Pennsylvania Power & Light Co. v. Pennsylvania Public Utility Commission

516 A.2d 426, 101 Pa. Commw. 370, 1986 Pa. Commw. LEXIS 2610
CourtCommonwealth Court of Pennsylvania
DecidedOctober 21, 1986
DocketAppeals, 1345 C.D. 1985, 1360 C.D. 1985, 1361 C.D. 1985 and 1464 C.D. 1985
StatusPublished
Cited by10 cases

This text of 516 A.2d 426 (Pennsylvania Power & Light Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Power & Light Co. v. Pennsylvania Public Utility Commission, 516 A.2d 426, 101 Pa. Commw. 370, 1986 Pa. Commw. LEXIS 2610 (Pa. Ct. App. 1986).

Opinion

Opinion by

Judge Palladino,

On July 27, 1984, Pennsylvania Power & Light Company (PP&L) filed Supplement No. 14 to Tariff Electric—Pa. P.U.C. No. 199, which was designed to increase PP&Ls rate levels to yield additional revenues of approximately $330 million per year, based upon a test year ending March 31, 1985. The Pennsylvania Public Utility Commission (Commission) suspended operation of the proposed rate increases and ordered that hearings be held regarding their lawfulness.

Thirty-four formal complaints were filed against the proposed rate increases. These complaints were consolidated by the Commission. Two pre-hearing conferences, nineteen days of evidentiary hearings, and six public comment hearings were conducted by an Administra *373 tive Law Judge (ALJ), who thereafter issued a Recommended Decision in which he found that PP&L was entitled to $236.2 million in additional revenues.

On April 26, 1985, the Commission entered an order approving rates calculated to produce additional annual revenues of only $120.8 million. In reaching its decision, the Commission imposed two “excesss capacity” adjustments on PP&Ls rate proposal. One adjustment disallowed all costs associated with a temporary “buyback” by PP&L of a 10% portion of Susquehanna Steam Electric Station Unit 1 (Susquehanna 1) and Unit 2 (Susquehanna 2), which PP&L had sold to Allegheny Electric Cooperative (Cooperative). The other adjustment disallowed all return on PP&Ls common equity investment in Susquehanna 2.

On May 17, 1985, PP&L filed a petition for review with this Court from the Commissions order, contending that the Commission erred by imposing the two excess capacity adjustments on the utility’s rate proposal. Cross-petitions were filed by Joyce Buehrle and Bernard King, who are customers of PP&L, and by the Eastern Penn Energy Association (Association). Cross-petitioners Buehrle and King appeal from the Commission’s order to the extent that it does not exclude from PP&L’s rate proposal all costs associated with Susquehanna 2. The Association appeals from that part of the Commissions order which addresses rate allocation; the Association contends that the method of allocation improperly favors PP&L’s residential customers at the expense of commercial and industrial customers. 1

Our scope of review is limited to a determination of whether constitutional rights have been violated, an error of law committed or whether the findings, determi *374 nations or order of the Commission are supported by substantial evidence. Cohen v. Pennsylvania Public Utility Commission, 90 Pa. Commonwealth Ct. 98, 494 A.2d 58 (1985).

A. Excess Capacity Adjustment Specific To Susquehanna 2

PP&L contends that the Commission improperly applied an excess capacity adjustment which is specific to Susquehanna 2 and which disallows all return on PP&Ls common equity investment in Susquehanna 2. In determining that there was such excess capacity on PP&Ls system, the Commission accepted the computation of excess capacity offered into evidence by its Trial Staff witness, who testified that PP&Ls peak demand of 5,284 megawatts (MW) plus a 22% reserve margin of 1,174 MW was 1,033 MW less than PP&Ls net installed capacity of 7,491 MW. In recognition of the last PP&L rate proceeding concerning Susquehanna 1 (wherein the Commission also found that PP&L had 945 MW of excess capacity), and because of “the obvious causal connection between the system excess and the introduction of [Susquehanna 2]”, the witness conservatively estimated the actual excess capacity to be 945 MW. (Commissions Opinion at p. 17).

