Hopewell Cogeneration Ltd. Partnership v. State Corp. Commission

453 S.E.2d 277, 249 Va. 107, 1995 Va. LEXIS 5
CourtSupreme Court of Virginia
DecidedJanuary 13, 1995
DocketRecord Nos. 940885-940888, 940901 and 940902
StatusPublished
Cited by8 cases

This text of 453 S.E.2d 277 (Hopewell Cogeneration Ltd. Partnership v. State Corp. Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hopewell Cogeneration Ltd. Partnership v. State Corp. Commission, 453 S.E.2d 277, 249 Va. 107, 1995 Va. LEXIS 5 (Va. 1995).

Opinion

JUSTICE LACY

delivered the opinion of the Court.

In this utility rate case appeal, we consider whether the State Corporation Commission properly eliminated certain expenses associated with the purchase of electric power from the rate base of Virginia Electric and Power Company (Virginia Power), thereby disallowing recovery of those expenses through the rates charged the utility’s electric customers.

On May 29, 1992, Virginia Power filed an application to increase its electric rates by an amount which would produce total annual operating revenues of $3,362,002,000. The application was divided into three phases with hearings held on each phase. Phase III addressed the expenses at issue here. The disputed expenses are a component of the amounts Virginia Power pays for electric power purchased from non-utility generators.

Utility purchases of electric power from non-utility generators are required by the Public Utility Regulatory Policies Act of 1978 (PURPA). 16 U.S.C. § 824 (1985). The rate a utility pays a non-utility generator for purchased power is regulated, at least in part, by federal statute and regulations. The rate must be just and reasonable, may not discriminate against small power producers, and may not exceed the “incremental cost to the electric utility of alternative electric energy.” 16 U.S.C. § 824a-3(b) (1985); 18 C.F.R. § 292.304(a) (1994). The “incremental cost” is the amount the utility saves by not constructing new power gener *111 ation facilities, 16 U.S.C. § 824a-3(d) (1985), 18 C.F.R. § 292.101(b)(6) (1994), and is generally referred to as the utility’s “avoided cost.”

Avoided cost rates cannot be calculated with precision. They depend on a number of assumptions, data inputs, estimates, and calculations. Recognizing the variables inherent in determining this type of rate, the Federal Energy Regulatory Commission (FERC) adopted regulations to guide such determinations. In those regulations, the FERC determined that, where the rate is based on estimates of the avoided costs over the life of the contract, the rate does not violate federal standards if it differs from the avoided costs at the time of the power’s actual delivery. 18 C.F.R. § 292.304(b)(5) (1994). The FERC also concluded that, although the supply characteristics affecting the avoided costs may vary among generators, without standardized rates, the transaction costs associated with determining individualized rates for small power producers could make the program uneconomic for these generators. Order No. 69, Docket No. 79-55, FERC Statutes and Regulations, Regulations Preambles 1977-1981, ¶ 30,128 at 30,878 (1980). Consequently, the regulations require the states to adopt standardized avoided cost rates that non-utility generators with design capacities of 100 kilowatts or less can utilize. 1 18 C.F.R. § 292.304(c) (1994). Finally, the states were directed to develop rules to implement PURPA and its regulations. 16 U.S.C. § 824a-3(f)(1) (1985).

In 1980, the State Corporation Commission began developing a methodology for calculating avoided costs for use in establishing the required standardized avoided cost rates for small power generators. These standardized rates were approved for Virginia Power in its Schedule 19. Implementation of Federal Rules concerning Cogeneration (and Small Power Production Facilities Pursuant to § 210 of the Public Utility) Regulatory Policies Act of 1978 for Virginia Electric and Power Company, Case No. PUE800102, 1983 S.C.C. Ann. Rep. 345 (Jan. 11, 1983). From its inception, the methodology used for Schedule 19 rates included a component based on a utility’s liability for gross receipts taxes *112 (GRT). The methodology and rates have been periodically reviewed and refined but have always included the GRT factor.

In 1992, in a proceeding reviewing the Schedule 19 rates, the staff of the Commission concluded that including a GRT factor as part of the utility’s avoided cost was in error. The utility’s GRT liability could not be avoided by purchasing, rather than generating, electric power. These taxes would always be paid by the utility based on its gross revenues. Therefore, amounts included in the avoided cost calculation based on GRT were not, and could never be, properly included in the “avoided” or “incremental” cost as defined by federal law. Consequently, in the Commission’s final order in that proceeding, the GRT portion of payments to non-utility generators was eliminated prospectively from Schedule 19 rates. Application of Virginia Electric and Power Company, Case No. PUE920060, 1993 S.C.C. Ann. Rep. 283 (Feb. 17, 1993).

In the present rate case, a GRT expense factor was identified in 58 electric power purchase contracts. The Commission staff recommended that the GRT expenses be allowed for such contracts only if the contract rate had been specifically approved by the Commission or the FERC or was governed by Schedule 19.* 1 2 3456The staff also indicated that disallowance would not be applicable to fully negotiated contracts in which no GRT component could be identified. The hearing examiner acknowledged that the GRT expense was not an avoided cost, but rejected the staffs position and recommended that the GRT expense in all contracts be allowed for ratemaking purposes.

The Commission, after considering the hearing examiner’s report and parties’ comments on that report, held that GRT ex *113 penses were not an element of avoided cost and therefore were “unnecessary and excessive.” The Commission disagreed with the hearing examiner’s recommendation regarding disallowance of GRT expenses and adopted the staffs position. In its final order entered February 3, 1994, the Commission disallowed the GRT expenses for those contracts which were not specifically ordered or approved by the FERC or the Commission, but declined to “reduce an expense which the FERC or we have reviewed, approved and explicitly ordered.”

Appeals were filed by Virginia Power and five non-utility power generators—Chesapeake Paper Products Company (Chesapeake), Hopewell Cogeneration Limited Partnership (HCLP), Enron-Richmond Power Corporation (Enron), Cogentrix Virginia Leasing Corporation (Cogentrix), and Appomattox Cogeneration Limited Partnership (ACLP). 3 The GRT expenses in the contracts between Virginia Power and these non-utility generators were within the group disallowed by the Commission. We consolidated the appeals for our review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Old Dominion Comm. for Fair Util. Rates v. State Corp.
803 S.E.2d 758 (Supreme Court of Virginia, 2017)
Potomac Edison Co. v. STATE CORP. COM'N
667 S.E.2d 772 (Supreme Court of Virginia, 2008)
GTE South Inc. v. AT&T Communications of Virginia, Inc.
527 S.E.2d 437 (Supreme Court of Virginia, 2000)
American Ass'n of Retired Persons v. Bell Atlantic-Virginia, Inc.
462 S.E.2d 702 (Supreme Court of Virginia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
453 S.E.2d 277, 249 Va. 107, 1995 Va. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hopewell-cogeneration-ltd-partnership-v-state-corp-commission-va-1995.