Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission

579 A.2d 1337, 135 Pa. Commw. 15, 1990 Pa. Commw. LEXIS 383
Commonwealth Court of Pennsylvania·Decided July 17, 1990·No. 2074 and 2092 C.D. 1989·Published·Cited by 20 cases

Opinion

CRAIG, Judge.

In several cases, including an earlier appeal involving this project, captioned Barasch v. Pennsylvania Public Utility Commission, 119 Pa. Commonwealth Ct. 81, 546 A.2d 1296, reargument denied, 119 Pa. Commonwealth Ct. 81, 550 A.2d 257 (1988) (Milesburg I), this court has considered various procedural questions concerning the implementation by the Pennsylvania Public Utility Commission (PUC or Commission) of the federal legislation and regulations designed to encourage the development of cogeneration and small power production from alternative energy sources.

*20 In the present appeals, the other shoe has now dropped, and the issues concern substantive limits on the power of the PUC to approve recovery from ratepayers of costs that an electric utility, West Penn Power Company (West Penn), will incur pursuant to an order of the PUC directing West Penn to enter into an electric energy purchase agreement (EEPA or contract) with Milesburg Energy, Inc. (MEI), which is a “qualifying facility” (QF) for the purposes of section 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA). 1 Armco Advanced Materials Corporation and Allegheny Ludlum Corporation (Armco/Allegheny), two large industrial customers of West Penn, and West Penn itself have appealed from the Commission’s order.

The principal questions presented are (1) whether the PUC had the authority to order payment to a QF of capacity credits 2 reflecting avoided costs calculated at a time before the QF had made a commitment to deliver capacity, where the applicable FERC regulation requires calculation of avoided costs when the QF has incurred a “legally enforceable obligation for the delivery of energy or capacity”, and (2) whether the PUC had the authority to order West Penn to enter into a new EEPA with MEI, after the first contract automatically terminated upon the expiration of a contract *21 deadline, where the new contract has a higher but as yet undetermined capacity rate, and the parties previously executed a consent decree stating that MEI would not seek or be entitled to a higher capacity rate. 3

FERC Regulations Implementing PURPA

In section 210(a) of PURPA, 16 U.S.C. § 824a-3(a), Congress created a federal statutory duty requiring that electric utilities offer to purchase electric energy from qualifying facilities and directed FERC to prescribe rules implementing that duty. In section 210(b) Congress provided that the rates for such purchases should be just and reasonable to the utility customers and in the public interest, not discriminatory against QFs, and not above the “incremental cost of alternative electric energy”, thereby assuring that the overall effect on ratepayers of the PURPA program would be neutral. In section 210(f), Congress designated state regulatory authorities, with their expertise and unique knowledge of local conditions, to be the primary enforcers of PURPA by implementing FERC’s rules.

FERC’s rule relating to state regulatory authority implementation, 18 C.F.R. § 292.401, provides in part:

(a) State regulatory authorities. Not later than one year after these rules take effect, each State regulatory authority shall, after notice and an opportunity for public hearing, commence implementation of Subpart C [relating to arrangements between utilities and QFs under section 210 of PURPA]____ Such implementation may consist of the issuance of regulations, an undertaking to resolve disputes between [QFs] and electric utilities arising under Subpart C, or any other action reasonably designed to *22 implement such subpart____[ 4 ]

FERC’s rule relating to rates for purchases by utilities from QFs is 18 C.F.R. § 292.304. In § 292.304(b)(2), FERC exercised its discretion by requiring rates equal to the utility’s full “avoided costs” (FAC), defined in § 292.101(b)(6) as “the incremental costs to the electric utility of electric energy or capacity or both which, but for the purchase from the qualifying facility or qualifying facilities, such utility would generate itself or purchase from another source.” 5

The FERC regulations permit a utility and a QF to negotiate privately and to agree to terms different from those prescribed. 18 C.F.R. § 292.301(b). Where, as in the present case, a utility and a QF negotiate a contract, but the utility conditions its obligation to purchase on preapproval from the state PUC of recovery from ratepayers of the contract costs, and submits the contract to the PUC to obtain such approval, the situation does not involve the private agreement contemplated by § 292.301(b). The state PUC’s review of such a petition appears to be proper under the § 292.401 grant of authority to take “any other action reasonably designed to implement [Subpart C of the regulations].” In such a case, the state PUC must make a calculation of FAC in order to determine whether the contract rate is at or below FAC and hence reasonable and recoverable. 6

*23 The PUC elected to implement the FERC rules by promulgating its own regulations contained in 52 Pa.Code §§ 57.-31-57.39. See 12 Pa.B. 4237 (December 11, 1982). Section 57.32(a) of the PUC’s regulations states, “The purpose of this subchapter is to implement the provisions of section 210 of the Public Utility Regulatory Policies Act of 1978____”

History

MEI and West Penn began negotiating on November 20, 1985, concerning MEI’s proposal to establish a 43 megawatt (MW) small power production facility to be fueled by bituminous coal refuse at the site of West Penn’s retired Miles-burg Power Station (Milesburg Project). West Penn asserts that it reached an oral agreement in principle with MEI on the capacity rate it would pay on May 7, 1986.

On May 27, 1986, West Penn submitted a written price offer to MEI with three different capacity rates for different in-service dates of the facility. The written offer stated that it was valid for six months only, subject to modification for changes in the facility’s characteristics, and subject to approval by West Penn’s Board of Directors.

Free access — add to your briefcase to read the full text and ask questions with AI

Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, 579 A.2d 1337, 135 Pa. Commw. 15, 1990 Pa. Commw. LEXIS 383 (Pa. Ct. App. 1990).

579 A.2d 1337 (Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Whitehall Wind, LLC v. Montana Public Service Commission
2015 MT 119 (Montana Supreme Court, 2015)
Arippa v. Pennsylvania Public Utility Commission
792 A.2d 636 (Commonwealth Court of Pennsylvania, 2002)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
677 A.2d 831 (Supreme Court of Pennsylvania, 1996)
Pa. Elec. Co. v. PA. PUBLIC UTIL. COM'N
677 A.2d 831 (Supreme Court of Pennsylvania, 1996)
South River Power Partners, L.P. v. Pennsylvania Public Utility Commission
673 A.2d 422 (Commonwealth Court of Pennsylvania, 1996)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
664 A.2d 630 (Commonwealth Court of Pennsylvania, 1995)
West Penn Power Co. v. Pennsylvania Public Utility Commission
659 A.2d 1055 (Commonwealth Court of Pennsylvania, 1995)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
648 A.2d 63 (Commonwealth Court of Pennsylvania, 1994)
Smith Cogeneration Management, Inc. v. Corp. Commission
863 P.2d 1227 (Supreme Court of Oklahoma, 1993)
Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
634 A.2d 207 (Supreme Court of Pennsylvania, 1993)
KES Brockton, Inc. v. Department of Public Utilities
416 Mass. 158 (Massachusetts Supreme Judicial Court, 1993)
GPU Industrial Intervenors v. Pennsylvania Public Utility Commission
628 A.2d 1187 (Commonwealth Court of Pennsylvania, 1993)
Allegheny Ludlum Corp. v. Pennsylvania Public Utility Commission
612 A.2d 604 (Commonwealth Court of Pennsylvania, 1992)