Agrilectric Power Partners, Ltd. v. Entergy Gulf States, Inc.

207 F.3d 301, 2000 U.S. App. LEXIS 6206, 2000 WL 293953
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 5, 2000
Docket99-30156
StatusPublished
Cited by5 cases

This text of 207 F.3d 301 (Agrilectric Power Partners, Ltd. v. Entergy Gulf States, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Agrilectric Power Partners, Ltd. v. Entergy Gulf States, Inc., 207 F.3d 301, 2000 U.S. App. LEXIS 6206, 2000 WL 293953 (5th Cir. 2000).

Opinion

W. EUGENE DAVIS, Circuit Judge:

This is an appeal by Agrilectric Power Partners, Ltd. (“Agrilectric”) from an order of the District Court interpreting and applying a contract between Agrilectric and Entergy Gulf States, Inc. (“Entergy”), a utility company providing electric power to consumers in Louisiana and Texas. We agree that the “regulatory-out” price adjustment clause in the contract is enforceable and affirm the district court’s judgment.

. I.

Agrilectric is a qualified facility (“QF”) under the Public Utility Regulatory Policies Act (“PURPA”), the federal statute governing this protected category of power-generating companies. PURPA requires that utilities purchase power from QFs, but states that they cannot be forced to pay more for this power than their “avoided costs,” the utilities’ cost of self-generating the power or purchasing it from other sources. 2

Originally entered into in 1984, the electricity sales contract between Agrilectric and Entergy was amended in 1987 and 1992. The 1992 contract established a 3.54 cents/Kwh flat-rate for the entire remaining ten-year contract term, but subjected this rate to a “regulatory-out” price adjustment clause. 3 This “regulatory-out” price adjustment clause limited the contract rate to an amount not greater than that which Entergy could legally recover from its retail customers and called for a price renegotiation if Entergy was legally prevented from making such a recovery.

In 1997, the Public Utility Commission of Texas (“PUCT”) and the Federal Energy Regulatory Commission (“FERC”) issued separate rulings regarding the retail rates Entergy had been charging and could continue to charge its retail customers. Holding that the flat-rate Entergy had been paying for Agrilectric’s power and passing on to its retail customers unreasonably exceeded its “avoided costs,” PUCT ordered Entergy to credit its retail customers for these overpayments. For similar reasons, FERC ordered that En-tergy could not make future recoveries after July of 1997 from its retail customers of amounts Entergy had been overpaying for Agrilectric’s energy.

In accordance with the contract’s “regulatory-out” price adjustment clause, Enter-gy contacted Agrilectric to recover retroactive reimbursements for past wholesale *303 electricity overpayments PUCT had ordered Entergy to credit its Texas retail customers and renegotiate the contract’s wholesale electricity rate consistent with FERC’s limitation on future retail utility rates. Agrilectric, however, refused to comply with either request. Consequently, in August of 1997, Entergy unilaterally reduced the price it was paying for Agri-lectric’s power to bring the wholesale electricity rate in line with the amount it was able to recover from its retail customers as per their “regulatory-out” price adjustment clause.

Agrilectric filed suit for declaratory relief and specific performance in the district court. Specifically, Agrilectic requested that the contract be enforced without the “regulatory-out” price adjustment clause, that its rights and obligations be declared under its interpretation of the contract, and that Entergy be ordered to abide by the contract’s 3.54 cents/Kwh flat-rate pricing provision. In response, Entergy filed a counterclaim, alleging that Agrilectic breached the contract by refusing to adjust the price in accordance with the “regulatory-out” price adjustment clause as triggered by the PUCT and FERC rulings. Entergy sought specific performance of this clause and over $2 million in damages, the amount it claims it suffered as a result of the breach.

The district court ruled that Agrilectric had breached the contract by refusing to adjust the price pursuant to the “regulatory-out” price adjustment clause. In a Supplemental Memorandum Ruling and Judgment, the court dismissed Agrilectric’s claims and awarded damages to Entergy in the amount of $1.9 million plus interest.

II.

In this appeal, Agrilectric argues that the electricity sales contract’s “regulatory-out” price adjustment clause is unenforceable and federally preempted by PURPA and its associated regulations. The gravamen of its argument is that QFs and utilities are restricted from including “regulatory-out” price adjustment clauses in their wholesale power sales contracts because such price adjustment provisions give state regulatory agencies the power to encroach on the federally preempted ambit of wholesale power rates between such parties. This argument is directly contradicted by PURPA, the regulations promulgated under its authority, and cases applying these laws to wholesale electricity contracts with similar “regulatory-out” price adjustment clauses.

While PURPA establishes that regulatory agencies may not alter wholesale price terms in contracts between QFs and utilities, see Freehold Cogeneration Assoc., L.P. v. Board of Regulatory Commissioners of New Jersey, 44 F.3d 1178 (3d Cir. 1995), the PUCT and FERC rulings in this case only address Entergy’s retail electricity rates, an area in which their authority has not been federally preempted, see Hopewell Cogeneration Limited Partnership v. State Corp. Comm., 249 Va. 107, 453 S.E.2d 277 (1995). Neither the PUCT nor FERC ruling purports to regulate the wholesale electricity rate paid by Entergy to Agrilectric. Instead, both directives simply declined to permit Entergy to pass through charges to its retail customers that these agencies deemed excessive. The only effect these orders had on Agri-lectric’s wholesale contract with Entergy was a derivative one, which Agrilectric felt through the “regulatory-out” price adjustment clause that Agrilectric freely agreed to in its 1992 contract with Entergy. PURPA and its regulations explicitly give QFs and utilities the freedom to voluntarily contract around these restrictions and agree to whatever other rates, terms, and conditions they prefer 4 , and, as a result, in *304 no way prohibit the “regulatory-out” price adjustment clause in this contract.

While Agrilectric asserts that similar “regulatory-out” price adjustment clauses have been rejected by the courts, the cases it presents for this proposition fail to support its argument. 5 In particular, during oral argument, Agrilectric’s counsel brought the recent case North American Natural Resources v. Michigan Public Service Commission, 73 F.Supp.2d 804 (W.D.Mich.1999), to the panel’s attention. While the district court in this ease did overturn a state’s retail price regulation altering wholesale electricity rates via a “regulatory-out” price adjustment clause similar to the one at issue in this appeal, the ruling was based on a finding that the state order threatened to deprive the QF of a rate equivalent to the utility’s full “avoided costs,” which PURPA entitles QFs to receive. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
207 F.3d 301, 2000 U.S. App. LEXIS 6206, 2000 WL 293953, Counsel Stack Legal Research, https://law.counselstack.com/opinion/agrilectric-power-partners-ltd-v-entergy-gulf-states-inc-ca5-2000.