Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission

664 A.2d 630, 1995 Pa. Commw. LEXIS 344
CourtCommonwealth Court of Pennsylvania
DecidedJuly 20, 1995
StatusPublished

This text of 664 A.2d 630 (Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, 664 A.2d 630, 1995 Pa. Commw. LEXIS 344 (Pa. Ct. App. 1995).

Opinion

PELLEGRINI, Judge.

West Penn Power Company (West Penn) and Armeo Advanced Materials Corporation and Allegheny Ludlum Corporation (Indus-trials), two large industrial customers of West Penn, petition for review of an order of the Pennsylvania Public Utility Commission (PUC) recalculating the amount West Penn is to pay for power from a qualifying facility1 (QF) called the Shannopin project to be built by Mon Valley Energy Corporation (Mon Valley). West Penn and the Industrials contend the amount to be paid for this power is excessive because the PUC used improper factors in calculating the amount to be paid for power produced by the Shannopin QF. The amount to be paid for QF power ordered by the PUC here was based on a recalculation of the avoided cost in response to a remand from this court, in West Penn Power Company v. Pennsylvania Public Utility Commission, 154 Pa.Commonwealth Ct. 136, 623 A.2d 383, appeals discontinued, 535 Pa. 662, 665, 634 A.2d 225, 227 (1993) (Shannopin III). We directed the PUC to make a new calculation of the amount to be paid to a QF, called the capacity cost rate, using inputs and criteria appropriate for October 15, 1987, the date of the “legally enforceable obligation” between West Penn and Mon Valley.

I.

To understand the issues in this case, it is first necessary to give the history of the Shannopin QF.2 The Shannopin QF project was one of a number of projects agreed to by West Penn so that the purchase of QF power would replace its portion of a 900 MW, coal-fired power station comprised of three units at one facility which was planned by West Penn’s parent company, Allegheny Power Systems, Inc.3 The first unit of the power station was planned to come on-line in 1995, the second and third units in 1997 and 1998. After lengthy negotiations, on October 15, 1987, the parties had entered into an electric energy purchase agreement (EEPA) for the Shannopin project. The agreement stated that Mon Valley would build the Shannopin facility to be an 80 MW output coal-fired cogeneration facility with a steam host. The EEPA had a term of thirty years and origi[633]*633nally stated Shaimopin would come on line in September of 1992. The EEPA provided that Mon Valley would receive a capacity credit of 4 cents per kilowatt hour for capacity, based on West Penn’s calculation of its avoided costs4 for a portion of the planned 900 MW power station. The avoided costs contained in the EEPA were based on West Penn’s projections at the time of “serious negotiations” with Mon Valley in September of 1986. At the same time, West Penn made agreements with two other QFs so that the three combined would replace its portion of the 900 MW plant. The anticipated power station was expected to meet West Penn’s demand for power beginning in 1995. Because of litigation delays, the Shannopin QF has not yet been built.

One of the other QF projects that was intended to replace the 900 MW power station was being developed by North Branch Energy Partners (now Washington Power Company) at Burgettstown. The EEPA for that QF project was signed on the same date the EEPA was signed for Shannopin, and the Burgettstown project would also be an 80 MW cogeneration facility. The EEPA with Burgettstown provided for a capacity cost rate of 3.6 cents per kilowatt hour and the term of the EEPA was for 33 years rather than the 30-year term of the EEPA for Shannopin. The capacity cost rate was lower for the Burgettstown project because it was expected to be in service as of October of 1991, whereas Shannopin was not expected to be in service until September of 1992, and, to a lesser extent, because it was for a three-year longer term. It too has not yet been built, and the approval of the Burgettstown project and its avoided cost rate has taken a parallel course with the litigation for the Shannopin project.

The litigation for both projects began almost immediately after the signing of the contracts, albeit initially it was amicable between the QFs and West Penn. In January of 1988, West Penn filed a petition with the PUC seeking approval of its EEPA with Mon Valley and seeking assurance that it would be able to recover all of the payments to the QF from ratepayers. After giving notice and an opportunity to be heard to West Penn’s customers,5 the PUC approved the EEPA and the pass-through of costs associated with it. On appeal, this court reversed the PUC in an unpublished decision, holding that the calculation of avoided costs under PURPA should not be based on the time of “serious negotiations” but instead should be based on the date of a “legally enforceable obligation”.6 We remanded the case for a recalculation of capacity cost rate as of October 15, 1987, the date of the contract signing. Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, No. 2091 C.D.1989, filed July 17, 1990, petition for allowance of appeal denied, No. 545 W.D. 1990, filed November 19, 1991 (Shannopin I). See also the related decision in Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, 135 Pa.Commonwealth Ct. 15, 579 A.2d 1337 (1990), affirmed per curiam, 535 Pa. 108, 634 A.2d 207 (1993), cert. denied, — U.S. —, 115 S.Ct. 311, 130 L.Ed.2d 274 (1994) (Milesburg II).7

[634]*634On remand, the PUC interpreted our decision to require recalculation of only the corporate tax rate component of the capacity cost rate, contending that it was the only component challenged by West Penn and the Industrials. The PUC directed all parties to submit proposed calculations of a capacity cost rate based on corporate tax rates in effect October 15, 1987, and for various potential in-service dates. The PUC issued an order adopting the calculations of Mon Valley and entering an order recalculating the cost rate. West Penn and the Industrials appealed.

Reversing the PUC, we held that by fixing as the “polestar” the date that the parties entered into a “legally enforceable obligation,” PURPA requires the PUC to determine as of that date whether the avoided cost agreed to by the utility and the QF was just and reasonable to ratepayers. Shannopin III, 154 Pa.Commonwealth Ct. at 145, 623 A.2d at 387. Because that determination is made on time-sensitive data and the avoided cost is set as of that date, we held that the PUC has to make the determination by reexamining all of the elements that determine the avoided cost, rather than just one element. Id. Again, we remanded for a recalculation of the amount to be paid for power produced by the Shannopin QF. It is the PUC’s calculation of the amount paid for QF power on the remand that is before us now.

II.

The amount to be paid for QF power is based on the avoided cost. The “avoided cost” essentially represents the amount of money a utility would otherwise spend if it had to construct a facility to produce needed energy or to purchase it from another source, rather than purchasing it from the QF. See 18 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GPU Industrial Intervenors v. Pennsylvania Public Utility Commission
628 A.2d 1187 (Commonwealth Court of Pennsylvania, 1993)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
579 A.2d 1337 (Commonwealth Court of Pennsylvania, 1990)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
634 A.2d 207 (Supreme Court of Pennsylvania, 1993)
West Penn Power Co. v. Pennsylvania Public Utility Commission
659 A.2d 1055 (Commonwealth Court of Pennsylvania, 1995)
West Penn Power Co. v. Pennsylvania Public Utility Commission
615 A.2d 951 (Commonwealth Court of Pennsylvania, 1992)
West Penn Power Co. v. Pennsylvania Public Utility Commission
623 A.2d 383 (Commonwealth Court of Pennsylvania, 1993)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
629 A.2d 221 (Commonwealth Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
664 A.2d 630, 1995 Pa. Commw. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/armco-advanced-materials-corp-v-pennsylvania-public-utility-commission-pacommwct-1995.