West Penn Power Co. v. Pennsylvania Public Utility Commission

623 A.2d 383, 154 Pa. Commw. 136, 1993 Pa. Commw. LEXIS 132
CourtCommonwealth Court of Pennsylvania
DecidedMarch 10, 1993
DocketNos. 1147 & 1148 C.D. 1992
StatusPublished
Cited by4 cases

This text of 623 A.2d 383 (West Penn Power Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Penn Power Co. v. Pennsylvania Public Utility Commission, 623 A.2d 383, 154 Pa. Commw. 136, 1993 Pa. Commw. LEXIS 132 (Pa. Ct. App. 1993).

Opinion

PELLEGRINI, Judge.

West Penn Power Company (West Penn) and Armco Advanced Materials Corporation and Allegheny Ludlum Corporation (Industrials), two large industrial customers of West Penn, appeal an order of the Public Utility Commission (PUC), recalculating West Penn’s avoided cost as being supplied power by Mon Valley Energy Company’s (Mon Valley) Shannopin plant rather than having to construct its own capacity.1 The PUC order was issued as a result of this [139]*139court’s order in Armco Advanced Materials Corporation and Allegheny Ludlum Corporation v. Pennsylvania Public Utility Commission, No. 2091 C.D. 1989, memorandum opinion filed July 17, 1990 (Shannopin I), directing the PUC to recalculate the capacity credit costs reflecting the avoided costs West Penn proposed to pay for energy purchased from Mon Valley’s Qualifying Cogeneration Facility (QF).2 The recalculation was necessary because the PUC had calculated costs at the time there were “serious negotiations” rather than at the time there was a “legally enforceable obligation” between West Penn and Mon Valley.3

The PUC interpreted our order to require recalculation of only the corporate tax rate component of the avoided cost, contending that was the only component challenged by West Penn and the Industrials and raised in Shannopin I. West Penn and the Industrials appealed that interpretation, assert[140]*140ing that they challenged the entire avoided cost calculation as evidenced by the plain language of our opinion and order purportedly requiring recalculation of all components of the avoided cost.

As with most QFs in Pennsylvania which had entered into voluntary agreements with the utilities to purchase their power, Shannopin has a long and complex legal history both before the PUC and this court. It began on September 10, 1986, when West Penn and Mon Valley agreed in principle that West Penn would purchase energy from a Mon Valley proposed Shannopin plant in lieu of West Penn building a coal-fired facility.4 Based on the avoided cost to West Penn, a proposed rate of $.04 per kilowatt hour (KWH) for the QF energy was to be charged to West Penn’s ratepayers and paid to Mon Valley.5 With the proposed capacity rate unchanged,6 [141]*141West Penn and Mon Valley entered into an agreement for the purchase of the QFs. The agreement, however, was conditioned upon the PUC’s approval. Approval was necessary to insulate West Penn from complaints that the rate of power from the plant was too high or the capacity was excess.

When West Penn filed a petition with the PUC seeking approval of the agreed-to rate recovery amounts, the Industrials opposed, arguing that the proposed rate was improperly calculated. Without a hearing, the PUC rejected the Industrials’ challenge and issued a Tentative Opinion and Order approving West Penn’s petition. However, in Barasch v. Pennsylvania Public Utility Commission, 119 Pa.Commonwealth Ct. 81, 546 A.2d 1296, reargument denied, 119 Pa.Commonwealth Ct. 115, 550 A.2d 257 (1988) (Milesburg I), we held that because the approval of an electric energy purchase agreement (EEPA) by the PUC was adjudicatory in nature and involved substantial property rights of ratepayers, due process required that a utility’s customers must be provided with notice of and an opportunity to comment on the proposed action. Relying on that decision, the PUC withdrew its Tentative Opinion and Order and consolidated the Shannopin Project petition with related West Penn/QF contract cases.

As with all the cases involving QFs, in Shannopin’s proceeding, there was an issue as to whether the avoided cost calculation should be made at the time there were “serious negotiations” (September 10, 1986) or when there was a “legally enforceable obligation” to purchase power (October 15, 1987). The PUC found that the avoided cost was to be calculated at the time there were “serious negotiations” between the utility and the QF because that was when the utility made its calculation to determine its avoided costs and whether it would enter into the agreement.

The Industrials appealed the decision of the PUC to this court, claiming that the proposed rate should be calculated at [142]*142the time there was a “legally enforceable obligation,” stating that the lower corporate tax rates in effect at the time the contract was finalized would result in a lower calculation of avoided cost. In the reported Armco Advanced Materials v. Pennsylvania Public Utility Commission, 135 Pa.Commonwealth Ct. 15, 579 A.2d 1337 (1990) (Milesburg II), we held that under FERC regulations, the time when a QF executes a contract with a utility or when it otherwise does everything in its power to create a legally enforceable obligation to deliver energy and capacity is the time when the PUC must calculate the utility’s avoided costs to determine the reasonableness of the proposed contract rates. Applying the Milesburg II holding, we directed in our Shannopin I opinion that:

The Commission calculate West Penn’s full avoided cost and corresponding capacity cost credit according to West Penn’s method and using tax rates in effect at the time Mon Valley and West Penn executed their contract, which was the first time Mon Valley had done everything in its power to incur a legally enforceable obligation to deliver energy and capacity.

Upon remand, the PUC entered an order directing that the interested parties submit recalculations of the proposed capacity rate based solely on the change in corporate tax rates that occurred between the time of “serious negotiations” and a “legally enforceable obligation.” After receiving recalculations from West Penn, Mon Valley and the Industrials, the PUC accepted the recalculation submitted by Mon Valley because it was the only recalculation that reflected changes in the corporate tax rates.7 West Penn and the Industrials recalculated the rate by updating all the compo[143]*143nents of avoided cost. This appeal followed.8

At issue in this case is whether the PUC improperly implemented our remand order in Shannopin I by only recalculating corporate tax rates as of the date there was a “legally binding agreement” and not recalculating all the other factors as of that date that make up that rate. The PUC and Mon Valley contend that it was proper for them to recalculate just the corporate tax component to determine avoided cost. They argue that in Shannopin I, that was the only component of avoided cost that the Industrials claimed changed between the time of “serious negotiations” and “binding agreement.” Because the accuracy of other components of the avoided cost were not raised in the previous appeal, they contend those components were not placed at issue and were waived. They further argue that our order in Shannopin I only requires the PUC to recalculate avoided cost by changing the corporate tax rates to reflect the rate at the time there was a legally enforceable agreement.

To the contrary, the Industrials and West Penn assert that they argued in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Armco Advanced Materials Corp. v. Pennsylvania Public Utility Commission
664 A.2d 630 (Commonwealth Court of Pennsylvania, 1995)
West Penn Power Co. v. Pennsylvania Public Utility Commission
659 A.2d 1055 (Commonwealth Court of Pennsylvania, 1995)
Hopewell Cogeneration Ltd. Partnership v. State Corp. Commission
453 S.E.2d 277 (Supreme Court of Virginia, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
623 A.2d 383, 154 Pa. Commw. 136, 1993 Pa. Commw. LEXIS 132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-penn-power-co-v-pennsylvania-public-utility-commission-pacommwct-1993.