In re Public Service Co.

539 A.2d 263, 130 N.H. 265, 1988 N.H. LEXIS 1
CourtSupreme Court of New Hampshire
DecidedJanuary 26, 1988
DocketNo. 87-311
StatusPublished
Cited by45 cases

This text of 539 A.2d 263 (In re Public Service Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Public Service Co., 539 A.2d 263, 130 N.H. 265, 1988 N.H. LEXIS 1 (N.H. 1988).

Opinion

Batchelder, J.

This interlocutory transfer, filed by the New Hampshire Public Utilities Commission (PUC or commission) pursuant to RSA 365:20, raises the issue of the constitutionality of applying RSA 378:30-a to the fixing of electric utility rates in an emergency rate proceeding. The commission reserved, certified, and transferred three questions of law which are set forth in the discussion below. We answer all three questions in the negative, and hold that RSA 378:30-a is constitutional under the State and Federal Constitutions on the facts presented to us in this transfer.

I. Facts and Procedural History

This interlocutory transfer is viewed, and its issues decided, against a factual background which must be unique in the annals of public utility financing. Public Service Company of New [268]*268Hampshire (PSNH or company) is the owner of an approximately 35% interest in the Seabrook Unit I nuclear generating station, which for practical purposes had its construction phase completed on or about October 31, 1986, at a cost to PSNH of $1,770,617,913. The total project cost, we were told at argument, has, since the completion date, been increasing at the rate of $50 million per month. Because its final licensing proceeding is yet to be complete, the plant is producing neither electricity nor income, and the likelihood and timing of either event are matters of speculation and uncertainty.

To ameliorate the costly effects of these circumstances, PSNH, on August 5, 1987, petitioned the commission to “Alter Existing Rates on Account of Emergency Circumstances,” docketed as DR 87-151 (application). PSNH requested an emergency rate surcharge which would produce approximately $70.98 million in additional annual revenues, an increase of 15% based on sales for the twelve months ended December 31, 1986. In its application, PSNH proposed that the commission allow the company a special emergency rate base increment of $464.5 million, representing approximately 27% of PSNH’s total investment of $1.77 billion in Unit I. PSNH proposed also that the commission allow a special emergency rate of return of 15.28%, the company’s cost of debt capital as determined by the commission in PSNH’s most recent rate case, DR 86-122. See Report and Order No. 18,726 (June 1987). In order to expedite consideration and determination of this application, PSNH submitted, on the same date, a request that the commission reserve, certify, and transfer the following question to this court in accordance with RSA 365:20:

“Where a public utility alleges that at its currently allowed rates as restricted by RSA 378:30-a,
(1) Its cash provided from internal sources is insufficient to meet all requirements of the conduct of its business;
(2) Its access to cash from external sources through sale of its securities is so restricted as to be unavailable upon reasonable terms, and
(3) Accordingly, its earnings are insufficient to enable it to attract capital or to maintain its credit, or otherwise to support its financial integrity,
[269]*269Is the public utility entitled to a hearing to establish a level of rates to restore its financial integrity consistent with the interests of customers, notwithstanding RSA 378:30-a, the so-called ‘anti-CWIP’ statute?”

The commission anticipated that answers to the question set forth in the requested transfer were likely to control the outcome of PSNH’s request for emergency relief in DR 87-151 and granted PSNH’s request without holding a hearing. Furthermore, without making specific findings of fact, the PUC provided this court with basic facts that the commission accepted for purposes of this transfer. The commission also added a second question which addressed the constitutionality of applying RSA 378:30-a:

“Does the U.S. Constitution or the N.H. Constitution require or allow the Commission to, when setting rates, include construction work in progress [(CWIP)] on a construction project in rate base before said construction project is actually providing service to customers, notwithstanding the requirements of RSA 378:30-a?”

