Mid-South Cogeneration, Inc. v. Tennessee Valley Authority

926 F. Supp. 1327, 1996 U.S. Dist. LEXIS 7675, 1996 WL 296949
CourtDistrict Court, E.D. Tennessee
DecidedMarch 18, 1996
Docket3:94-cv-00283
StatusPublished
Cited by1 cases

This text of 926 F. Supp. 1327 (Mid-South Cogeneration, Inc. v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mid-South Cogeneration, Inc. v. Tennessee Valley Authority, 926 F. Supp. 1327, 1996 U.S. Dist. LEXIS 7675, 1996 WL 296949 (E.D. Tenn. 1996).

Opinion

*1329 FINDINGS OF FACT AND CONCLUSIONS OF LAW

JORDAN, District Judge.

This civil action came on for trial without a jury beginning on Tuesday, December 4, 1995. At the time of trial, the court had under advisement the defendant’s motion for summary judgment [doc. 12]. The court has considered the evidentiary material filed in support of and in opposition to this motion for summary judgment together with the evidence adduced at trial. The following are the court’s findings of fact and conclusions of law rendered under Fed.R.Civ.P. 52(a).

The plaintiff states three theories of recovery in its complaint. First, it claims that it is entitled to relief under the Public Utility Regulatory Policies Act of 1978 (PURPA), and specifically under 16 U.S.C. § 824a-3. The statute, in § 824a-3(a) and (b), requires electric utilities, like the defendant Tennessee Valley Authority (TVA), to purchase electric energy from qualifying small power production facilities and qualifying cogeneration facilities at non-discriminatory rates based on the purchasing utilities’ avoided costs. The term “avoided cost” is an abbreviated reference to “incremental cost of alternative electric energy,” which is defined in § 824a-3(d) to mean “the cost to the electric utility of the electric energy which, but for the purchase from such cogenerator or small power producer, such utility would generate or purchase from another source.”

The plaintiffs second theory of recovery is based on its allegation that it had a contract with the defendant TVA under which TVA agreed to purchase electric energy from the plaintiff at certain rates. The plaintiff says that the defendant breached this contract. The third theory of recovery is that the defendant caused the plaintiff to incur damages by misrepresentation.

The exhibits attached to the plaintiffs complaint, read with the complaint, show or suggest many of the pertinent facts in this case. Its principals formed the plaintiff, Mid-South Cogeneration, Inc. (Mid-South), to take advantage of business opportunities in the southeastern United States in the operation of wood-waste cogeneration facilities and small power production facilities. The power production facility (the Clinch River facility) which is a subject of this litigation came to Mid-South’s attention via a television news broadcast. The plaintiff developed a business plan to purchase the facility from a bankruptcy estate, to operate it to sell electric energy to TVA directly or through TVA’s local distributor, the Harriman Utility Board, and to operate it also to sell steam to an adjacent paper plant.

Mid-South inquired of TVA about assuming the obligations of the prior owner of this power production facility under an existing cogeneration agreement, dating from 1982. TVA responded in an April 25, 1991, letter, exhibit A to the complaint filed in this civil action. TVA rejected any proposal of an assumption of the existing cogeneration agreement, in part because Mid-South proposed an amount of output greater than that provided for by the existing agreement. The proposal of greater output from the Clinch River facility created a need, in TVA’s view, to reexamine the electrical facilities at the Clinch River facility, to ensure the safety of any connection of this facility to TVA’s electric energy transmission system.

This April 25, 1991, letter is important for its discussion of the rates which TVA might pay for Mid-South’s output at this facility:

Based on the information provided, the facility you describe would be eligible for new purchase arrangements under the current Dispersed Power Production Guidelines for purchase of up to 17,500 kW of power from the wood-waste-fired facility. In order for purchases to be made under Part C of the Dispersed Power Price Schedule CSPP (or comparable provisions of any replacement standard price schedule that might then be applicable) the contract term would need to be at least 10 years. The purchase prices for fiscal year 1991 under Part C are shown on the enclosed schedule.
The facility may qualify for other purchase arrangements involving fixed prices or levelized prices for a portion of the contract term. Prices under these arrangements *1330 would be based on TVA’s projected avoided costs over the contract term.

It is clear from this letter that as of April 25, 1991, no enforceable agreement existed between these parties.

The different pricing schemes for electric energy purchased under PURPA in effect at the time of this April 1991 letter were explained in TVA’s modified Dispersed Power Production Guidelines and Dispersed Power Price Schedule CSPP, published in the Federal Register on April 30, 1984 [see doc. 13, ex. A], Part C of the price schedule provided for a rate of 2.420 cents per kWh for onpeak kilowatthours, and for a rate of 1.750 cents per kWh for offpeak kilowatthours. It was noted in the price schedule that the differential for onpeak kilowatt hours was based in part on long-term projections of capacity cost savings; this was at least part of the reason why Part C pricing was available only for purchases of energy under contracts having terms of 10 years or longer. Put simply, TVA could afford to pay better rates under Part C because long-term contracts for electric energy enabled TVA to avoid construction and other costs associated with increasing the capacity of its system to meet long-term projected needs.

Both the guidelines and the price schedule made it clear that the Part C rates were subject to annual adjustment for changed projections of avoided energy costs and of avoided capacity costs, and were subject also to adjustment, modification, or change due to changing conditions on the TVA power system, and other power supply considerations. The guidelines provided that in an individual ease, the amounts payable might be modified to reflect costs, such as administrative costs, metering costs, and transmission line losses, incurred by the TVA electric system because of purchasing from a qualified producer under the Dispersed Power Production Guidelines.

Fixed rates for the purchase of energy over a portion of the life of a purchase contract obviously provided greater financial security to the cogenerator or small power producer. Levelized rates provided less certainty than fixed rates, but protected the eogenerator or producer to some extent from fluctuations in avoided costs determined under PURPA and applicable regulations.

Mid-South’s application to the Federal Energy Regulatory Commission (FERC) for self-certification as a qualifying small power production facility, a certified copy of which is attached to the defendant TVA’s motion for summary judgment, is dated December 30, 1991, and shows that it was docketed by the commission on December 30, 1992. Therefore, while the plaintiff was negotiating with the defendant concerning the terms under which the defendant might purchase energy from the Clinch River facility, Mid-South was not, at least technically, a qualified facility for the purposes of PURPA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
926 F. Supp. 1327, 1996 U.S. Dist. LEXIS 7675, 1996 WL 296949, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mid-south-cogeneration-inc-v-tennessee-valley-authority-tned-1996.