On the basis of this evidence, the Commission determined that the appropriate adjustment for the excess capacity should be specific to Susquehanna 2, in acknowledgment of the fact that “the cause of the excess capacity on PP&Ls system is the addition of [Susquehanna 2].” (Commissions Order at p. 21). Accordingly, the Commission ordered an adjustment to PP&Ls rate proposal which denied PP&L all return on common equity investment in Susquehanna 2, until such time as PP&L can show (1) that the net benefits from Susquehanna 2 will exceed the net costs of the unit to PP&Ls ratepayers, or (2) that the capacity from Susquehanna 2 *375 is necessary for system reliability. The Commission did, however, allow PP&L to recover all reasonable operating, maintenance, and depreciation expenses of Susquehanna 2.

PP&L argues that the Commission erred in finding excess capacity on PP&Ls system, because the formula employed by the Commission does not take into account a variety of factors which impinge upon PP&Ls ability to provide reliable and economic service to its customers. Moreover, PP&L contends that the Commissions formula is inappropriate as applied to new base-load generating plants, because an excess capacity adjustment would necessarily occur whenever a utility brings a new base-load plant into service, unless the utility’s existing capacity was grossly inadequate. In the alternative, PP&L argues that, assuming there is excess capacity on its system, the adjustment for such excess should not be directed specifically to Susquehanna 2 because of the following reasons: (1) Susquehanna 2 is used and useful property, upon which PP&L is entitled to a fair return on investment; (2) an adjustment specific to Susquehanna 2 is inconsistent with the Commission’s system-wide excess capacity adjustment imposed when Susquehanna 1 was put into service; 2 (3) the adjustment is inconsistent with the Commission’s prior approval of Susquehanna 2; and (4) the adjustment foils to balance properly the interest of PP&L’s shareholders against that of PP&L’s customers.

The law concerning adjustments made to a utility’s rate base is well settled. A unit may be properly excluded from a utility’s rate base if the investment in that *376 unit is found to be a result of managerial imprudence occurring at the time the decision to invest was made. Philadelphia Electric Company v. Pennsylvania Public Utility Commission, 61 Pa. Commonwealth Ct. 325, 433 A.2d 620 (1981). It does not necessarily follow, however, that recovery of costs prudently incurred will always be allowed. Duquesne Light v. Pennsylvania Public Utility Commission, 96 Pa. Commonwealth Ct. 398, 507 A.2d 1274 (1986). Rather, the “touchstone for determining whether or not a prudently constructed unit should be included in a utility’s rate base is whether or not, during the test year involved, the unit will be used and useful in rendering service to the public.” Philadelphia Electric Company, 61 Pa. Commonwealth Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Penn Power Co. v. Pennsylvania Public Utility Commission
623 A.2d 383 (Commonwealth Court of Pennsylvania, 1993)
Office of Consumer Advocate v. Utilities Board
452 N.W.2d 588 (Supreme Court of Iowa, 1990)
Pennsylvania Power Co. v. Pennsylvania Public Utility Commission
561 A.2d 43 (Commonwealth Court of Pennsylvania, 1989)
City of Novi v. City of Detroit
446 N.W.2d 118 (Michigan Supreme Court, 1989)
Philadelphia Electric Co. v. Pennsylvania Public Utility Commission
552 A.2d 342 (Commonwealth Court of Pennsylvania, 1989)
Barasch v. Pennsylvania Public Utility Commission
540 A.2d 966 (Commonwealth Court of Pennsylvania, 1988)
Equitable Gas Co. v. Pennsylvania Public Utility Commission
536 A.2d 846 (Commonwealth Court of Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
516 A.2d 426, 101 Pa. Commw. 370, 1986 Pa. Commw. LEXIS 2610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-power-light-co-v-pennsylvania-public-utility-commission-pacommwct-1986.