, of nearly $52 million (including $11 million *328 covering Unit 1 restart costs). Pennsylvania Electric was awarded an increase, over and above the temporary rates, of approximately $55.5 million (including $5.5 million covering Unit 1 restart costs). Metropolitan Edison and Pennsylvania Electric had sought larger rate increases, of $76.4 million and $67.4 million respectively. Appeals were taken to the Commonwealth Court, where the orders of the PUC were affirmed. The instant appeal ensued.

The issue presented in this appeal is a narrow one, namely whether the decision of the United States Supreme Court in Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333 (1944) established a requirement, of constitutional dimension, that utility rates set by regulatory authorities be set at sufficiently high levels as to guarantee, irrespective of countervailing consumer interests, the continued financial integrity of the utilities concerned. In Hope, the United States Supreme Court addressed the considerations to be taken into account by the Federal Power Commission in setting “just and reasonable” rates for natural gas companies, as required under § 4(a) of the Natural Gas Act, 15 U.S.C. § 717. The Court noted that there were no applicable constitutional requirements more exacting than the requirement of “just and reasonable” rates set forth in the Act. 320 U.S. at 607, 64 S.Ct. at 290, 88 L.Ed. at 347. Indeed, in the Court’s subsequent decision in Permian Basin Area Bate Cases, 390 U.S. 747, 770, 88 S.Ct. 1344, 1361, 20 L.Ed.2d 312, 338 (1968), reh. den. 392 U.S. 917, 88 S.Ct. 2050, 20 L.Ed.2d 1379 (1968), it was held that “the just and reasonable standard of the Natural Gas Act ‘coincides ’ with the applicable constitutional standards ... and any rate selected by the Commission from the broad zone of reasonableness permitted by the Act cannot properly be attacked as confiscatory.” (emphasis added) (citation omitted). See also Federal Power Commission v. Natural Gas Pipeline Co., 315 U.S. 575, 585-586, 62 S.Ct. 736, 742-43, 86 L.Ed. 1037, 1049 (1942). It is to be noted that the constitutionally based requirement of “just and reasonable” rates, under the Fifth *329 and Fourteenth Amendments, is in effect embodied in terminology found in the Pennsylvania Public Utility Law, which governs the rates being challenged in the instant appeal. Indeed, in Pennsylvania Public Utility Commission v. Pennsylvania Gas and Water Co., 492 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emporium Water Co. v. Public Utility Commission
859 A.2d 20 (Commonwealth Court of Pennsylvania, 2004)
In Re Citizens Utilities Co.
769 A.2d 19 (Supreme Court of Vermont, 2000)
Public Advocate v. Philadelphia Gas Commission
674 A.2d 1056 (Supreme Court of Pennsylvania, 1996)
Popowsky v. Pennsylvania Public Utility Commission
665 A.2d 808 (Supreme Court of Pennsylvania, 1995)
Popowsky v. Pennsylvania Public Utility Commission
645 A.2d 912 (Commonwealth Court of Pennsylvania, 1994)
Ohio Edison Co. v. Public Utilities Commission
589 N.E.2d 1292 (Ohio Supreme Court, 1992)
Gulf States Utilities v. PSC
578 So. 2d 71 (Supreme Court of Louisiana, 1991)
Alliance for Aff. Energy v. New Orleans
578 So. 2d 949 (Louisiana Court of Appeal, 1991)
Pennsylvania Power Co. v. Pennsylvania Public Utility Commission
561 A.2d 43 (Commonwealth Court of Pennsylvania, 1989)
Pennsylvania Public Utility Commission v. Philadelphia Electric Co.
561 A.2d 1224 (Supreme Court of Pennsylvania, 1989)
Philadelphia Electric Co. v. Pennsylvania Public Utility Commission
538 A.2d 98 (Commonwealth Court of Pennsylvania, 1988)
In re Public Service Co.
539 A.2d 263 (Supreme Court of New Hampshire, 1988)
Barasch v. Pennsylvania Public Utility Commission
532 A.2d 325 (Supreme Court of Pennsylvania, 1987)
Pennsylvania Power & Light Co. v. Pennsylvania Public Utility Commission
516 A.2d 426 (Commonwealth Court of Pennsylvania, 1986)
Kansas Gas & Electric Co. v. Kansas Corporation Comm'n
720 P.2d 1063 (Supreme Court of Kansas, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
502 A.2d 130, 509 Pa. 324, 1985 Pa. LEXIS 442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-co-v-pennsylvania-public-utility-commission-pa-1985.