Kansas Gas & Electric Co. v. State Corporation Comm.

544 P.2d 1396, 218 Kan. 670, 1976 Kan. LEXIS 318
CourtSupreme Court of Kansas
DecidedJanuary 24, 1976
Docket47,832
StatusPublished
Cited by29 cases

This text of 544 P.2d 1396 (Kansas Gas & Electric Co. v. State Corporation Comm.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Gas & Electric Co. v. State Corporation Comm., 544 P.2d 1396, 218 Kan. 670, 1976 Kan. LEXIS 318 (kan 1976).

Opinion

The opinion of the court was delivered by

Kaul, J.:

This appeal stems from an application filed by appellee, Kansas Gas and Electric Company (hereafter referred to as KG&E) with the State Corporation Commission (hereafter referred to as the commission) seeking an increase in electricity *671 service rates. The crux of the controversy centers around the commissions exclusion from KG&E’s rate base one-third of its interest in a new electric generating facility, which is referred to as the La Cygne plant.

The La Cygne plant is a jointly-owned facility. One-half is owned by KG&E and the other one-half is owned by the Kansas City Power and Light Company (hereafter referred to as KCP&L). The cost of operation is equally shared by the two companies and the generating capacity is for practical purposes equally apportioned.

KG&E filed its application on August 31, 1973, seeking a rate increase amounting to approximately 13.5 million dollars. The commission docketed the application as No. 99,486-U and hearings were held, commencing January 28, 1974, and running through February 1, 1974. On March 29, 1974, the commission entered its order granting a rate increase of approximately 8.3 million dollars, the difference resulting from the allocation of only sixty-six and two-thirds percent of KG&E’s interest in the La Cygne plant to rate base. KG&E’s motion for rehearing was denied.

Thereafter, on May 14, 1974, KG&E filed its notice of appeal with the district court of Neosho County. The relief requested was that those portions of the commission’s order which excluded thirty-three and one-third percent of KG&E’s interest in the La Cygne plant be found to be unlawful, unreasonable, arbitrary and confiscatory and be set aside.

On October 14, 1974, the district court set aside the commission’s order and ordered that KG&E’s full investment in the La Cygne plant be included in the rate base and that appropriate rates be filed with the commission giving effect to the district court’s judgment.

The court rested its decision on two propositions; one that the commission’s order was not authorized by statute; and two that it was not supported by any evidence. The court specifically found there was no evidence to support the commission’s order allocating only sixty-six and two-thirds percent of the utility’s investment in the La Cygne facility. The court further stated that it was unable to find any legal authority, and that none was cited to it, enabling the commission to ascertain the value of a utility’s property and then apply a fraction of that value for the determination of a rate base. The court concluded that:

*672 “. . . [A] generating plant is a unit and it is either used or required to be used, or not used or not required to be used, and therefore it should be included in full or excluded in full. . . .”

Thereafter, KG&E submitted new rate requests as allowed by the district court and these rates were approved by the commission on October 29, 1974. However, the commission qualified its approval by ruling that the excess rates above those allowed by the commission’s original order be held by the utility subject to refund with interest in case the district court’s judgment should be reversed. KG&E objected to these refund conditions in a limited notice of compliance, but apparently the commission took no action with regard the objections. On January 21, 1975, on the grounds that the commission had taken no action on its objections, KG&E filed a motion in the district court to enforce the judgment of October 14, 1974, by compelling the commission to strike and remove the refund and interest conditions in the commission’s October 29, 1974, order.

On March 12, 1975, the district court issued its order setting aside all parts of the commission’s order, which made the new rates subject to refund and interest.

During the, pendency of these proceedings, further hearings were had before the commission in another rate increase application filed by KCP&L, KG&E’s co-owner of the La Cygne plant. The commission previously had excluded one-third of KCP&L’s half interest in the La Cygne plant from its rate base, but after hearings on November 15, 1974, the commission determined that the La Cygne plant was now operating properly, and that it could, as of December 19, 1974, be included in the KCP&L rate base. By order, dated February 12, 1975, in Docket No. 99,486-U, the commission took administrative notice of its action in KCP&L’s case and thereupon, likejwise, allowed the full KG&E portion of the La Cygne plant into KG&E’s rate base effective December 19, 1974. Consequently, the issue became narrowed to the disallowance of one-third of KG&E’s portion of the La Cygne plant in rate base for the period of time between implementation of the district court’s order and the date the plant was allowed in the rate base for both companies, a time span of approximately two months.

