Smith Cogeneration Management, Inc. v. Corp. Commission

863 P.2d 1227, 1993 WL 469112
CourtSupreme Court of Oklahoma
DecidedDecember 9, 1993
Docket78041
StatusPublished
Cited by38 cases

This text of 863 P.2d 1227 (Smith Cogeneration Management, Inc. v. Corp. Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith Cogeneration Management, Inc. v. Corp. Commission, 863 P.2d 1227, 1993 WL 469112 (Okla. 1993).

Opinion

KAUGER, Justice.

Three issues are presented: 1 1) whether Corporation Commission Order Nos. 358343 and 358913 violate federal or state law and whether the orders are supported by substantial evidence; 2) whether the Corporation Commission has subject matter jurisdiction to review reserve margins 2 and whether it exceeded its authority in doing so; and 3) whether the Corporation Commission’s Rule 58(h), codified as OAC 165:35 — 29—1(h), 3 is pre-empted by federal law. We find that: 1) Corporation Commission Order Nos. 358343 and 358913 do not violate federal or state law and that the orders are supported by substantial evidence; 2) The Corporation Commission has subject matter jurisdiction to review reserve margins and it did not exceed its authority in doing so; and 3) Corporation Commission Rule 58(h), codified as OAC 165:35-29-l(h), is pre-empted by the Public Utility Regulatory Policies Act of 1978. Because the Rule is pre-empted, the Corporation Commission may not require utilities and qualifying facilities to include a notice provision in approved contracts allowing reconsideration of estimated costs once a qualifying facility obligates itself to deliver power.

FACTS

This cause concerns the proposal of Smith Cogeneration Management, Inc. (Smith/appellant), to build a cogeneration plant at the Goodyear Tire and Rubber Company facility in Lawton, Oklahoma. On August 9, 1988, Smith filed an application with the Oklahoma Corporation Commission (Corporation Commission), pursuant to the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. §§ 796 and 824a-3 et seq., 4 requesting that the Corporation Commission direct Public Service Company of Oklahoma (PSO/appel-lee), 5 to enter into negotiations with Smith regarding the proposed cogeneration plant. Smith requested that the Corporation Commission: 1) review and approve the final sales agreement; 2) mediate any disputes arising during the regulatory process; 3) determine the amount of avoided cost payments 6 that PSO would be required to pay *1231 for the power generated by the proposed project; and 4) waive its Electric Rule 58(H), codified as OAC 165:35-29-l(h), 7 precluding the Corporation Commission from reopening the terms and conditions of the power sales agreement once avoided costs were determined.

On July 12, 1990, Smith filed a Motion to Disqualify the consultants/experts hired by the Corporation Commission staff (Staff), to evaluate independently the pre-filed testimony of both Smith and PSO. The hearing officer granted the motion to disqualify on July 16, 1990. On appeal, the Corporation Commission en banc reversed, and it directed the hearing officer to reserve judgment on the witness’ testimony until after the hearing officer had an opportunity to evaluate the existence of any bias or prejudice in favor of PSO. 8

The hearing on the merits began on July 23, 1990. The issues tried before the hearing officer primarily concerned Smith’s and PSO’s proposed findings regarding PSO’s present and future power needs based on PSO’s ability to obtain a supply of electricity from itself, its sister companies, and other interconnected facilities and customer demands. 9 On December 31, 1990, the administrative judge issued a report partially adopting Smith’s and PSO’s proposed findings. The hearing officer denied Smith’s claims of potential witness bias and denied PSO's proposal to prohibit Smith from filing further applications for at least four years. In addition, the hearing officer found that Rule 58(H) 10 , codified as OAC 165:35 — 29—1(h), should be waived.

