KES Brockton, Inc. v. Department of Public Utilities

416 Mass. 158
CourtMassachusetts Supreme Judicial Court
DecidedAugust 13, 1993
StatusPublished
Cited by6 cases

This text of 416 Mass. 158 (KES Brockton, Inc. v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KES Brockton, Inc. v. Department of Public Utilities, 416 Mass. 158 (Mass. 1993).

Opinion

Abrams, J.

The petitioners, general partners of Brockton Wood, L.P. (Brockton Wood), appeal from the disapproval by the Department of Public Utilities (department) of an electricity purchase contract between Brockton Wood and the Western Massachusetts Electric Company (WME); the department’s denial of the petitioners’ motion to intervene in the department’s contract review process; and the department’s denial of the petitioners’ motion for reconsideration. The petitioners appealed to the Supreme Judicial Court for Suffolk County; on joint motion of the parties, see G. L. c. 25, § 5 (1992 ed.), a single justice reserved and reported the case to this court. We conclude that the petitioners have no standing to appeal.

On October 5, 1988, WME issued a solicitation (REP) for bids for the competitive purchase of electricity from Qualifying Facilities (QFs), pursuant to 220 Code Mass. Regs. § 8.00 (1986) (QF regulations). On February 2, 1989, Ta-mal Development Corporation (Tamal) submitted a project proposal in response to the RFP. During October and November, 1989, Tamal provided WME further details on the proposal. On December 12, 1989, WME notified Tamal that the Tamal proposal would be included in the award group. See 220 Code Mass. Regs. § 8.05 (6) (a) (1986).

As originally bid, the project proposal was as follows: The project would be located in Assonet, inside WME’s service area; WME would purchase electricity the project generated from Tamal; the primary generating technology would be a low-BTU boiler/steam turbine generator; the primary fuel would be wood waste, supplied to Tamal by the owner of the project site, from on-site sources (under a letter of intent); the project capacity would be twenty megawatts (MW); the contract would run for twenty years from the expected in-service date of January 1, 1994; and the price had a fixed and variable component. Tamal Energy, Inc., was listed as the 100% owner of the project.

[160]*160In January, 1990, Tamal proposed to WME that the project’s generating technology be changed from wood gasifi-cation to a wood-fired stoker. WME initially rejected this change as constituting a change that would fundamentally alter the nature of the proposal. Following a department decision that WME interpreted as urging utilities to be more flexible in dealing with project developers, WME allowed Tamal to update its proposal to include the technology change, but suspended contract negotiations and recalculated the project’s score to determine whether the revised project remained in the award group. WME reranked the proposal and notified Tamal on May 10, 1990, that the proposal remained in the award group, and that contract negotiations could be reopened.

On May 15, 1990, Tamal informed WME that the project would have to be relocated to an alternative site. WME suspended negotiations pending verification of the economic feasibility of the project after the proposed changes and reranking of the project. On July 18, 1990, WME notified Tamal that the rescored project2 remained within the award group; contract negotiations resumed.

In October, 1990, WME rejected Tamal’s subsequent request to modify its pricing formula and to increase project size. In November, 1990, Tamal informed WME that Tamal intended to proceed on the bid terms and would provide a revised bid proposal; WME provided Tamal a draft contract incorporating all agreed changes.

During the first part of 1991, the parties continued to revise the proposed contract. WME repeatedly requested a revised project proposal. On July 15, 1991, WME notified Tamal that if WME did not receive an updated proposal by August 1, 1991, the project would be removed from the award group. On July 31, 1991, and during the following three weeks, Tamal informed WME of various changes in the proposed project’s ownership, capital structure, capital costs, schedule and project description. Tamal also indicated [161]*161that the project no longer had a committed long-term fuel supply. WME again suspended contract negotiations to obtain information it needed to rescore and rerank the project in light of the proposed changes. On October 9, 1991, WME notified Brockton Wood3 that the proposal remained in the award group and that contract negotiations could be resumed.

In October, 1991, Brockton Wood requested that WME accede to a reduction in project size from twenty MW to 16.9 MW. WME agreed to the change in project size. In February, 1992, KES informed WME that an alternate site had been chosen in Brockton to address environmental considerations. WME agreed to the change in site. Brockton Wood executed the electric power purchase agreement (contract) in June, 1992; WME executed the contract in July, 1992.

In September, 1992, WME submitted the contract to the department for review pursuant to 220 Code Mass. Regs. § 8.03 (2). In October and November, 1992, the department issued, and WME responded to, four information requests regarding the contract. On November 11, 1992, Brockton Wood submitted to the department comments on WME’s response to a department information request regarding an avoided-costs calculation of the Brockton Wood project pro-posai. Brockton Wood also filed a petition to intervene pursuant to 220 Code Mass. Regs. § 1.03 to present additional evidence to the department disputing some of the assump-tians that WME relied on in its cost-benefit analysis. Brock-ton Wood asked “to participate as an intervenor in this matter, and where appropriate, engage in any technical sessions or hearings, offer evidence and cross examine witnesses, present oral argument before the Department, and submit comments and briefs for the- Department’s consideration.” WME corrected its original response and commented on Brockton Wood’s earlier comments.

[162]*162On November 16, 1992, the department issued a letter decisión disapproving the contract pursuant to 220 Code Mass. Regs. § 8.03 (2), focusing on the number and significance of the changes made to the original project proposal.4 The department denied Brockton Wood’s motion to intervene that same day, thereby limiting Brockton Wood’s participation to the submissions previously filed with the department.

On December 14, 1992, the petitioners filed a petition for appeal with the Supreme Judicial Court for Suffolk County under G. L. c. 25, § 5, and a motion for reconsideration with the department; both pleadings challenged the department’s disapproval of the contract and the department’s decision to deny intervention. On January 22, 1993, Brockton Wood moved for leave to file a memorandum in support of its motion for reconsideration in the department. On March 15, 1993, on joint motion of the parties, the single justice reserved and reported the case to this court. On May 19, 1993, the department denied Brockton Wood’s mo-[163]*163tian for reconsideration, upholding its earlier decision denying Brockton Wood’s intervention on the grounds that (i) 220 Code Mass. Regs. § 8.03 (2) did not require a full G. L. c. 30A adjudicatory hearing5; (ii) Brockton Wood had no constitutional right to a full adjudicatory hearing; and (iii) the department’s review of the contract did not require process beyond what the department gave.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. Hull
D. Massachusetts, 2021
Caesars Massachusetts Management Co. v. Crosby
778 F.3d 327 (First Circuit, 2015)
Melone v. Department of Public Utilities
967 N.E.2d 596 (Massachusetts Supreme Judicial Court, 2012)
Tofias v. Energy Facilities Siting Board
435 Mass. 340 (Massachusetts Supreme Judicial Court, 2001)
Cablevision Systems Corp. v. Department of Telecommunications & Energy
702 N.E.2d 799 (Massachusetts Supreme Judicial Court, 1998)
Ginther v. Commissioner of Insurance
427 Mass. 319 (Massachusetts Supreme Judicial Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
416 Mass. 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kes-brockton-inc-v-department-of-public-utilities-mass-1993.