On October 29, 1974, the commission filed its appeal from the original judgment of the district court of Neosho County and raised the following issues in its statement of points:

“1. The District Court of Neosho County, Kansas, committed error in *673 finding that the disallowance of % of the Plaintiff’s LaCygne Plant from rate base by the State Corporation Commission was arbitrary, unreasonable, and unlawful; the court’s action being a misinterpretation of K. S. A. 66-128.
“2. The District Court of Neosho County, Kansas, committed error in determining that the exclusion of of the LaCygne Plant from Plaintiff’s rate base was not based on substantial and competent evidence, the record having been revealed that the LaCygne Plant was not operating properly and having been so acknowledged by the court.
“3. The District Court of Neosho County, Kansas, committed error in substituting its judgment for that of the State Corporation Commission upon a determination by the court that the evidence disclosed that the LaCygne Plant was not operating properly.”

We are first confronted with procedural questions raised by a motion to dismiss filed by KG&E. We have concluded, however, that in view of our disposition of the appeal it is unnecessary to decide or discuss the procedural points raised.

The statutory authority of the commission in its rate fixing function under the Public Utilities Aot (K. S. A. and K. S. A. 1975 Supp. 66-101, et seq.) and the scope of judicial review of its actions are set forth in detail in the recent case of Kansas-Nebraska Natural Gas Co. v. State Corporation Commission, 217 Kan. 604, 538 P. 2d 702 (July 17, 1975). A restatement at this early date would serve no useful purpose. It will suffice, to say that in this case we are not confronted with any question pertaining to the scope of judicial review. Neither are we concerned with the application of any particular rate base formula which is usually the question in such cases. It is uncontroverted that the plant was in operation as distinguished from being under construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams Natural Gas Co. v. State Corporation Commission
916 P.2d 52 (Court of Appeals of Kansas, 1996)
Kansas Gas & Electric Co. v. Kansas Corporation Comm'n
720 P.2d 1063 (Supreme Court of Kansas, 1986)
MAPCO Intrastate Pipeline Co. v. State Corp. Commission
704 P.2d 989 (Court of Appeals of Kansas, 1985)
Northwest Central Pipeline Corp. v. State Corp. Commission
699 P.2d 1002 (Supreme Court of Kansas, 1985)
Public Service Co. v. Oklahoma Corp. Commission
688 P.2d 1274 (Supreme Court of Oklahoma, 1984)
In Re Application of Southwestern Bell Tel. Co.
685 P.2d 304 (Court of Appeals of Kansas, 1984)
Kansas Electric Power Cooperative, Inc. v. State Corp. Commission
683 P.2d 1235 (Supreme Court of Kansas, 1984)
Oilfield Fluid Motor Carriers v. KANSAS CORP. COMM'N
677 P.2d 982 (Supreme Court of Kansas, 1984)
Union Gas System, Inc. v. KANSAS CORPORATION COMM
663 P.2d 304 (Court of Appeals of Kansas, 1983)
Ash Grove Cement Co. v. KANSAS CORPORATION COMM.
650 P.2d 747 (Court of Appeals of Kansas, 1982)
Southwestern Public Service Co. v. State
1981 OK 136 (Supreme Court of Oklahoma, 1981)
Sunflower Pipeline Co. v. State Corp. Commission
624 P.2d 466 (Court of Appeals of Kansas, 1981)
Midwest Gas Users Ass'n v. State Corp. Commission
623 P.2d 924 (Court of Appeals of Kansas, 1981)
Kansas Power & Light Co. v. State Corp. Commission
620 P.2d 329 (Court of Appeals of Kansas, 1980)
Kansas Gas & Electric Co. v. State Corp. Commission
612 P.2d 184 (Court of Appeals of Kansas, 1980)
Kansas-Nebraska Natural Gas Co. v. State Corp. Commission
610 P.2d 121 (Court of Appeals of Kansas, 1980)
Gas Service Co. v. Kansas Corporation Commission
609 P.2d 1157 (Court of Appeals of Kansas, 1980)
Sekan Electric Cooperative Ass'n v. State Corp. Commission
609 P.2d 188 (Court of Appeals of Kansas, 1980)
Southwestern Bell Telephone Co. v. State Corp. Commission
602 P.2d 131 (Court of Appeals of Kansas, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
544 P.2d 1396, 218 Kan. 670, 1976 Kan. LEXIS 318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-gas-electric-co-v-state-corporation-comm-kan-1976.