Both PSO and Smith appealed to the Corporation Commission en banc. On July 3, 1991, the Corporation Commission issued Order No. 358343 partially overruling the administrative judge. It found that: 1) PSO would not need any additional capacity until 1999; 2) Smith would only be able to collect avoided energy payments until 1999, based on an after-the-fact redispatch methodology, to insure that only actual costs of fuel and heat are paid; 3) because PSO’s generation expansion plan was not subjected to a computer analysis incorporating the Corporation Commission’s findings, another analysis should be run to insure the plan is optimal; 4) any avoided capacity payments would be calculated after December 31, 1994, if the Smith cogeneration project *1232 is on-line and delivering power by that time; 5) in the event Smith is unable to deliver power by December 31, 1994, avoided capacity costs will be reviewed by the Corporation Commission subsequent to that time; 6) under these facts, Rule 58(h) should not be waived; and 7) it would be against public policy to adopt PSO’s proposition that Smith, or any other party, be prohibited from filing an application for avoided capacity payments from PSO for at least four years.

On July 15, 1991, Smith filed a motion with the Corporation Commission to reconsider and vacate. On July 29, 1991, the Corporation Commission issued Order No. 358913 (clarifying order), denying Smith’s requested relief. The briefing cycle was completed on June 1, 1992, and the cause was retained by the Oklahoma Supreme Court on March 31, 1993.

I.

THE CORPORATION COMMISSION’S ORDER NOS. 358343 AND 358913 DO NOT VIOLATE FEDERAL OR STATE LAW AND THE ORDERS ARE SUPPORTED BY SUBSTANTIAL EVIDENCE.

Smith attacks Order No. 358343 and Order No. 358913 on multiple grounds, the efficacy of which depends upon whether the orders are supported by substantial evidence. 11 Smith insists that pursuant to an August, 1988, proposal to deliver power to PSO a unilateral, legally enforceable obligation arose requiring the Corporation Commission to set avoided costs for the life of the proposed agreement. 12

The Corporation Commission staff contend that the orders are supported by substantial evidence, and that they cannot be set aside merely because the evidence is conflicting or conflicting inferences can be drawn from it. PSO argues that even if the Corporation Commission failed to set avoided costs, Smith has no legally enforceable obligation to deliver power. Both the Corporation Commission staff and PSO insist that in effect, the Corporation Commission set avoided capacity costs at $0 per kilowatt by determining that PSO did not need additional capacity until 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IOCHEM CORPORATION v. OKLAHOMA CORPORATION COMMISSION
2021 OK CIV APP 28 (Court of Civil Appeals of Oklahoma, 2021)
SPARKS v. OLD REPUBLIC HOME PROTECTION CO. INC.
2020 OK 42 (Supreme Court of Oklahoma, 2020)
KOPPITZ v. CHESAPEAKE ENERGY CORPORATION
2018 OK CIV APP 50 (Court of Civil Appeals of Oklahoma, 2018)
Koppitz v. Chesapeake Energy Corp.
421 P.3d 319 (Court of Civil Appeals of Oklahoma, 2018)
Local 514 Transport Workers Union v. Keating
2003 OK 110 (Supreme Court of Oklahoma, 2003)
Hollaway v. UNUM Life Insurance Co. of America
2003 OK 90 (Supreme Court of Oklahoma, 2003)
Chesapeake Operating, Inc. v. Burlington Resources Oil & Gas Co.
2002 OK CIV APP 125 (Court of Civil Appeals of Oklahoma, 2002)
North American Natural Resources, Inc. v. Strand
252 F.3d 808 (Sixth Circuit, 2001)
Oregon Trail Electric Consumers Cooperative, Inc. v. Co-Gen Co.
7 P.3d 594 (Court of Appeals of Oregon, 2000)
Mendus v. Morgan & Associates, P.C.
1999 OK CIV APP 137 (Court of Civil Appeals of Oklahoma, 1999)
South River Power Partners L.P. v. Pennsylvania Public Utility Commission
696 A.2d 926 (Commonwealth Court of Pennsylvania, 1997)
Mid-South Cogeneration, Inc. v. Tennessee Valley Authority
926 F. Supp. 1327 (E.D. Tennessee, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
863 P.2d 1227, 1993 WL 469112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-cogeneration-management-inc-v-corp-commission-okla-1993.