Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission

629 A.2d 221, 157 Pa. Commw. 150, 1993 Pa. Commw. LEXIS 437
CourtCommonwealth Court of Pennsylvania
DecidedJuly 15, 1993
DocketNos. 2742, 2755 C.D. 1992
StatusPublished
Cited by3 cases

This text of 629 A.2d 221 (Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, 629 A.2d 221, 157 Pa. Commw. 150, 1993 Pa. Commw. LEXIS 437 (Pa. Ct. App. 1993).

Opinion

PELLEGRINI, Judge.

West Penn Power Company (West Penn) and two of its large industrial customers, Armco Advanced Materials Corporation and Allegheny Ludlum Corporation (Industrials), have filed consolidated appeals from an order of the Pennsylvania Public Utility Commission (PUC) adopting from North Branch Energy Partners, L.P. (North Branch) rather than from West Penn, the recalculation of avoided cost as of October 15, 1987, relative to the purchase of power by West Penn from the Burgettstown Project.

As with most cases involving purchase power agreements, this appeal has a long history with unexpected twists and turns. It arises as a result of the remand order we issued in Armco Advanced Materials Corporation and Allegheny Ludlum Corporation, et al. v. Pennsylvania Public Utility Commission (Nos. 2090 and 2097 C.D.1989, filed September 7, [153]*1531990), petition for allowance of appeal denied, No. 31 W.D. allocator Docket 1990 (November 19,1991), petition for reconsideration denied, (February 3, 1992) {Burgettstown I). In that case, North Branch proposed to build and operate a qualifying cogeneration facility (QF)1 in Robinson Township, Washington County (Burgettstown Project), capable of providing up to 80 megawatts (MW) of power for 33 years. The QF would be fueled by coal waste located at the project site.

In 1985, North Branch began “serious negotiations” with West Penn to sell it capacity from its proposed power plant. Negotiations continued for more than two years, and on October 15, 1987, the parties executed an electric energy purchase agreement (EEPA). That agreement provided that the avoided cost rate would be 3.6 cents per kilowatt hour (kwh) based upon West Penn’s avoided cost as of October 6, 1986, also the time of serious negotiations between the parties, with an expected in-service date of October, 1991. West Penn’s decision to enter into the EEPA was based on its future anticipated need to purchase electric power, as determined by West Penn’s parent company, the Allegheny Power System (APS).

On January 5, 1988, West Penn filed a petition with the PUC requesting approval of the EEPA and of rate recovery firom its ratepayers. The petition also requested that the PUC provide notice and a comment period to satisfy the due process rights of ratepayers. The Industrials filed a petition to intervene arguing that the EEPA should not be approved because the avoided cost rate was excessive. Without providing for the requested notice or a comment period, the PUC issued an order on September 29, 1988, approving the EEPA based on West Penn’s avoided cost calculated at the time of serious negotiations on October 6, 1986, and authorizing rate recovery of costs.

[154]*154After the PUC entered its order, this court in Barasch v. Pennsylvania Public Utility Commission, 119 Pa.Commonwealth 81, 546 A.2d 1296, reargument denied, 119 Pa.Commonwealth Ct. 81, 550 A.2d 257 (1988), petition for allowance of appeal denied, 523 Pa. 652, 567 A.2d 655 (1989) (Milesburg I), held that before the PUC could approve a contract for a utility’s purchase of power from a QF which involved substantial payments for such capacity, due process required that the utility’s customers be provided with notice of the proceedings and an opportunity to be heard because substantial property rights were involved.

Pursuant to our holding in Barasch, the PUC withdrew its order, consolidated several appeals regarding other similar projects2 and heard the Burgettstown Project approval petition. Subsequently, North Branch filed a petition requesting a modification of the EEPA, stating that because of delays in the approval petition, it would not be able to meet the existing financing closing date of October 1, 1989. North Branch requested the PUC to modify the EEPA by setting the closing date as six months from the date of a final order of the PUC in the proceeding and adjusting other milestone dates accordingly. The modification petition also requested an increase in the agreed upon avoided cost of 3.6 cents/kwh to 4.65 cents/ kwh based on the change of the in-service date from October of 1991 to January of 1993 due to litigation delays.

At the hearings, the Administrative Law Judge (ALJ) bifurcated the proceedings into two phases. Phase One concerned issues relating to the capacity rates to be paid to North Branch, and Phase Two concerned issues raised by North Branch’s modification petition. The ALJ issued a recommended decision approving the capacity rate of 3.6 cents/kwh based upon West Penn’s avoided cost as of October 6, 1986, the time of serious negotiations between the parties.

As to the Phase Two issues, the ALJ recommended that North Branch’s modification petition be denied because, while the delays caused by the litigation were not foreseen, the [155]*155parties had voluntarily agreed to various risks in the original negotiations and in the EEPA.3 By order dated September 29, 1989, the PUC adopted the ALJ’s recommendations as to Phase One issues approving the EEPA between West Penn and North Branch and recovery of costs through the energy cost rate at the time of serious negotiations. However, the PUC reversed the ALJ’s recommendation and granted North Branch’s modification petition, stating that if it were denied, the EEPA would expire by its own terms on October 1, 1989, and would send the erroneous message to those opposing future QFs that they could win by default merely by the passage of time. Because North Branch had previously withdrawn its request for an increase in its avoided cost, the PUC did not address that issue.

The Industrials filed an appeal with this court from the PUC’s decision. They argued that the PUC’s policy of calculating avoided costs as of the time of serious negotiations was invalid pursuant to 18 C.F.R. § 292.304(d), which required avoided cost to be calculated at the time a legally enforceable obligation was incurred. Further, due to tax changes occurring between 1986 and 1987, the payment to North Branch should be modified to reflect those changes. West Penn also argued that the PUC had improperly extended the milestone dates for the Burgettstown Project and the EEPA had expired by its own terms.

We determined that the PUC had properly exercised its authority in ordering a modification of the contract milestone dates.4 We also agreed that avoided cost was to be calculated [156]*156as of the time that a legally enforceable obligation was incurred by North Branch to deliver capacity to West Penn, and that date was October 15, 1987, when the EEPA was signed. We then issued an order remanding the case to the PUC to make a new calculation of avoided cost using factors in existence at the time the EEPA was executed rather than at the time of serious negotiations.5

Pursuant to our remand order, the PUC directed the parties to submit a recalculation of avoided cost using all avoided cost inputs as of the time of the legally enforceable obligation.6 Without the benefit of an evidentiary hearing, North Branch, West Penn and the Industrials submitted their recalculations to the PUC.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
664 A.2d 630 (Commonwealth Court of Pennsylvania, 1995)
West Penn Power Co. v. Pennsylvania Public Utility Commission
659 A.2d 1055 (Commonwealth Court of Pennsylvania, 1995)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
648 A.2d 63 (Commonwealth Court of Pennsylvania, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
629 A.2d 221, 157 Pa. Commw. 150, 1993 Pa. Commw. LEXIS 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armco-advanced-materials-corp-v-pennsylvania-public-utility-commission-pacommwct-1993.