Following the filing of the interlocutory transfer, a prehearing evaluation conference was held before Howard J. Zibel, Esquire, Deputy Clerk of this court, for the Supreme Court on August 25, 1987, the primary focus of which was consideration of the adequacy of the factual record. As a result of that conference, we deferred acceptance of the transfer in an order dated September 2, 1987, until the commission conducted hearings and made findings of fact sufficient for “informed consideration of [the] constitutional issues.” Appeal of Public Serv. Co. of N.H., 125 N.H. 46, 48, 480 A.2d 20, 21 (1984). Specifically, this court requested the commission to make findings of fact on the following issues:

“a. The claimed need to include some of the company’s investment in the Seabrook I reactor in the company’s rate base in order to obtain the cash required by the end of 1987 to make interest payments as they come due, to pay off existing debt as it matures and to pay for the expansion of services to customers.
b. The date upon which the commission first authorized inclusion of such investment in the rate base, and the amounts of the company’s investment prior to that date, between that date and the effective date of § 30-a, and thereafter.”

[270]*270The commission held hearings on the proposed issues on September 16, 17, and 21, and on October 16, 1987, submitted to this court a record reflecting findings of fact on both issues. See Report and Sixth Supplemental Order No. 18,873. A supplemental report and record was transferred to this court on November 2. Report and Ninth Supplemental Order No. 18,890.

Under issue a., the PUC found with respect to the “claimed need” of PSNH that it was unlikely that PSNH would be in a position to meet its cash obligations as they became due: namely, interest and principal payments on debts, expansion of service to customers, and fuel expenses, payroll, and other related expenses. The commission examined two traditional sources of funds for PSNH: external financing and rates. The PUC found that financial markets are unwilling to provide additional new funds for PSNH due to investor perceptions of high risk. The commission noted, however, that there is the possibility that existing debt could be restructured, but it is improbable that this would occur before January, 1988. External financing, therefore, is not a dependable alternative for restoring PSNH’s financial integrity.

The other source of funds for PSNH is rates. Before considering the variables involved in an actual rate increase, the commission examined two rate-related alternatives. The commission found that PSNH could delay a refund owed to ratepayers ordered by the PUC in a previous docket. This would provide approximately $21 million, and would permit PSNH to meet its cash obligations into 1988. However, PSNH did not request authorization to delay the refunds, and the commission did not intend to authorize such a delay sua sponte.

The second alternative dealt with the possibility of PSNH’s successfully appealing the prior rate order in DR 86-122.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Richard Horton & a. v. David Clemens & a.
Supreme Court of New Hampshire, 2020
State v. Moussa
53 A.3d 630 (Supreme Court of New Hampshire, 2012)
Appeal of Union Telephone Co.
999 A.2d 336 (Supreme Court of New Hampshire, 2010)
Bel Air Associates v. New Hampshire Department of Health & Human Services
910 A.2d 1232 (Supreme Court of New Hampshire, 2006)
Soraghan v. Mt. Cranmore Ski Resort, Inc.
881 A.2d 693 (Supreme Court of New Hampshire, 2005)
In re Glaude
855 A.2d 494 (Supreme Court of New Hampshire, 2004)
City of Corpus Christi v. Public Utility Commission of Texas
51 S.W.3d 231 (Texas Supreme Court, 2001)
Appeal of Campaign for Ratepayers Rights
766 A.2d 702 (Supreme Court of New Hampshire, 2001)
In Re Citizens Utilities Co.
769 A.2d 19 (Supreme Court of Vermont, 2000)
Rye Beach Country Club, Inc. v. Town of Rye
719 A.2d 623 (Supreme Court of New Hampshire, 1998)
Galloway v. Chicago-Soft, Ltd.
713 A.2d 982 (Supreme Court of New Hampshire, 1998)
Cheever v. Southern New Hampshire Regional Medical Center
688 A.2d 565 (Supreme Court of New Hampshire, 1997)
Appeal of Ashland Electric Department
682 A.2d 710 (Supreme Court of New Hampshire, 1996)
State v. Farrow
667 A.2d 1029 (Supreme Court of New Hampshire, 1995)
Citizens Utility Board v. Illinois Commerce Commission
658 N.E.2d 1194 (Appellate Court of Illinois, 1995)
State v. Woods
654 A.2d 960 (Supreme Court of New Hampshire, 1995)
Appeal of Gielen
652 A.2d 144 (Supreme Court of New Hampshire, 1994)
Bartlett v. Giguere (In Re Bartlett)
168 B.R. 488 (D. New Hampshire, 1994)
Barksdale v. Town of Epsom
618 A.2d 814 (Supreme Court of New Hampshire, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
539 A.2d 263, 130 N.H. 265, 1988 N.H. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-public-service-co-nh-1988.