Philadelphia Electric Co. v. Pennsylvania Public Utility Commission

538 A.2d 98, 114 Pa. Commw. 22, 90 P.U.R.4th 560, 1988 Pa. Commw. LEXIS 319
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 24, 1988
DocketAppeal, No. 3204 C.D. 1985
StatusPublished
Cited by3 cases

This text of 538 A.2d 98 (Philadelphia Electric Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Electric Co. v. Pennsylvania Public Utility Commission, 538 A.2d 98, 114 Pa. Commw. 22, 90 P.U.R.4th 560, 1988 Pa. Commw. LEXIS 319 (Pa. Ct. App. 1988).

Opinions

Opinion by

President Judge Crumlish, Jr.,

Philadelphia Electric Company (PECO) appeals a Pennsylvania Public Utility Commission (PUC) order which, in pertinent part, disallowed approximately $58 million in replacement power costs incurred during certain outages at the Salem Nuclear Generating Station Unit 1 (Salem 1), the Peach Bottom Atomic Power Station Units 2 and 3 (Peach Bottom 2 and 3) and the Eddystone Power Station. The Office of Consumer Advocate (OCA) has intervened on behalf of the PUC in this appeal.

On July 19, 1983, the OCA filed a Petition for an Investigation and an Order to Show Cause, alleging imprudence as to PECOs entitlement claim to replacement power costs related to a 1983 Salem 1 outage. The PUC granted the petition and instituted the investigation. Four days of hearings were held before Administrative Law Judge (ALJ) Dennis Harnish.

Prior to the issuance of a recommended decision, the petition and order were consolidated with Energy Cost Rate (ECR) Statement No. 8 which proposed an increase of approximately $151 million in the ECR.1 This amount purported to represent undercollections of energy costs associated with the 1983 Salem 1 outage, as well as projected costs attributable in large measure to a 1984 Salem 1 outage, 1983 and 1984 Peach Bottom 2 and 3 outages and a 1983-1984 Eddystone 1 outage. Complaints were filed by OCA and others;2 the PUC [25]*25then suspended approximately $106 million of PECOs ECR request and conducted a consolidated investigation.3 Following eleven days of hearings, ALJ George M. Kashi, who succeeded ALJ Harnish, issued a Recommended Decision disallowing approximately $82 million of PECOs ECR request.

Upon review of exceptions, the Commission reduced the disallowance to $73 million, of which approximately $58 million is attributable to the five outages here at issue. We will review seriatim the factual scenario and legal conclusions for each outage.

1983 Salem 1 Outage

This outage occurred on February 25, 1983, and ended May 20, 1983. While attempting to bring the unit up to power, Public Service Electric & Gas Company (PSE&G), the operator of Salem l,4 experienced certain mechanical difficulties which necessitated a shutdown. Two automatic reactor scram breakers, designed to shut down the unit automatically in such circumstances, foiled.5 The unit was shut down manually, but the automatic shutdown failure went undetected until three days later, when the reactor scram breakers again failed. Based on these two unprecedented incidents, the Nuclear Regulatory Commission (NRC) in[26]*26stituted an investigation and ultimately found that the outage was caused by inadequate maintenance and supervisory practices.6 On April 29, 1983, the NRC authorized PSE&G to restart Salem 1, but further delays occurred due to shellfish infestation found in certain cooling water lines.

In a lengthy analysis, the PUC denied replacement power costs based on its finding that PSE&G had failed to exercise “the high degree of care” which it determined was required of á public utility in the operation of a nuclear generating facility. PUC opinion, pp. 54-56.

PECOs principal contention is that the PUC erroneously adopted a standard of review equivalent to the strict standard applied by the NRC. PECO further argues that under a properly applied “prudence” standard, substantial evidence supports its position that reasonable procedures were . followed and prudent choices were made to maintain the units and to minimize the length of the outage, thereby reducing the necessity of purchasing replacement power.7

The PUCs authority to review the internal management decisions of a utility company in a rate proceeding [27]*27is limited. It may not interfere with such decisions unless it finds an abuse of the utility’s managerial discretion. National Fuel Gas Distribution Corp. v. Pennsylvania Public Utility Commission, 76 Pa. Commonwealth Ct. 102, 464 A.2d 546 (1983). Such abuse must be determined on the basis of what the utility’s management knew or should have known at the time of the decision at issue. Id. Judgment by hindsight is prohibited. Pittsburgh v. Pennsylvania Public Utility Commission, 370 Pa. 305, 88 A.2d 59 (1952).

In formulating its standard of review, the PUC stated:

In the case of nuclear plants, in particular, the high degree of care imposed upon PECO under the NRC standards, in our opinion, are [sic] equally applicable to the degree of care required of PECO under the reasonable standard or prudency [sic] lor rate determination purposes. . . . The very magnitude of the horrendous cost, relatively speaking, of replacement power in the event of a nuclear generation outage, which PECO claims its customers should bear, compels the conclusion that PECO, under the reasonable person doctrine or standard, must operate its generation with a high degree of care. We conclude that a reasonable person operating a nuclear generation plant would in fact operate the plant with a high degree of care in order to minimize the necessity of purchasing costly replacement power. This degree of care is closely akin to the highest degree of care as generally understood to apply in certain areas of negligence law.

PUC opinion, p. 16.

Pursuant to its authority to ensure the safe operation of nuclear facilities and to address the tremendous risks [28]*28nuclear facilities pose to the public health, safety and welfare, the NRC requires that plant operators exercise a high degree of care in designing, maintaining and operating all aspects of a facility. However, we believe that this heightened standard of care which the PUC attempts to extract from the field of tort law is not applicable in a utility rate proceeding. See Florida Power Corp. v. Public Service Commission, 424 So.2d 745 (Fla. 1982).

The primary purpose of rate proceedings is not to insure public safety but to regulate the economic relationship between a utility and the public and to protect the public from unreasonably high utility costs. We discern an incompatibility of standards between the strict NRC requirement of a high degree of care as to plant safety and an equally high PUC standard as to the minimization of replacement power costs. The simultaneous imposition of these two standards would, in effect, require the utility to practice flawless safety techniques while optimizing, almost absolutely, production capacity. Such a stringent dual standard approaches that of strict liability, a principle far removed from the standard of imprudence previously enunciated by this Court. See National Fuel Gas Distributing Corp.

Therefore, we hold that in a rate proceeding involving the ongoing operation of a nuclear facility, the utility is required to demonstrate only that it did not abuse its managerial discretion, i.e., that its decisions as to optimizing energy production within federal regulatory constraints were reasonable and prudent given the facts known to it at the time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gulf States Utilities v. PSC
578 So. 2d 71 (Supreme Court of Louisiana, 1991)
Pennsylvania Public Utility Commission v. Philadelphia Electric Co.
561 A.2d 1224 (Supreme Court of Pennsylvania, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
538 A.2d 98, 114 Pa. Commw. 22, 90 P.U.R.4th 560, 1988 Pa. Commw. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-electric-co-v-pennsylvania-public-utility-commission-pacommwct-1988.