Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission

677 A.2d 831, 544 Pa. 475, 1996 Pa. LEXIS 1290
CourtSupreme Court of Pennsylvania
DecidedJune 19, 1996
StatusPublished
Cited by1 cases

This text of 677 A.2d 831 (Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 677 A.2d 831, 544 Pa. 475, 1996 Pa. LEXIS 1290 (Pa. 1996).

Opinion

OPINION OF THE COURT

FLAHERTY, Justice.

This is an appeal by allowance from an order of the Commonwealth Court which affirmed in part and reversed in part an order of the Pennsylvania Public Utility Commission (PUC). At issue is the proper application of a regulatory requirement that electric utilities purchase power from outside sources.

The Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. § 824a-3, encourages the use of alternative energy sources, such as cogeneration and small power production facilities, for the generation of electric power. PURPA mandates that states create legal mechanisms to compel regulated electric utilities to purchase needed power from such sources instead of building additional capacity or acquiring power from other regulated utilities. The Federal Energy Regulatory Commission (FERC) has promulgated regulations under PURPA 18 C.F.R. § 292.101 et seq. The regulations provide leeway, within the bounds of FERC requirements, for state regulatory authorities to implement PURPA. Accordingly, the PUC adopted implementation regulations. 52 Pa.Code § 57.31 et seq.

The PUC regulations denominate as “qualifying facilities” (QFs) various non-utility suppliers of electric power. 52 Pa.Code § 57.31. Electric utilities are required to enter long-term agreements to purchase power from QFs if the utilities have a demonstrated future need, within a ten-year time frame, for generating capacity that QFs can provide. 52 Pa.Code § 57.34. Compensation for QFs is limited by the regulations in accordance with a PURPA requirement that compensation not exceed a utility’s “avoided costs,” i.e., the costs that the utility would have incurred for a similar amount of electricity generated in-house or purchased from another utility. Id. [833]*833See generally 16 U.S.C. § 824a-3(b) (avoided costs).

The practical effect of PUKPA is to divert potential profits from regulated electric companies, whose earnings are largely based on the value of their owned facilities, to the owners of QFs.

In 1991, three QFs petitioned the PUC to order the Pennsylvania Electric Company (PECO), appellant herein, to enter power purchase agreements. The QFs proposed to supply varying amounts of power, the total of their proposals being for five hundred eighty megawatts of capacity. PECO opposed all three petitions on the ground that it did not have a need for such capacity.

During 1992, extensive hearings were held by an administrative law judge on the question of PECO’s future energy needs. Needs during the ten-year period commencing with the spring of 1991 were examined. Based on the record of those hearings, the PUC determined that PECO would need approximately one hundred sixty megawatts of additional capacity by the year 2000.

The PUC assigned priorities to the competing QFs based on the extent of their development, the quality of existing utility service in their locales, the viability of the various proposals, and the sequence in which the QFs filed their petitions with the PUC. PECO was then directed to enter long-term purchase agreements with two of the QFs, namely LG & E Energy Systems, Inc. (LG & E) and American Power Corporation/CMS Generation Company (American/CMS). LG & E and Ameriean/CMS were to provide eighty megawatts of capacity apiece. The PUC specified that if either of these QFs failed to enter agreements with PECO then a third QF, Cambria Partners, would be substituted.

An appeal was taken to the Commonwealth Court. That court affirmed the PUC’s decision in most respects, but reversed in part and remanded for a recalculation of the avoided costs that determine compensation payable to the QFs.

At issue in the present appeal is the proper time for determining PECO’s needs and avoided costs for additional capacity. PECO asserts that these are to be determined as of the date when a QF incurs a “legally enforceable obligation” to supply power. PECO further asserts that none of the petitioning QFs ever incurred such obligations. Hence, according to PECO, no determination of needs and avoided costs should have been made by the PUC.

The PUC ruled that capacity needs and costs were to be determined in proximity to March 21, 1991. That was when the first of the three QFs filed a petition asking the PUC to order PECO to purchase capacity. The other two QFs filed petitions soon thereafter.

The date selected for evaluation of need and cost factors is significant, for it limits the range of evidence that the PUC will consider. For example, the PUC, in concluding that PECO would need at least one hundred sixty megawatts of additional capacity, relied on PECO’s 1991 Annual Resource Planning Report (ARP) estimate of capacity needs. PECO contends that developments after publication of the 1991 ARP substantially reduced or eliminated the need for additional capacity. Such developments were described in PECO’s 1992 ARP, which was filed in the spring of 1992 after proceedings to determine PECO’s energy needs had commenced. The PUC declined, however, to consider the 1992 ARP, reasoning that capacity needs were to be determined as of the time when proceedings were initiated, namely, the spring of 1991.1 PECO claims that the PUC, [834]*834by ignoring the 1992 ARP and other post-1991 evidence of reduced capacity needs, grossly overestimated the need for additional capacity. It is further asserted that, because PECO’s costs are passed directly through to ratepayers, ratepayers will ultimately bear the burden of paying for this unneeded capacity.

PECO’s argument that capacity needs and costs are not to be determined unless a QF has incurred a legally enforceable obligation to supply power is based on regulatory requirements that were analyzed in Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission, 135 Pa.Cmwlth. 15, 579 A.2d 1337 (1990), aff'd. per curiam, 535 Pa. 108, 634 A.2d 207 (1993) (Milesburg II) (per curiam affirmance being unanimous in part and by an equally divided court in remaining part), cert. denied, — U.S. —, 115 S.Ct. 311, 130 L.Ed.2d 274 (1994).

Milesburg II focused on a FERC regulation by which QFs are provided with options as to the manner in which they can sell energy or capacity to electric utilities. Those options, set forth in 18 C.F.R. § 292.304(d), are as follows:

(d) Purchases “as available” or pursuant to a legally enforceable obligation. Each qualifying facility shall have the option either:
(1) To provide energy as the qualifying facility determines such energy to be available for such purchases, in which case the rates for such purchases shall be based on the purchasing utility’s avoided costs calculated at the time of delivery; or
(2) To provide energy or capacity pursuant to a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pa. Elec. Co. v. PA. PUBLIC UTIL. COM'N
677 A.2d 831 (Supreme Court of Pennsylvania, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
677 A.2d 831, 544 Pa. 475, 1996 Pa. LEXIS 1290, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-co-v-pennsylvania-public-utility-commission-pa-1996.