Pennsylvania Public Utility Commission v. Philadelphia Electric Co.

561 A.2d 1224, 522 Pa. 338, 1989 Pa. LEXIS 330
CourtSupreme Court of Pennsylvania
DecidedJuly 18, 1989
Docket116 E.D. and 117 E.D. Appeal Dockets 1988
StatusPublished
Cited by10 cases

This text of 561 A.2d 1224 (Pennsylvania Public Utility Commission v. Philadelphia Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Public Utility Commission v. Philadelphia Electric Co., 561 A.2d 1224, 522 Pa. 338, 1989 Pa. LEXIS 330 (Pa. 1989).

Opinion

OPINION

ZAPPALA, Justice.

In this appeal, we are requested to review the Opinion and Order of the Commonwealth Court reversing the Order of the Pennsylvania Public Utility Commission (Commission) which had disallowed a $57 million rate increase. 114 Pa.Cmwlth. 22, 538 A.2d 98. The proposed rate increase was necessary to offset energy replacement costs incurred as a result of the closing of the Salem and Peach Bottom nuclear power plants on two occasions each. The Commission denied the Appellee’s request, finding that part of the energy replacement costs were caused by mismanagement. Furthermore, the Commission held that since one of the outages was caused by a manufacturing defect and that Appellee was in the best position to pursue redress against the manufacturer, no additional costs should be passed on to the ratepayer. Commonwealth Court reversed, holding that the Commission used an incorrect standard of care to evaluate Appellee’s actions and that it was improper to impute a third party’s negligence to Appellee under the *341 current record. Because of the important issues raised, we granted the Appellants’ petitions for allowance of appeal.

The requisite facts are not in dispute. On February 22, 1983, while the nuclear reactor at Salem 1 was shut down for a scheduled refueling outage and as attempts were being made to restart the unit, the automatic protection system used to shut down the nuclear reactor failed. However, this failure went undetected until three days later when a second failure occurred. As a result of the second failure, the Nuclear Regulatory Commission (NRC) instituted an investigation which culminated in the Appellee paying an $850,000 fine and the scheduling of a target restart date of May 21, 1983. The NRC investigation uncovered inadequate operations with regard to maintenance and testing of current circuit breakers and related component parts, inadequate training of operators and overall station management. Prior to restarting, NRC required that the Appellee develop and demonstrate procedures to cure these problems. Although the actual restart had been set for April 29, 1983, it had to be cancelled due to Appellee’s discovery of shellfish infestation in cooling water lines. Restart finally occurred on May 21, 1983.

The following year, on February 24, 1984, the Salem 1 generator failed. It appears that this failure was caused by the defective manufacturing of resins which surround the coils that protect the generator from the ill effects of vibrations. This power outage lasted until October 22, 1984.

In addition to the problems at the Salem plant, problems were being experienced at the Peach Bottom Plant also. Although originally shut down for refueling, this shutdown period was extended for almost eight months as a result of problems with cracking in pipes, reactor cavity overflow and difficulty in welding and valve joints. Similar problems occurred at a second Peach Bottom unit resulting in a shutdown from July 4, 1983 through December 3, 1983.

After extensive hearings before an administrative law judge, the Appellee’s request for reimbursement of energy *342 replacement costs for the Salem 1 outage of February 1983 and February 1984 were disallowed. In addition, the judge determined that Appellee was responsible for seven days of outage at Peach Bottom Unit 3 and forty hours at Peach Bottom Unit 2. This finding excluded another $2.5 million from the requested rate increase.

On appeal to Commonwealth Court, that Court reversed, finding that the Commission had relied upon an improper standard of care in evaluating the Appellee’s actions, that Appellee could not be denied reimbursement of energy replacement costs for Westinghouse’s tortious conduct unless the Commission made a finding that Appellee had actual control over Westinghouse, that the NRC was dilatory in approving the restart for Peach Bottom Unit 2 and that the gasket leak in Peach Bottom Unit 3 was totally unforeseeable. Commonwealth Court then remanded the case to the Commission for further development of the record and review in light of that Court’s determination as to the proper standard of care.

Our scope of review of the actions of a Commonwealth agency is controlled by statute:

... After hearing, the court shall affirm the adjudication unless it shall find that the adjudication is in violation of the constitutional rights of the appellant, or is not in accordance with law, or that the provisions of Subchapter A of Chapter 5 (relating to practice and procedure of Commonwealth agencies) have been violated in the proceedings before the agency, or that any finding of fact made by the agency and necessary to support its adjudication is not supported by substantial evidence____

2 Pa.C.S. § 704. In further explaining the court’s role in reviewing decisions of the Commission, Commonwealth Court correctly stated:

[T]he appellate courts cannot conceive an independent judgment from the record, and substitute it for the judgment of the PUC. We may not indulge in the process of weighing evidence in resolving conflicts and testimony. The PUC’s discretionary findings and conclusions must be *343 accepted unless they are totally without support in the record, are based on an error of law, or are unconstitutional.

Pennsylvania Public Utility Commission v. Pennsylvania Gas and Water Company, 19 Pa.Commw. 214, 220, 341 A.2d 239, 244 (1975), rev’d on other grounds, 492 Pa. 326, 424 A.2d 1213 (1980), cert. denied 454 U.S. 824, 102 S.Ct. 112, 70 L.Ed.2d 97 (1981). See also, McGovern’s Estate v. State Employee’s Retirement Board, 512 Pa. 377, 517 A.2d 523 (1986).

In this appeal we are requested to review the propriety of a requested rate increase. Under Section 1301 of the Public Utility Code, 66 Pa.C.S. § 1301, all established rates must be just and reasonable:

Every rate made, demanded, or received by any public utility, or by any two or more public utilities jointly, shall be just and reasonable, and in conformity with regulations or orders of the commission____

66 Pa.C.S.A. § 1301. In determining whether a rate increase is “just and reasonable”, the Commission must balance the prices charged to the customer with the rate of return on capital to the investor. Pennsylvania Electric v. Pennsylvania Public Utility Commission, 509 Pa. 324, 502 A.2d 130 (1985). Furthermore, in undertaking this balancing process, the Commission must take into consideration reasonable costs of producing the power source. Metropolitan Edison v. Pennsylvania Public Utility Commission, 62 Pa.Commw.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burhans-Crouse Funeral Home v. PA PUC
Commonwealth Court of Pennsylvania, 2025
Pickford v. Public Utility Commission
4 A.3d 707 (Commonwealth Court of Pennsylvania, 2010)
Entergy Gulf States v. PUBLIC SERV. COM'N
726 So. 2d 870 (Supreme Court of Louisiana, 1999)
Indianapolis Power & Light Co. v. Pennsylvania Public Utility Commission
711 A.2d 1071 (Commonwealth Court of Pennsylvania, 1998)
Popowsky v. Pennsylvania Public Utility Commission
669 A.2d 1029 (Commonwealth Court of Pennsylvania, 1995)
Popowsky v. Pennsylvania Public Utility Commission
665 A.2d 808 (Supreme Court of Pennsylvania, 1995)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
629 A.2d 221 (Commonwealth Court of Pennsylvania, 1993)
Pennsylvania Power Co. v. Pennsylvania Public Utility Commission
625 A.2d 719 (Commonwealth Court of Pennsylvania, 1993)
Arrowhead Public Service Corp. v. Pennsylvania Public Utility Commission
600 A.2d 251 (Commonwealth Court of Pennsylvania, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
561 A.2d 1224, 522 Pa. 338, 1989 Pa. LEXIS 330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-public-utility-commission-v-philadelphia-electric-co-pa-1989.