Public Service Co. v. Oklahoma Corp. Commission

688 P.2d 1274
CourtSupreme Court of Oklahoma
DecidedOctober 1, 1984
Docket55320, 55346 and 55354
StatusPublished
Cited by12 cases

This text of 688 P.2d 1274 (Public Service Co. v. Oklahoma Corp. Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Co. v. Oklahoma Corp. Commission, 688 P.2d 1274 (Okla. 1984).

Opinion

DOOLIN, Justice:

Public Service Company (PSO), a Tulsa-based public utility, applied to the Corporation Commission for a $29 million rate increase. Following hearings at which several parties intervened, the Commission issued order No. 168923 from which PSO and the intervenors appeal.

I

The initial issue to be addressed is the timing of the PSO appeal itself. The Commission order granting the increase was handed down May 7, with stipulation that it shall be stayed “for thirty (30) days or until further order of the Commission .... ” PSO filed its appeal June 2, inside the 30-day stay. The Coalition for Fair Utility Rates, Inc. (Coalition) argues there was no final appealable order on June 2, and therefore the PSO petition is fatally defective, and should be dismissed.

Earlier in its order the Commission explained its stay as follows: “It is, therefore, the finding of the Commission that the effect of this order should be stayed and the applicant given 30 days to show cause, if any, why new rates should not be implemented as ordered herein.”

It is obvious from a reading of the order that the “stay” was given to grant PSO time to submit a new rate increase application and ask that it take precedent over the rate, structure approved by the Commission. That PSO chose not to take advantage of those thirty (30) days, does not render the initial order a nonfinal, nonappealable order. See our order of September 8,1980, where we denied Coalition’s motion to dismiss PSO’s appeal on the same grounds. The Corporation Commission is not authorized to extend appeal time by postponing the effective day of its final order.

II

In its initial proposition of error, PSO compalins of the manner in which Commission treated its Northeastern generating plant No. 3. PSO used as a test year the twelve months ending June 30, 1979. No. 3 came on line six months later, shortly before the rate hearing began. PSO says it was forced to include all construction costs of No. 3 in the category of Construction Work in Progress (CWIP). However, PSO wanted to include all of these costs in its rate base because No. 3 was completed within twelve months of the test year. The Commission refused that method of calculation and instead authorized 19.1% of the CWIP to the rate base. PSO argues that as error.

The Commission said it would refuse to allow CWIP to be included in a rate base unless it had approved the construction plans.

PSO admits in its brief that “... CWIP traditionally has not been constitutionally required to be included in the rate base,” but argues that case law shows that construction completed and operating before commencement of the rate hearing, regardless of the stage of completion during the test year, must be fully considered in establishing the utility’s rate base.

PSO further admits that No. 3 was included as CWIP in its application, but only because it was forced by statute to file for a rate investigation at that time. If not for the mandate of 17 O.S. 1981, § 263, PSO said it would have waited the six months until No. 3 was completed and on line, so as to include all of No. 3’s costs in its rate base.

PSO argues that the Commission has no authority to control internal business deci *1277 sions, and it is in effect doing that by-refusing to approve construction costs in a rate base unless it first approved the construction plan itself.

In Oklahoma Gas & Electric Co. v. Corporation Commission, 543 P.2d 546 (Okla.1975), we said:

“... the Corporation Commission is vested with the power to regulate and supervise the operation, management and conduct of the business of utilities under its jurisdiction, insofar as its public duties and obligations are concerned, but does not empower the Commission with such powers concerning the internal operations and management of such utilities to the extent that the Corporation Commission has the authority to prohibit the construction of the proposed project by O G & E.” (Emphasis added).

In the above cited case, we also quoted with approval a passage from Lone Star Gas Co. v. Corporation Commission, 170 Okla. 292, 39 P.2d 547 (Okl.1934):

“To give an illustration of what we mean. The Commission had no power to prohibit the unification of the companies involved herein, and has no power to dissolve their relationship. It had no power of inspection or approval of the contracts between the companies. But now that such contracts are made and are put forward as establishing certain rights upon the part of the contracting parties, the Commission may ascertain their effect upon the public rights and approve, modify, or reject such effect, if found to be unreasonable, unfair, or prejudicial.” (Emphasis added).

As applied to the case before us, the Commission has no power to demand prior approval of construction plans for a' new plant, but once it is built, the Commission is empowered to ascertain its effect upon the public rates. That is precisely what the Commission did here. It attempted to calculate the use by test year and customers of the increased capacity, and arrived at the 19.1% figure, 1 and so allowed 19.1% of the costs as CWIP in the rate base. Neither the Commission, nor PSO, nor for that matter either of the interve-nors, can cite Oklahoma authority governing this type of utility rate application procedure. They do, however, point to other states which have handled it.

PSO cites two cases which are distinguished. In Kansas Gas & Electric Co. v. State Corporation Commission, 218 Kan. 670, 544 P.2d 1396 (1976), there is no indication why the Kansas Commission initially authorized only two-thirds of the cost of a new generating plant to be added to the rate base. Two months later it granted the other one-third. The court found the two-thirds/one-third designation arbitrary and without authorization of law. There is an indication the Commission determined the plant was only partially used and required to meet demands.

A similar case, also cited by PSO, is Latourneau, et al. v. Citizens Util. Co., 125 Vt. 38, 209 A.2d 307 (1965), cited in Kansas Gas, supra. The Vermont Commission granted only fifty percent of the cost of a new plant to be included in the rate base because it determined that only fifty percent of its capacity could be presently used. The Vermont court, in allowing 100 percent of the construction costs (CWIP) in the rate base, said it “recognizes that business judgment must be employed to anticipate future needs and that this judgment cannot be arbitrarily interfered with.”

Neither the Kansas nor the Vermont case notes whether its plant was on line during the test year. Such is not the case here as No. 3 was not completed, much less on line, when the rate increase application was made.

More on point with our fact situation is Re Arizona Pub. Service Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SIERRA CLUB v. CORPORATION COMMISSION
2018 OK 31 (Supreme Court of Oklahoma, 2018)
And Okla. Energy Results LLC. v. Corp. (In re Okla. Gas & Elec. Co.)
417 P.3d 1196 (Supreme Court of Oklahoma, 2018)
Smith Cogeneration Management, Inc. v. Corp. Commission
863 P.2d 1227 (Supreme Court of Oklahoma, 1993)
Northeast Okl. Elec. v. Corp. Com'n
808 P.2d 680 (Supreme Court of Oklahoma, 1991)
French Petroleum Corp. v. Oklahoma Corp. Commission
1991 OK 1 (Supreme Court of Oklahoma, 1991)
Turpen v. Oklahoma Corp. Commission
769 P.2d 1309 (Supreme Court of Oklahoma, 1989)
Lease Lights, Inc. v. Public Service Co. of Oklahoma
849 F.2d 1330 (Tenth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
688 P.2d 1274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-co-v-oklahoma-corp-commission-okla-1984.